Free Electron Laser Commissioning Meeting

Friday, 8 May 98
Recorder: C. Bohn

Next Meeting


Date: 15 May 98
Time: "0845"-0945
Place: FEL Facility Break Room

Agenda for Next Meeting


Item Person Responsible Time ---- ------------------ -------- Status of Open Action Items All 5 min Scheduling and Commissioning Program Bohn/All 50 min New Issues All 5 min

This Week's Attendees


J. Bennett, S. Benson, C. Bohn, J. Boyce, D. Douglas, F. Dylla, J. Fugitt, A. Hofler, C. Hovater, R. Lauze, R. Li, L. Merminga, G. Neil, M. Shinn, Q.-S. Shu, T. Siggins, R. Walker, B. Yunn

Closed Action Items


Items of Discussion


This week's activities centered on continued commissioning of diagnostics, including development of procedures to use them, additional difference-orbit measurements, and developing a reproducible injector-setup procedure that involves diagnostics downstream of the injector. None of these activities are complete yet, but progress was made in all of them. In addition, one shift was used to devise a BLM setup that would permit operating the Happek interferometric bunch-length monitors as well as to recheck the BLM settings for cw running. Regarding the latter, the voltage of the BLM at the straight-ahead dump was adjusted, but otherwise the existing setup looked appropriate.

One complication is a persistent drift in the rf phase of the drive laser that began to be observable about two weeks ago. The drift causes the beam properties to change concomitantly, and it must be eliminated prior to trying to lase. We believe that it was introduced as a consequence of some hardware changes in the drive-laser rf system, and we have been trying to track down the cause using well-defined test plans. At this writing (1115, 8 May 98) we still had not done so definitively, but we have suspected causes that we will check over the next few days.

C. Bohn summarized the status of the electron-beam diagnostics as follows:

As a general remark, phase-space parameters that have been measured thus far generally fall within a factor 2-3 (far less than an order of magnitude!) from those required for lasing. Of course, if all parameters were double the requirement, no lasing could happen. The point is that the data continue to suggest we're within reach but need to continue fine-tuning the beam before installing the wiggler.

G. Neil reported that significant progress was made toward setting up the FEL optical systems. Optical transport diagnostics were completed, aligned and put under vacuum, and they were used to take a surrogate HeNe beam from the FEL to the diagnostics table in the optical control room. Patch panels to the optical control room were installed and fully wired. Fiducialization of the first-light mirrors was completed. The mirror-control software for save/restore was verified. The cavity mirror alignment as viewed through position sensors drifted by less than 10 µrad over several days, well within specification.

More discussion about the always popular topic of configuration control arose. D. Douglas pointed out that he has difficulty iterating toward an optimal orbit when the machine setup keeps changing. Bohn reviewed the configuration control policies instituted to date, reiterated that the present Golden File is Douglas's file from last Wednesday, and explained once again how the planned shift activities are designed to converge on a usable setup for lasing. The process should get easier, and the procedures should get firmer, once the machine is "complete", meaning to zeroth order that the Happek monitors are installed and checked out, and that is scheduled for the beginning of next week. Bohn is totally open to ideas on how to do things better and more efficiently. He also will soon convene a meeting to discuss elements of the procedure for setting up the longitudinal phase space.

R. Lauze asked that we prepare a glossary of FEL terminology as an aid to CEBAF operators. New hires should be showing up soon, and they will benefit from this head start. R. Walker will begin compiling the glossary.

M. Shinn presented a synopsis of measurements of drive-laser noise. Her principal observations are:

She offered three proposed solutions: As a result of her talk and her recommendations, Michelle was asked to prepare a plan to do the first two fixes so we can provide resources and schedule the activities.

Over the next two weeks the basic program is to do orbit and phase-space optimization during day shifts, cw runs during swing shifts, and beam diagnostics/beam quality measurements during owl shifts. Progress from each shift will feed into the other shifts as together we iterate toward a usable lasing setup. Shift assignments for the next two weeks are (remember to use the CEBAF operator!):

11-15 May 1998:
Owl -- Merminga, CEBAF operator, Piot on standby
Day -- Douglas, CEBAF operator, Benson on standby
Swing -- Shinn, CEBAF operator, Siggins on standby (Krafft also on standby for Happek checks on 11-12 May)
18-22 May 1998:
Owl -- Walker, CEBAF operator, Piot on standby
Day -- Bohn, CEBAF operator, Neil on standby
Swing -- Siggins, CEBAF operator, Hill on standby

Status of the remaining top-level MUST-priority prerequisites to lasing is:
1.Stable, easily recoverable 1.1 mA, 38 MeV beam with sufficiently good beam quality.

Status: Must evolve from the iterative commissioning process described above.
2. Working diagnostics: 3. Adequate injector setup.
Status: Working toward a procedure for reproducible setup.
4. Detailed procedures and test plans well communicated to MCC staff.
Status: Ongoing. See, for example, list at end of these minutes.
5. Working optical transport, including Laser Safety System for the Optical Control Room.
Status: See summary above. LSS still needs installation. Total remaining work could be done within one week, i.e., it will be done by the time the accelerator is ready for lasing.
6. Radiation monitor at wiggler location (to protect wiggler).
Status: Complete. Gathering data in conjunction with commissioning.

New Issues


None, but the FEL ARR is scheduled for 27 May 98, and presently we do have some "issues" to be addressed in the context of the ARR subsequent to providing photons to users.

New Action Items


Old Action Items


Test Plans in Work



Procedures in Work


Set Up Longitudinal Phase Space                 Douglas, 15 May 98
Set Up Transverse Phase Space                   Douglas, 15 May 98
Set Up Beam Steering                            Douglas, 15 May 98
Emittance Growth from CSR



Procedures Needed for Recirculation


Thread Beam around Machine, Top-Level Douglas, finalize 30 June 98 RF Stability during Energy Recovery Merminga, 30 June 98