[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

change of run plan



Dear Colleagues,

 It now appears certain that due to the budget situation in FY08 the 
startup of the accelerator will be delayed by one month. This also 
affects the startup of the endstation refrigerator which will not be 
available before October 1. Therefore, all work requiring 
superconducting magnets in the Hall will be delayed accordingly.  In 
particular, the start of e1-dvcs will be delayed and the entire run 
schedule shifted accordingly. There is also the distinct possibility 
that the number of scheduled experiment weeks in FY09 will be further 
reduced, contingent upon the length of the continuing budget resolution 
in 2009.

I will keep you informed as new information emerges.

Volker Burkert