Quarterly Progress Meetings:
October 16, 2008 1:00-5:00 at JLab CC-A110
* Final definition of active detector volumes
* Draft of each detector's reserved space
* Plan and Elevation views with real dimensions for active volumes
or components; draft layout for frames, supports, PMTs, front-end
electronics, cables, piping, etc.
* Draft layout data was sent out last month.
February '09
* Final definition of reserved space in detector stack
* Plan and Elevation Assembly drawings with full dimensioning -- all
on-detector items.
* Proposed detailed plumbing/wiring layout.
* Provide specifications for supporting services:
* Readout electronics, HVPS, LVPS rack space requirements, number of
NIM/FB/CAMAC/VME slots and rough locations.
* Cable list (from/to, how many, what type, patch panels, ...)
* Utilities & Services Requirements: AC power, gas, vents, plumbing.
* Other support hardware space needs: pumps, refrigerators,
manifolds, distribution systems, lasers, etc.
June '09
* Final resolution of interferences.
* Detail of mounting and alignment systems
* Layout of all supporting hardware, cable/plumbing routing &
supports, patch panel and electronics locations.