Archived Messages for HALLA_RUNS@cebaf.gov: The Last Commissioning Run: Optics study

The Last Commissioning Run: Optics study

Riad Suleiman (suleiman@CEBAF.GOV)
Fri, 18 Apr 1997 16:55:11 -0400 (EDT)


Dear Hall A Collaborators,

The last commissioning run before 16O will be from April 24th to April 28th.

To be able to make a resonable schedule, I identify the
following responsibilities:

1. Magnets
2. Detectors
3. Data Acquisition
4. Beamline & Target
5. Data Analysis.

In your response, I would like from you to fill the following for each
shift:

++ : Want to be on this shift.
+- : Will not mind if I were on this shift
-- : Do not want to be on this shift

and claim a responsibility.

I will send you an example of how the response should be. You may edit
the example and change it to fit you.

Note: please reply by Tuesday, April 22 1997 12:00.

Best Regards,
Riad Suleiman.