Free Electron Laser Commissioning/Diagnostic Meeting
Tuesday, July 30, 1996
Recorder: R. Legg
Next Meeting
- Date: August 6, 1996
- Time: 3:00 - 4:00
- Place: Test Lab Conference Room
Attendees
P. Piot, D. Douglas, J.C. Denard, D. Kehne
R. Legg, G. Biallas, K. Jordan, R. Walker and G. Krafft
Corrections to Previous Minutes
- J.C. Denard informed me that the 9 MHz micropulse frequency
suggested for tune-up mode in the last set of minutes was
not adequate for the BPM's to function. Instead the PRF for
the micropulses will be 18 MHz and the macropulses will be
reduced to 2 Hz to maintain the low average current.
Items of Discussion
- Dave D. reported on the 10/42 MeV magnet which had been suggested to phase
the cryomodule. He presented 4 plans to accomplish this.
- Crest 1-2 cavities at a time and power the dipole at 1.4 to 1.5
times the design.
- Build new extraction chicane dipoles to bend a 42 MeV beam.
- Build extra dipoles to boost the amount of bending produced.
- Phase the cavites to crest and anti-crest.
Because 2 and 3) required new magnet types to be designed, they were discounted and a
combination of 1) and 4) will be adopted particularly since Leigh didn't have
grave reservations about overpowering the dipoles by 40-50%. Dave will detail this
design after his vacation and put it on the www.
- The possibility of simultaneous longitudinal/transverse measurement after
the new ceramics are installed in November was discussed by D. Kehne.
The experiment has several issues, it needs a small beam in the chopper
to reduce the energy shear, and the use of Dave Engwall's smaller aperture
will require the beam to be focussed to close to 100 um at the slit. The solenoid
used to focus the beam has to be in front of the chopper or it will re-focus
the beam and reduce the resolution on bunchlength, but by putting it in front
of the chopper, the aspect ratio is about 5:1 and the focussing will be tricky.
Dave will do some more calculations to verify the cavity power and focussing
parameters. Geoff will work with him off-line to help firm up the mechanical
issues in the next two weeks. There will be a meeting on just this topic
next Monday at 3:30 PM in room A110.
- The cryounit pair are positioned to run at 12 MV/m and 9 MV/m. D. Kehne modeled
the effect that assymetric powering of the cavities has on emittance. He reports
that it is less than a 10% effect from the 8 mm-mR nominal for a 350 keV input
beam.
- D. Douglas said that by the inclusion of one more of the 10 MeV chicane dipoles
the dump can be designed to very good momentum resolution for phasing and a good
place for an emittance measurement. Legg, Douglas and Krafft (only ones who showed)
met to lay out the 10 MeV diagnostics. It was decided to use a QB quad to focus the
beam on an emittance slit or to compensate for dispersion, followed by a slit,
a gap monitor, the QB quads to blow up the beam on the dump face, the raster and
finally an OTR viewer to look at the slit results and to verify the raster and
blow up quads operation.
Dave Douglas will pass the DIMAD deck to George Biallas for review and mechanical
design.
New Issues
- The Transverse experiment has a three milestone schedule of
Design, Fab, and Ready-to-Use. No dates,YET...
- Modeling of lower than 10 MeV injector to account for off crest
phasing in the quarter cryounit. Kehne to look at by 10/1/96.
- K. Jordan suggested we plan to have a second gun running in the
test lab for 18-24 months to act as a spare and do further
gun tests directed toward the 1 um and UV FEL's. Court Bohn to investigate.
- D. Douglas has posted most of his technotes on the web
for perusal and links to the FEL pages. Check for requirements and
magnet information.
- D. Kehne talked to Uwe Hapeck about his student and he was very
receptive to having them stay here and perform other experiments
and work with the machine. Kevin says he thinks he has a way to
pay for his room and board. This could give us a third experimenter
for the 10 MeV test and ease around the clock coverage.
Action Items
A-37 Assymetric powering of cryounit. Kehne complete
A-38 meeting to discuss dump diagnostics Krafft complete
A-16 Average Current Measurement/Assess Far. Cup Legg complete
A-17 4-Channel BPM on the IRFEL Bohn, Denard complete
A-41 Modeling of lower than 10 MeV injector Kehne, Liu 10/1/96
A-42 2nd gun for long term tests Bohn 10/1/96
Action Items (assigned)
A-01 Update Drawing Bohn weekly
A-02 Magnet Specifications Webbed Douglas
A-04 Unit gradient precision Bohn, Liu
A-05 Injector energy precision Douglas
A-06 10 MeV dump optics Douglas
A-09 Dump Instrumentation Legg 6/04/96
A-10 Back leg diagnostic placement Douglas
A-11 Multifrequency CSR Measurements Krafft 6/04/96
A-12 How should the path length be checked? Krafft, Jordan 6/11/96
A-15 Commissioning Procedure Legg, Krafft 5/16/96
A-19 Web Documentation Krafft weekly
A-20 10->42 MeV dump Biallas
A-21 Diagnostics reviews Jordan 6/11/96
A-22 Beam dump and scaper design Wiseman 6/18/96
A-24 Beam loss Bohn
A-25 Synchrotron Light Monitors Krafft
A-26 IR Camera Plan Neil
A-27 Autosteer Plan Bohn
A-28 Transverse Effects in CSR Li
A-29 Software Planning for Longer Term Bohn
A-30 Burnthrough/Conflat Expansion Denard, Kloppel
A-32 10 MeV emittance Plan Bohn
A-33 FSD Plan Mahoney, Legg
A-34 Consistent Linac phasing plan Yunn
A-35 simultaneous transverse and longitudinal Kehne/Engwall 8/6/96
A-36 'bad' injection dipole/dump geometry. Douglas 7/30/96
A-39 report on ARR plan Legg 8/23.
A-40 post tentative commissioning strategy Legg 8/6/96
Action Items (pending)
P-01 Determine Beam Pulse structure for setup
P-02 Laser phase modulator
P-03 Slit emittance measurement
P-04 Is an energy compression scheme needed?
P-05 Devise fine-tuning procedure for buncher gradient
P-07 Diagnostics "Freeze"
P-08 How do we change energy? What is the energy range?
P-09 Do we need bunching after the module
P-10 Will the SLM monitor work to center the large beam
P-11 Calculate from Hall C data how much scatter the BPMs can take
P-12 FEL/OTR interaction question
P-13 Do we have sufficient diagnostics for emittance degradation measurements
P-14 How is the gun/laser operated?
P-15 Discussion on robustness of controls??????
P-16 Injector diagnostics in the main machine
P-18 Technote by Yunn summarizing machine impedance
P-19 Consistent linac/bunching phase sets
P-20 Lock plans (who in particular)
P-21 Save/restore plans
P-24 FEL Commissioning review
P-25 RF control sensitivities/Microphonics Diff for FEL/Pathlength effect
P-26 What if studies
P-27 Plan to measure beam loss
P-28 Scrapers: Where and How?
P-29 FEL/linac interaction
P-30 Tracking including realistic wiggler fields
P-31 What drives the vacuum spec.
P-32 Are two sextupole families enough to tune M56
P-33 Is path length feedback needed?
P-35 Coordinated ITS beam running/SRF commissioning plan
P-36 Beam power robust BPMs
P-37 42 MeV dump design and interlocking
Agenda for Next Meeting
Item Person Responsible Time
---- ------------------ ----
* Review agenda/corrections to minutes Legg 5 min.
* New issues 10 min
* Simultaneous longitudinal/transverse tests Kehne/Engwall 10 min
* BPM can design Jordan/Yunn 5 min
* 10 MeV Dump design Douglas 10 min.
* Agenda for next meeting All 5 min.