TOF Team,

We meet yesterday and reviewed our readiness for the run. Much needs to be
accomplished next week. The forward carriage moves today, Wednesday. The north clam shell
moves Monday, the south on Tuesday. Cabling must occur on Wednesday. We can take data with
the forward carriage now. As soon as cabling is complete, we can take data on the north
(Tuesday?) and south clam shells.

Next Tuesday at 1:30, we will have a TOF training session in the counting house, to
go over monitoring of the TOF system.

I include various lists we went over in the meeting, including the current list of
bad channels:
TOF Tasks 11/25/97

Task Responsibility Status

Hardware
laser calibration system Dale Hancock
electronics Costy
scalers Elton
Calibration Constants
TDC calibrations Maurik/Simon New constants in map
mip peaks Costy First pass in map
attenuation lengths Costy
left-right Simon Next Iteration in map
counter-to-counter Simon Next Iteration in map
panel-to-panel Latifa
Gain Matching Panel 4 Costy Start When cabled
Monitoring Software
documentation
what needs to be monitored
Offline Software

TOF Checklist

Grounding straps to carriages Doug
Signals to counting House operational Costy
All Large-Angle signals connected Costy/Elton/Tom Check by HV selection
Trigger and Gate Signals Connected
between forward carriage, space frame ?
Laser: gas, flow, power (as required) Dale/Costy
CAMAC crates: remote operation Simon
VXI crates: remote operation Simon
HV: remote operation Costy
Take Cosmic-Ray Data Simon/Costy
Take Laser Data Simon/Costy
Visual Check Forward Carriage Elton

Surveys and positions Kelly Tremblay
Inclusion of surveys in RECSIS ?
TDC calibrations Simon / Maurik Program complete
Cosmic Ray Runs (Pair HV=0) Costy complete
laser runs
time-walk corrections Simon / Costy FC complete
ADC gate Costy January
Backing Structure / Sector 5 48b Tom complete
Problem Channels Costy / Tom Fixes 11/03
ADC Cable order Elton Due 12/15
Scalers Simon / Elton Sector 2?
Equalization of Scint Pairs Tom January
Install Sect 1,2,3,4 Panel 4 Tom / Doug complete
Tracking
Time Resolution Determinations Simon
Time Matching with particles
electrons
charged pions
neutral pions

Original List 9/22/97
Updated 11/25/97 with notes

Sector Scint ADC TDC Name Date Comment

3 18R ok bad Costy 11/24/97 FIXED bad lemo cable
3 30R ok bad Carstens 9/23/97 ? Signal at splitter

4 8L ok bad Costy 11/24/97 FIXED bad lemo cable

5 9R bad bad Costy 11/24/97 FIXED itself?
5 36R bad ok Carstens 9/23/97 ? Signal at splitter

6 1R bad bad Carstens 9/23/97 CRATT Bad at first jumper
6 30R bad ok Carstens 9/23/97 ? Signal at splitter
6 45L(A) ok low Carstens 9/23/97 New / light leak or weak

CRATT: Cannot Repair At This Time.

Problem: ADC and TDC ADC or TDC

Status before fixes: 2 6 11/03/97
Status after fixes: 1 4 11/24/97