Free Electron Laser Commissioning/Diagnostic Meeting

Tuesday, June 3, 1997
Recorder: R. Legg

Next Meeting


Date: June 10, 1997
Time: 3:00 - 4:00
Place: Test Lab Conference Room

Attendees


R. Legg, C. L. Bohn, B. Yunn, J. Bennett S. Benson, R. Walker, P. Piot, G. Neil, K. Jordan D. Douglas, Q.S. Shu, G. Biallas

Addenda/Errata to Previous Minutes
-------------------------------

   
Action Priority  Items (assigned)
----------------------------------

A-15   1  Commissioning Procedure                       Legg, Krafft    5/16/96
A-19   0  Web Documentation                                             weekly
A-24  1,2 Beam loss                                     Bohn
A-30   1  Burnthrough/Conflat Expansion                 Denard, Kloppel
A-34   2  Consistent Linac phasing plan                 Yunn
A-42   2  2nd gun for long term tests			Bohn		10/1/96
A-44  1,2 Start Rui on emittance code                   Bohn            8/13/96
A-47   1  OTR beam interaction number by 		Denard		9/11
A-55   1  Laser Diagnostic Proc				Benson		11/1/96

Action Items (pending)
------------

P-05  1   Devise fine-tuning procedure for buncher gradient		Krafft/Kehne
P-08 1,2  How do we change energy? What is the energy range?		Benson
P-14  1   How is the gun/laser operated?				Benson
P-15      Discussion on robustness of controls				Legg
P-19  2   Consistent linac/bunching phase sets				Yunn
P-20  1   Lock plans (who in particular)				Johannes?
P-21  1   Save/restore plans						Benesch
P-25 1,2  RF control sensitivities/					Merminga
	    Microphonics Diff for FEL/
	    Pathlength effect
P-29  2   FEL/linac interaction						Merminga
P-30  2   Tracking including realistic wiggler fields			Douglas
P-37  1   42 MeV dump design and interlocking				Wiseman

Agenda for Next Meeting
-----------------------

                Item                              Person Responsible     Time
                ----                              ------------------     ----
    *	Review agenda/corrections to minutes	        Legg	         5 min.
    *	CSR experimental plan				Douglas		 30 min
    *   Magnetic probes					Terrell		 10 min	
    *	Agenda for next meeting		                All		 5 min.