Dear Hall A Collaborators,

The FPP tests with unpolarized beam (2.4 GeV) and water-fall target
commissioning will be from
April 17th to April 21st.

To be able to make a resonable schedule, I identify the
following responsibilities:

1. Magnets
2. Detectors
3. Data Acquisition
4. Beamline & Target
5. Data Analysis.

In your response, I would like from you to fill the following for each
shift:

++ : Want to be on this shift.
+- : Will not mind if I were on this shift
-- : Do not want to be on this shift

and claim a responsibility.

I will send you an example of how the response should be. You may edit
the example and change it to fit you.

Note: please reply by Tuesday, April 15 1997 12:00.

Best Regards,