Therefore, the new schedule is:
March 10-17: Install photon beam setup, including cryotarget
March 18-23: Photon commissioning at 4 GeV
March 24-25: Maintenance
March 26-27: Moeller tests
March 28-31: Install and setup photofission; possibly begin run March 31
April 1-6: Run photofission at 4 GeV; possibly test 0.8 GeV on April 6
April 7: Maintenance
April 8: Possibly tune 0.8 GeV, but if not promising, then 1.6 GeV
April 9-12: Run photofission, possibly at 0.8 GeV, more likely 1.6 GeV
April 13-14: Possible contingency, but pressure will be on to begin g1
One of the beauties of this schedule is that Hall B has priority for April
6-14.
Well, please make your plans accordingly. I would appreciate it if you
would let me know the dates of your availability. Thanks very much.
Here's to a successful Photofission experiment!
Cheers, Barry
Barry L. Berman
Professor and Chair
Department of Physics
The George Washington University
Corcoran Hall, Suite 208
725 21st Street NW
Washington, DC 20052
Telephone: (202) 994-7192
Secretary: (202) 994-6276
Fax: (202) 994-3001
>>> Please note: My new E-mail address is berman@gwis2.circ.gwu.edu <<<