|
|
TITLE: |
||
|
|
|||
|
DOCUMENT ID: |
3410
Appendix T2 Mitigation
Requirements for Hazard
Issues involving Service and Construction Procurements
|
||
|
|
|||
1.0
Purpose
Jefferson Lab’s Subcontracting Officer’s Technical Representatives (SOTR) use this procedure to:
· Appropriately plan procurement documents to accurately identify hazard issues and required mitigation;
· Adequately communicate mitigation requirements to subcontractor prior to bid;
· Reiterate mitigation requirements to subcontractor during a post contract award and pre-work meeting;
· Document Feedback and Lessons Learned.
2.0
Scope
The requirements of this appendix apply to all subcontracted services including construction in accordance with ES&H Manual Chapter 3410 ES&H Aspects of Procurements.
3.0
Responsibilities
NOTE: Management authority may be delegated at the discretion of the responsible manager.
3.1
Requisitioner/Subcontracting
Officer’s Technical Representative (SOTR)
·
Complete and maintain GEN
133 Activity Hazard Analysis.
·
Identify hazard issues.
(See ES&H
Manual 2410 Appendix T1 Hazard Issues List.)
·
Establish safety and health mitigation requirements - Confer with
ES&H Subject
Matter Experts (SMEs).
·
Explicitly identify safety and health requirements within the
contract documents.
·
Document feedback and lessons learned in accordance with ES&H Manual Chapter
3410 Appendix T1 Mitigation Requirements for Hazard Issues relating
to Equipment and Material Procurements.
3.1.1
SOTR also:
· Determine the need of a Subcontractor Safety Plan and/or Hazard Analysis.
· Communicate Jefferson Lab’s hazard mitigation requirements to subcontractors as detailed within
relevant ES&H Manual Chapters.
· Communicate
subcontractor ES&H deficiencies to Procurement.
3.2
Procurement Services
·
Assure the identified ES&H requirements are included within
the contract.
·
Maintain records of supplier/subcontractor performance related to
ES&H requirements.
·
Evaluate
subcontractor’s eligibility for future subcontracts by reviewing feedback
documentation.
3.3
ESH&Q Division
· Provide guidance to requisitioners,
SOTRs, and Procurement Services, in the development of ES&H mitigation requirements.
3.4
Facilities Management
&Logistics Manager
·
Maintains ES&H specifications for procured services and
construction.
4.0
Process Steps
The SOTR completes the following
process steps and uses the information to develop procurement documents that
contain mitigation required by Jefferson Lab for recognized hazard issues.
Step 1:
Identify
Hazard Issues
· Review ES&H Manual
Chapter 2410 Appendix T1 Hazard Issues List.
·
Determine
relevant hazard issues.
Step 2:
Establish Safety and Health Mitigation
Requirements
For
all hazard issues recognized to be relevant:
·
Review
the associated ES&H Manual Chapters and Appendices listed to determine the
established hazard mitigation requirements.
·
Consult with the Subject Matter Experts to identify specific ES&H requirements.
NOTE: The Material Identification and
Traceability, Supplier Evaluation, and Pressure System Quality
Procedures may apply to some acquisitions
(e.g., materials for use in pressure vessel systems). These documents are available in the QA Program Description.
|
Step 3:
Explicitly Identify Mitigation
Requirements within the Contract Documents:
·
Include FM&L’s Division 1 Master Specifications in all
procurements of construction services
·
Subcontractor Safety Plan (SSP)
The need for a subcontractor to
provide a SSP is related to the scope, complexity, and duration of the
work. The determination is made by the
SOTR after consultation with Procurement, the Division
Safety Officer,
and the ESH&Q professional(s).
Jefferson Lab reserves the right to request a SSP for any work performed
by an outside vendor. One is required
if:
o The value of the subcontract
exceeds $20 million,
o The subcontract will occur over
multiple years with the value of services in any year exceeding $5 million
OR
o All construction activities,
regardless of cost
o On-site fabrication
activities with an estimated cost of $100,000 and above,
o Any activity that has an anticipated Risk
Code of >3 (see ES&H Manual
Chapter 3210 Appendix T3 Risk Code Assignment), or
o As required for
specialized work*.
|
*Specialized work includes:
o cutting
of masonry products o installing,
cutting, or removing concrete o installing
or removing sheet rock compound
o Use
of chemicals in a quantity or manner recommended by the MSDS. o As
recommended by manufacturer information.
Submit
any mitigation requirement documents, or equivalent, to ES&H Division Liaison
for review prior to approval. |
4.2
Communicate Mitigation
Requirements to Subcontractor
The SOTR completes the following
process steps.
Step 1:
Schedule Pre-Work
(e.g.: Pre-Bid, Pre-Award) Meeting
· Invite relevant ESH&Q SMEs to the
meeting.
· Allow ESH&Q SMEs adequate time to
fully explain mitigation required by Jefferson Lab
ESH&Q staff will utilize the following
worksheet:
4.3
Post Contract Award
and Pre-Work Meeting
The SOTR
completes the following process steps.
Step 1:
Review and Approve
Subcontractor Documentation
·
Conduct
a pre-work meeting with subcontractors to communicate Jefferson Lab’s
expectations regarding ES&H work practices.
·
Invite
relevant ESH&Q SMEs to the meeting.
·
Allow
ESH&Q SMEs adequate time to fully explain mitigation required by Jefferson
Lab.
ESH&Q staff will utilize the following
worksheet:
·
Submit
any required safety plans, licenses, permits, training to appropriate SME for
review prior to commencement of work.
4.4
Document Feedback and Lessons
Learned
5.0
Revision
Summary
Revision
2.2 – 09/17/12 - Clarification
made to Process Steps.
Revision
2.1 – 07/18/11 - Technical
Point-of-Contact re-assigned from John Kelly to Bob May, per Mary Logue.
Revision
2 – 01/28/10 –
Edited to address responsibility of requisitioners
and SOTRs to review ES&H
Manual Chapter 2410 Appendix T1 Hazard Issues List and associated documents
to ensure Jefferson Lab safety requirements are addressed for material and
subcontractor procurements.
Revision
1 – 03/10/09 –
Re-write of document to reflect current laboratory operations.
|
|
ISSUING
AUTHORITY |
TECHNICAL POINT-OF-CONTACT |
APPROVAL
DATE |
EXPIRATION
DATE |
REV. |
|
|
|
ESH&Q Division |
01/28/10 |
01/28/13 |
2.2 |
|