January 2018

Director, with the Leadership Council, discusses the LDRD Program funding level for the FY18 fiscal year.

February 2018

FY18 LDRD Program begins.

 

Call for Proposals: Director issues the Call for Proposals. It includes guidance on the anticipated funding level and a reminder of the broad nature and goals of the program.
The call includes the solicitation of (optional) Letters of Intent (due no later than the end of February). The call is transmitted via email to the scientific and engineering staff throughout the laboratory.

 

The anticipated LDRD Program funding level is transmitted by the Director to the CFO/Budget Office.

 

CFO/Budget Office includes LDRD funding into the annual Field Budget.

March 15, 2018

Deadline for Letters of Intent (format defined) to be submitted to the LDRD Program Manager.

March 15- April 7, 2018

LDRD Project Review Team reviews the Letters of Intent, getting advice from sources they deem relevant. No later than March 27 they provide the author(s) of the Letters of Intent with comments and suggestions.

March 31, 2018
(Will be changed.
Please check back)

Deadline for contacting your Division Budget Analyst to develop a plan for completing the budget section of your proposal.

 

 

April 28, 2018

Proposal submission deadline. FY18 formal project proposals submitted via ADs to LDRD Program Manager.

Note that this will also be the deadline for mid-year reports of progress (and of continuation funding proposals if applicable) for ongoing FY17 LDRD projects.

 

 

May 1 - July 3, 2018

LDRD Program Manager coordinates peer-reviews (internal and external to JLab) as deemed necessary to gather all relevant information required to fully evaluate the project proposals.

June 4, 2018

PIs receive preliminary feedback from reviewers

July 5, 2018

Presentation by PIs to Review Team and final review by Review Team

July 6 - August 31

Director solicits additional input as needed and does final review

September 2018

Director chooses final FY18 project proposals and submits to JLab DOE Site Office for concurrence.

 

Awards announced

 

CFO/Budget Office coordinates approval of current year's project proposals, and prepares LDRD account numbers and execution guidelines.

 

LDRD Program Manager coordinates EHS&Q Reviews of each approved project. Submission of NEPA checklists by lead scientists for approval by ES&H/DOE Site Office (These reviews are required only required for approved projects.)

October 2018

LDRD Program Manager holds FY18 LDRD Program kick-off, LDRD projects formally begin.

October 31, 2018

Note: this is the deadline for FY17 LDRD project annual reports for ongoing LDRD projects.

   

Calendar Year 2018

April 27, 2018

Deadline for FY18 midyear update reports due from lead scientists to the JLab LDRD Program Manager.

October 31, 2018

Deadline for FY18 LDRD Project Annual Reports due to the JLab LDRD Program Manager

 