|
|
ES&H
Manual Fire Protection Supplement |
|
Chapter 10: Fire Barriers |
|
|
|
|
|
|
|
|
|
|
|
|
1.0
Purpose
Most building construction includes the use of fire barriers to protect the occupants in the event of a fire emergency. Fire barriers embody many features that must be kept intact for the barrier to perform its intended function of protection. Inspection of fire barriers must be made throughout Jefferson Lab buildings
2.0
Scope
This document provides the requirements for the inspection of fire barriers.
3.0
Responsibilities
3.1
Building Managers and Safety Wardens
· Conduct regularly scheduled walk throughs of all spaces
· Document the walk through and findings.
3.2
Fire
Protection Engineer (FPE)
· Conduct a fire barrier inspection of buildings.
· Maintains records of inspections and evaluations.
4.0
General Information
4.1
Fire Barriers and Fire Walls
·
Fire Barrier Wall or Fire Partition
Wall – an
interior wall that serves to restrict the spread of fire, but does not qualify
as a fire wall. A fire barrier wall
subdivides a floor or an area and is erected to extend from the floor to the
underside of the floor or roof above.
Fire partitions may be constructed of noncombustible, limited
combustible, or protected combustible materials, and should be attached to and
supported by structural memberts having fire resistance at least equal to that
of the partition.
·
Fire Wall – a wall of sufficient fire
resistance, durability and stability to withstand the effects of an
uncontrolled fire exposure, which may result in collapse of the structural
framework on either side. Openings in the wall, if allowed, must be
protected. Fire walls provide a fire
separation between areas of the same building.
Fire walls are constructed of reinforced concretem concrete blockm
prest4ressed concretem and sometimes brick.
A fire wall can separate buildings or subdivide a building to prevent
the spread of fire.
·
Fire Walls, Fire Barrier Walls and
Fire Partition Walls
o
Are
designed and installed during new construction.
These walls should be inspected and accepted at the time of
construction. Refer to Reference 6.1 for a comprehensive list of present
day design criteria used during new construction. The pertinent sections of this code are:
§ Section 8.3.3 Fire Walls
§ Section 8.4 Fire Barrier Walls
§ Section 8.6 Horizontal Assemblies
§ Section 8.7 Opening Protectives
§ Section 8.8 Penetrations
o
Are
inspected annually.
4.2 Fire Door Assemblies
To satisfy the requirements of Reference 6.3 Section 5.2.1 fire door assemblies are inspected and tested not less than annually and a written record of the inspection is signed.
4.3 Fire Dampers
To satisfy the requirements of Reference 6.3 Section 19.4.1 Fire dampers are tested and inspected one year after installation. The test and inspection frequency is then every four years.
5.0
Process Steps
5.1
Fire
Wall, Fire Barrier Wall and Fire Partition Wall Annual Inspection
5.1.1 Inspect the walls that comprise a fire barrier in each location listed on Table 1. All portions of the wall are to be viewed. Fire barrier walls are continuous through all concealed spaces, such as those found above a ceiling, including interstitial spaces. Inspect each wall using the following criteria:
· Opening Protectives – Fire Doors installed in a fire barrier wall are self- or automatic-closing. All openings are protected by approved, listed and labeled fire door assemblies and fire window assemblies and their accompanying hardware, including all frames, closing devices, anchorage, and sills in accordance with the requirements of Reference 6.3 Section 5.2.3 Functional Test
·
Penetrations
– Penetrations for cables, cable trays, conduits, pipes, tubes, combustion
vents and exhaust vents, wires, and similar items to accommodate electrical,
mechanical, plumbing, and communications systems that pass through a wall,
floor, or floor/ceiling assembly constructed as a fire barrier are protected by
a firestop system or device.
· Ducts and Air Transfer Openings – Fire dampers are installed to protect ducts and air-transfer openings that penetrate fire barriers and fire walls as required by other sections of Reference 6.1. All ducts are not required to be installed with dampers. Refer to Reference 6.1 Section 8.8.8.2 Fire Damper Requirements.
5.1.2 Complete and sign an Inspection Report
Table 1 – Fire Barrier
Locations
|
BUILDING |
FIRE BARRIER |
|
#12
CEBAF Center |
Stairwell
A, B, C, D, E, F, G, H, I, F-Wing\Attrium\Kitchen
common wall Attrium
walls |
|
#28
Support Service Center |
Boiler
Room |
|
#58
Test Lab |
High
Bay\Office Wing Wall High
Bay\Annex Wall Annex
East Stairwell Annex
West Stairwell |
|
#18
FEL |
Skylight
Stairwell |
|
#38
North Access Building |
Tunnel
Exit Stairwell |
|
#67
South Access Building |
Tunnel
Exit Stairwell |
|
#97
Counting House |
Stairwell
Hall
A Cable Shaft Hall
B Cable Shaft Hall
C Cable Shaft |
|
#98 CRYO Fab. Shop |
Common
Wall with electronics area |
|
#94
Hall B |
Labrynth
Exit |
|
#96
Hall C |
Labrynth
Exit |
|
#101
Hall A |
Labrynth
Exit |
5.2 Building
Floor Plans





















6.0
References
6.1 National Fire Protection Association 5000 Building Construction and Safety Code 2009 Edition
6.2 National Fire Protection Association 221, Standard for High Challenge Fire walls, Fire Walls and Fire Barrier Walls 2009 Edition
6.3 National Fire Protection Association 80 Standard for Fire Doors and Fire Walls 2010 Edition
7.0
Revision
Summary
Revision 2 – 02/10/11 – Separated “Combustible Loading” content to Chapter 11.
Revision 1 – 10/01/09 – Updated to reflect current laboratory operations.
|
|
ISSUING
AUTHORITY |
CHAPTER
AUTHOR |
APPROVAL
DATE |
EFFECTIVE
DATE |
EXPIRATION
DATE |
REV. |
|
|
|
Fire Protection Dept |
02/10/11 |
02/10/11 |
02/10/14 |
2 |