1. Region I installation and testing
RI has been installed. The last cables were hooked up last night. Chamber
has been at full high voltage. Seven HV channels are tripping; needs to be
investigated. Ready to put in trigger counter and take cosmic ray data.
Estimate to finish RI work by Saturday.
2. Sequence of upcoming events
Friday day move forward carriage
night tagged photon test run
(sweep Hall B at 6:00 p.m.)
Saturday
7:00 a.m. Hall B open
morning put mini-torus on insertion cart
afternoon install mini-torus in magnet bore
put cryo-target on insertion cart
(need to look at potential interference with
surveyors' I-beam)
Sunday
morning survey and position mini-torus
afternoon mount cryo-target to mini-torus
Monday survey cryo-target
3. Access/egress from carriages (status and plans)
Forward carriage
Deck 1 cable room
Deck 2
main access (draw) bridge to stairs on north side
(2 positions for in/out)
second egress for in-position: walkway to forward alcove +
roll-up stairs to ground level
none for out-position
Deck 3
main access (draw) bridge to stairs on north side
(2 positions for in/out)
second egress platform on south side + vertical caged ladder
to floor level
(has been fabricated, to be installed during
October/November down time)
Deck 4
main access removable fiberglass ladder (to be replaced by
permanently installed vertical ladder)
second egress vertical ladder leading to Deck 3 platform on
south
(has been fabricated, to be installed during
October/November down time)
Clamshell north
Electronics deck
main access (draw) bridge to Indiana platform
(2 positions for in/out)
needs to be fabricated and installed
second egress back walkway + roll-up stairs
(walkway has been fabricated, to be installed
during October/November down time)
Laser deck
main access (draw) bridge to Indiana platform
(2 positions for in/out)
needs to be fabricated and installed
second egress vertical ladder to electronics deck below
(needs to be fabricated, to be installed
during October/November down time)
Clamshell south
Electronics deck
main access roll-up stairs to front of racks
second egress back walkway + second roll-up stairs