|
|
TITLE: |
||
|
|
|||
|
DOCUMENT ID: |
3330
Appendix T4 Work Re-Start
Procedure |
||
|
|
|||
Jefferson Lab provides this work re-start procedure to ensure the safety of individuals, equipment, and the environment after a work delay. Characteristics of each delay, including urgency, resources, timeliness of communications, etc, differ. This document provides the minimum requirements to ensure that safe, effective work planning has been enacted prior to work re-start.
This procedure is applied after:
· A concern has been identified during in-progress work and all parties agree to a resolution; however work must be delayed until the resolution is implemented. (See ES&H Manual Chapter 3330 Appendix T1 Suspend Work for Safety Procedure.)
· Completion of the process steps as outlined within ES&H Manual Chapter 3330 Appendix T2 Stop Work for Safety Procedure.
This appendix is written in coordination with ES&H Manual Chapter 3330 Stop Work and Re-Start for Safety Program, and all relevant content within the chapter applies to the procedure outlined in this appendix.
3.1
Point of Contact - Appointed by Associate Director and/or
Division Manager
·
Coordinate
all Re-Start Work Process Steps.
·
Establish
a Resolution Team
·
Make
ATLis (or similar) entries regarding work re-start plans.
·
Communicate
status updates and plan activities to management.
|
If, at any time during the implementation of these process steps, an additional hazard or concern is identified a “Stop Work Order” may be issued by the identifier. See ES&H Manual Chapter 3330 Appendix T2 Stop Work Order for Safety Procedure. |
Unless otherwise noted the Point-of-Contact performs the following process steps to re-start work:
|
As soon as
practicable, contact the ESH&Q Reporting Officer who will perform a preliminary causal analysis. A more detailed causal analysis will
follow, along with an appropriate Notable Event Report. |
|
As soon as
practicable, contact the ESH&Q Reporting Officer who will perform a preliminary causal analysis. A more detailed causal analysis will
follow, along with an appropriate Notable Event Report. |
·
Establish
a Resolution Team. Members include:
o
Subject
Matter Expert(s) (designated “Responsible” within ATLis)
o
Equipment
Owner(s)
o
ESH&Q
Professional
o
Others
as appropriate
o
Determine
the most effective strategy to resolve the hazard.
o
Outline
a plan for implementation and return to normal operations.
o
Communicate
the plan to the Point-of-Contact.
Step 2:
ATLis (or similar):
·
Input
the plan into an original ATLis (or similar) entry including:
o
Task
Hazard Analysis (function included in ATLis)
o
The
estimated time requirement, including a timeline/milestone associated with
separate tasks.
o
Other
systems affected, i.e., a plan, timeline and resources for conducting an
Extent-of-Condition analysis.
o
Other
standard entries as required.
·
Team Members provide status updates into the ATLis (or
similar) “Comment” field to include:
o
Subtask
ATLis Task ID numbers.
o
Accomplished
work, including when it was completed, and
o
Any
other issues of relevance.
·
Using
ATLis (or similar) “Comment” field, provide Jefferson Lab Management with the
following updates:
o
Initial
Plan Overview – Provided as soon as practical.
o
Periodic
Update(s) – number is dependent on complexity and duration of plan; and upon
request of management.
o
Final
Completion – before operations are returned to normal.
·
Jefferson Lab Management addresses concerns through the Point-of-Contact
or by ATLis entry.
·
Subject Matter Expert: Upon completion of the plan the original
ATLis entry is denoted “completed.”
·
Work Re-Start
follows normal ATLis (or similar) guidelines.
Step 6:
Feedback and Lessons Learned
· Point-of-Contact provides Jefferson Lab relevant information regarding the work re-start activities using the Jefferson Lab’s Corporate Operating Experience (COE) website.
Point-of-Contact
ensures that implemented safety measures continue to be used.
4.0
Revision Summary
Periodic Review – 02/28/13 – No substantive changes per HFanning.
Revision 0 – 01/28/10 – This is new content.
|
|
ISSUING
AUTHORITY |
TECHNICAL POINT-OF-CONTACT |
APPROVAL
DATE |
REVIEW
REQUIRED DATE |
REV. |
|
|
|
ESH&Q Division |
01/28/10 |
01/28/16 |
0 |
|