Friends of the SHMS Detector Package,

It appears that the one date that we can all meet is

    Thursday, October 16, 1:00-5:00 p.m. (EDT)

Please mark your calendars and reserve the date. I am reserving a room now.

    Howard

*FINAL DESIGN Review by 9/30/09*
      

Quarterly Progress Meetings:
October 16, 2008 1:00-5:00 at JLab CC-A110 

    * Final definition of active detector volumes
    * Draft of each detector's reserved space
    * Plan and Elevation views with real dimensions for active volumes
      or components; draft layout for frames, supports, PMTs, front-end
      electronics, cables, piping, etc.
    * Draft layout data was sent out last month.

February '09

    * Final definition of reserved space in detector stack
    * Plan and Elevation Assembly drawings with full dimensioning -- all
      on-detector items.
    * Proposed detailed plumbing/wiring layout.
    * Provide specifications for supporting services:
    * Readout electronics, HVPS, LVPS rack space requirements, number of
      NIM/FB/CAMAC/VME slots and rough locations.
    * Cable list (from/to, how many, what type, patch panels, ...)
    * Utilities & Services Requirements: AC power, gas, vents, plumbing.
    * Other support hardware space needs: pumps, refrigerators,
      manifolds, distribution systems, lasers, etc.

June '09

    * Final resolution of interferences.
    * Detail of mounting and alignment systems
    * Layout of all supporting hardware, cable/plumbing routing &
      supports, patch panel and electronics locations.