Tagger commissioning schedule

Day Shift leader Scheduled activity
******************************************************************
Thur. 3/26
F.I.U. Moller tests. Start the checkout of beamline
devices.

Fri. 3/27
F.I.U. Moller tests. Start the checkout of beamline
devices.

Sat. 3/28
day: Arne Freyberger Tune 2.4 GeV beam.
night: Elton Smith Tune photon beam, collimator studies, check
backgrounds in TOF and DC, DC readout turned
on, shielding studies.

Sun. 3/29
owl: C.U.A. Plateau the tagger T-counters.
day: Simon Taylor Start counter checkout.
night: Mike Klusman Plateau the E-counters, pair spectrometer,
pair counter

Mon. 3/30
owl: Mike Dugger Plateau the E-counters, pair spectrometer,
pair counter.
day: Barry Ritchie Total absorption counter and platform checkout.
night: Mike Klusman Pair spectrometer and pair counter tests.

Tue. 3/31
owl: C.U.A. Pair spectrometer and pair counter tests.
day: Rory Miskimen Timing studies of tagger scalers.
night: Steve Barrow Asynchronous trigger test. Study timing
between Start counter and TOF, and MOR.

Wed. 4/1
owl: C.M.U. Study timing between Start counter and TOF,
and MOR.
day: Burin Asavapibhop Begin trigger and DAQ studies. Optimize
MOR*ST coincidence, TOF pulse width.
night: Claude Marchand Test tagger prescaling. Turn on drift chamber
readout. Study DAQ rates.

Thur. 4/2
owl: C.M.U. Flux normalization.
day: Change energy to 4.0 GeV.

--=====================_890705079==_
Content-Type: text/plain; charset="us-ascii"

Rory Miskimen
miskimen@phast.umass.edu
Phone: 413-545-2480
Fax: 413-545-4884

--=====================_890705079==_--