BTLLPEG CHECKLIST
Update Monday December 2nd , 2002
1. Magnets (Joe & Simon) 2. Viewers (Tony) 3. Beam Dump (Tony)
  • All Cards Present
  • 3 Amp & 1 Amp
  • MEDM Computer control
  • Check Field - proper connections
15 degree Bend Magnet (Joe)
  • Map Magnet
  • Install magnet
  • Cameras
  • Lenses (ordered and installed)
  • Pneumatics
  • Software Not Epics Controlled (Tony see #7
  • PicoAmmeter
  • Software Support Meter given to Pam
  • Cable and Proper Load from Dump to Control Room 
4. Interlocks (hardware) (Tony) 5. Laser  6. Mechanical
  • Radiation Warnings (not interlocked)
  • Water Flow
  • Bend Magnet 
  • Laser Shutter
  • Crash Button
  • Diode Current Supply (John)
  • 100Kv HV comparator window 
  • Grounding Chain
  • Door Interlock
  • Interlock PLC
  • X/Y Stage (Tony) Steppermotor Chassis
  • Serial Communication, both PSUB on IOCPL2
  • Seed Laser (John)
  • Attenuator ( High Poarization) (John)
  • Shutter (John)
  • Door handles (Phil / Plan)
  • Door locks (Jim)
  • Laser Enclosure (Jim)
  • Add Laser Enclosure Cover micro switch
  • Cable Pulls
7. Additional Electronics (Tony) 8. Smoke Detectors  (Maud w/ Plant) 9. Documentation
  • Debug PS Digital I/O Card(additional MEDM Channels)
  • 100kV AC interlock circuit added to BTLLPEG Power Supply
  • 100kV 0-10V scaled output circuit added to BTLLPEG Power Supply
  • Laser interlock circuit added to Laser and Enclosure
  • Add .1 ohm to 15' bend magnet circuit for comparator
  • Mount & wire comparators in  Control room rack (Bend & 100kV)
  • One set of contacts for Fire System
  • Extra set of contacts for machine protection
  • Detector installed in Laser Hut, North & South Cave
Plant says money not available for work to be completed
  • LSOP (1) (Maud)
  • SOP (1) (Maud)
  • TOSP (1) (Marcy)
  • Interlock & Laser Interlock Check Lists (Tony)
  • BTLLPEG setup and backout procedures (Marcy & Tony)
10. Radiation (Tony) 11. Dark Current (Marcy) 12. Lead Wall Certification (Maud w/ RadCon)
  • Proper Signage
  • Beacons (Tony)
  • HV Beacons 
  • Laser Beacons 
  • BTLLPEG/ ITS South RadCon Wall Survey
  • DVM and Camera (Experiment Postponed)
  • Finish measurements 
  • Proper Sign for wall construction 
  • Proper Sign for Aproval of RadCon
Page maintenance performed on Dec. 2, 2002
Maintained by daya@jlab.org
 
  • completed
  • started