Free Electron Laser Commissioning Meeting

Friday, 14 Nov 97
Recorder: C. Bohn

Next Meeting


Date: 21 Nov 97
Time: 0830-0930
Place: FEL Facility Break Room

Agenda for Next Meeting


Item Person Responsible Time ---- ------------------ -------- Status of Action Items All 5 min Scheduling Update Bohn 15 min Progress Report on Commissioning Legg/Bohn 5 min Cryounit Noise, Residual and Microphonic Merminga 10 min FEL Commissioning Metaprocedure Neil 15 min New Issues All 5 min Agenda for next week All 5 min

This Week's Attendees


J. Bennett, G. Biallas, J. Bisognano, C. Bohn, J. Boyce, D. Douglas, F. Dylla, D. Engwall, J. Fugitt, E. Gilmann (NSU), A. Hofler, C. Hovater, K. Jordan, G. Krafft, R. Legg, R. Li, L. Merminga, J. Musson, G. Neil, P. Piot, J. Preble, Q.-S. Shu, R. Walker, B. Yunn

Closed Action Items


The following actions from last week's report were closed out:

        Bohn                            11/25-28/97, 12/22/97 - 1/1/98
        Engwall                         12/23-30/97
        Jordan                          11/23-30/97
        Krafft                          11/23-30/97
        Legg                            12/8/97
        Neil                            11/25/97 - 1/6/98
        Shu                             11/25/97 - 12/2/97
        Walker                          11/15/97 - 12/2/97
        Yunn                            12/15/97 - 1/21/98

We, of course, will do our best to accommodate these plans while arranging shift work, but request people to be communicative and adaptable.

Items of Discussion


        Shift times presently differ for weekdays and weekends.  They are:
        Weekdays:  Owl @ 2300-0600, Day @ 0600-1530, Swing @ 1530-2300.
        Weekends:  Owl @ 0000-0800, Day @ 0800-1600, Swing @ 1600-0000.
The reason for the difference is that installation is taking place on day shifts during weekdays, but not on weekends, and we are accommodating the work schedule of the installation crews. The shift times are posted for each day on the scheduling boards in the FEL Facility Break Room. If confusion reigns, we will adjust.

Commissioning over Thanksgiving break and weekend will be on a voluntary basis, with no formally established shift assignments. Work on Thanksgiving Day is, by proclamation, verboten!

R. Legg and J. Preble presented this week's commissioning highlights:

B. Yunn outlined his recent injector modelling, done in conjunction with srf commissioning of the cryounit. At gradients of 12 MV/m and 8 MV/m and rf phases of 0 deg and -42.5 deg for the entrance and exit cavities, respectively, he finds an output kinetic energy of 8.5 MeV. The situation improves considerably with the exit cavity powered at 8.5 MV/m, for which its rf phase is -35 deg, producing an output kinetic energy of 9.1 MeV, a value compatible with the beam transport system. Yunn still needs to finalize the machine settings and will do so by Monday, 17 Nov 97.

D. Douglas discussed the status of the DV (injection-extraction) dipoles. Regarding DVs, the problem is unwanted fringe fields extending over the beamline from the injector and the beamline leading to the energy-recovery dump. Two fixes are in consideration. The first is to build a new Y-chamber for the energy-recovery dump and leave the magnets out altogether for first light; the present Y-chamber has insufficient acceptance without the magnet. Second is to lengthen the field clamp to extend over the whole Y, then add a coil to counter the fringe field. The second option is clearly preferred from a programmatic viewpoint, since there is insufficient cost and schedule to build another Y-chamber and no one wants to postpone resolution. TOSCA runs continue to be in progress and hopefully will be completed imminently. A working code would permit us to set parameters for the modifications. Absent that, we will likely need to establish parameters in situ.

Douglas also discussed the status of the DQ (reverse-bend) dipoles, for which the good- field region is a factor of two too small, achieving dB/B = 10^-4 at ±6 cm rather than at the specified ±10 cm. The transverse beam size in the horizontal plane is very large through these magnets. DIMAD results suggest a do-nothing approach would put the acceptance of the beam- transport system marginally at 5%, and probably less than that. Comparison with CEBAF magnet performance also gives rise to concern. Possible fixes include adding surface coils and/or shims. Efficacy of surface coils is presently being assessed in the Magnet Test Stand.

J. Musson presented a brief overview of the design of the FEL master-oscillator (MO) system and measured results after its installation. The MO involves four legs, one for the injector and the other three for three cryomodules (meaning only two are presently in use). It is based on a STAR configuration, with cables anchored to the LCW input lines and insulation wrapped around the cables and LCW lines. The LCW temperature is measured to be stable to ±1 deg F. Measured performance for all four legs is about 0.1 deg phase variation for 1 deg F temperature variation. This is in a quiescent environment, i.e., without the accelerator in full-up operation, but the results are nevertheless quite promising.

New Issues


J. Fugitt pointed out that the high-voltage power supply for the photocathode gun exhibits a voltage drop in pulsed operation on millisecond time scales. He advised that this be monitored and taken into consideration for pulsed operation during commissioning.

New Action Items


Old Action Items


Procedures in Work


First Light Setup

Emittance Growth from CSR

Thread Beam around Machine, Top-Level           Douglas, 1 Dec 97