Laboratory Directed Research & Development
LDRD Draft Calendar
Deadlines for Fiscal Year 2018 LDRD Program
Calendar Year 2018 |
|
January 2018 |
Director, with the Leadership Council, discusses the LDRD Program funding level for the FY18 fiscal year. |
February 2018 |
FY18 LDRD Program begins. |
|
Call for Proposals: Director issues the Call for Proposals. It includes guidance on the anticipated funding level and a reminder of the broad nature and goals of the program. |
|
The anticipated LDRD Program funding level is transmitted by the Director to the CFO/Budget Office. |
|
CFO/Budget Office includes LDRD funding into the annual Field Budget. |
March 15, 2018 |
Deadline for Letters of Intent (format defined) to be submitted to the LDRD Program Manager. |
March 15- April 7, 2018 |
LDRD Project Review Team reviews the Letters of Intent, getting advice from sources they deem relevant. No later than March 27 they provide the author(s) of the Letters of Intent with comments and suggestions. |
March 31, 2018 |
Deadline for contacting your Division Budget Analyst to develop a plan for completing the budget section of your proposal. |
|
|
April 28, 2018 |
Proposal submission deadline. FY18 formal project proposals submitted via ADs to LDRD Program Manager. Note that this will also be the deadline for mid-year reports of progress (and of continuation funding proposals if applicable) for ongoing FY17 LDRD projects. |
|
|
May 1 - July 3, 2018 |
LDRD Program Manager coordinates peer-reviews (internal and external to JLab) as deemed necessary to gather all relevant information required to fully evaluate the project proposals. |
June 4, 2018 |
PIs receive preliminary feedback from reviewers |
July 5, 2018 |
Presentation by PIs to Review Team and final review by Review Team |
July 6 - August 31 |
Director solicits additional input as needed and does final review |
September 2018 |
Director chooses final FY18 project proposals and submits to JLab DOE Site Office for concurrence. |
|
Awards announced |
|
CFO/Budget Office coordinates approval of current year's project proposals, and prepares LDRD account numbers and execution guidelines. |
|
LDRD Program Manager coordinates EHS&Q Reviews of each approved project. Submission of NEPA checklists by lead scientists for approval by ES&H/DOE Site Office (These reviews are required only required for approved projects.) |
October 2018 |
LDRD Program Manager holds FY18 LDRD Program kick-off, LDRD projects formally begin. |
October 31, 2018 |
Note: this is the deadline for FY17 LDRD project annual reports for ongoing LDRD projects. |
Calendar Year 2018 |
|
April 27, 2018 |
Deadline for FY18 midyear update reports due from lead scientists to the JLab LDRD Program Manager. |
October 31, 2018 |
Deadline for FY18 LDRD Project Annual Reports due to the JLab LDRD Program Manager |
See LDRD Project Review Team for the membership of this group