Final Schedule - 2002

Date Weekday Accelerator Hall A Hall A Hall B Hall B Hall C Hall C Priority FEL Notes
    GeV/pass/Pol Experiment GeV/mA Experiment GeV/nA Experiment GeV/mA Hall Status 1-7
01/01/02 Tuesday Holiday  Holiday   –   Holiday   –   Holiday   –             
01/02/02 Wednesday Restore  Install Calorimeter   –   –   –   –   –             
01/03/02 Thursday Restore  Install Calorimeter   –   –   –   –   –             
01/04/02 Friday Restore  Install Calorimeter   –   –   –   –   –             
01/05/02 Saturday 1.139/High  Install Calorimeter   –   e1-6   5.759/50/p   Reconfigure                
01/06/02 Sunday 1.139/High  Install Calorimeter   –   e1-6   5.759/50/p   Reconfigure                
01/07/02 Monday 1.139/High  Install Calorimeter   –   e1-6   5.759/50/p   Reconfigure                
01/08/02 Tuesday 1.139/High  Install Calorimeter   –   e1-6   5.759/50/p   Reconfigure                
01/09/02 Wednesday 1.139/High  Install Calorimeter   –   e1-6   5.759/50/p   Reconfigure                
01/10/02 Thursday 1.139/High  Install Calorimeter   –   e1-6   5.759/50/p   Reconfigure                
01/11/02 Friday 1.139/High  Install Calorimeter   –   e1-6   5.759/50/p   Reconfigure                
01/12/02 Saturday 1.139/High  Commission   –   e1-6   5.759/50/p   Reconfigure       A/B          
01/13/02 Sunday 1.139/High  Commission   –   e1-6   5.759/50/p   Reconfigure       A/B          
01/14/02 Monday 1.139/High  E99-114   –   e1-6   5.759/50/p   Reconfigure       A/B          
01/15/02 Tuesday 1.139/High  Compton Scattering   –   e1-6   5.759/50/p   Reconfigure       A/B          
01/16/02 Wednesday 1.139/High  Commission   –   e1-6   5.759/50/p   Reconfigure       A/B          
01/17/02 Thursday 1.139/High  Commission   –   e1-6   5.759/50/p   Reconfigure       A/B          
01/18/02 Friday 1.139/High  Commission   –   e1-6   5.759/50/p   Reconfigure       A/B          
01/19/02 Saturday 1.139/High  Commission   –   e1-6   5.759/50/p   Reconfigure       A/B          
01/20/02 Sunday 1.139/High  Commission   –   e1-6   5.759/50/p   Reconfigure       A/B          
01/21/02 Monday 1.139/High  Commission   –   e1-6   5.759/50/p   Commission   5.759/0.10/p    C/B/A          
01/22/02 Tuesday 1.139/High  Commission   –   e1-6   5.759/50/p   Commission   5.759/0.10/p    C/B/A          
01/23/02 Wednesday 1.139/High  Commission   –   e1-6   5.759/50/p    E01-006  5.759/0.10/p    C/B/A          
01/24/02 Thursday 1.139/High  E99-114   2.332/50   e1-6   5.759/50/p   Nucleon Struct.   5.759/0.10/p    C/B/A          
01/25/02 Friday 1.139/High  E99-114   4.620/50   e1-6   5.759/50/p   E01-006   5.759/0.10/p    C/B/A          
01/26/02 Saturday 1.139/High  E99-114   4.620/50   e1-6   5.759/50/p   E01-006   5.759/0.10/p    C/B/A          
01/27/02 Sunday 1.139/High  E99-114   4.620/50   e1-6   5.759/50/p   E01-006   5.759/0.10/p    C/B/A          
01/28/02 Monday 1.139/High  E99-114   4.620/50   e1-6   5.759/50/p   E01-006   5.759/0.10/p    C/B/A          
01/29/02 Tuesday 1.139/High  E99-114   4.620/50   e1-6   5.759/50/p   E01-006   5.759/0.10/p    C/B/A          
01/30/02 Wednesday 1.139/High  E99-114   4.620/50   Target Change   –   E01-006   5.759/0.10/p    C/B/A          
01/31/02 Thursday 1.139/High  E99-114   5.759/50   Commission   5.759/50/p   E01-006   5.759/0.10/p    B/A/C          
02/01/02 Friday 1.139/High  E99-114   5.759/50   Commission   5.759/50/p   E01-006   5.759/0.10/p    B/A/C          
02/02/02 Saturday 1.139/High  E99-114   5.759/50   e6   5.759/50/p   E01-006   5.759/0.10/p    B/A/C          
02/03/02 Sunday 1.139/High  E99-114   5.759/50   e6   5.759/50/p   E01-006   5.759/0.10/p    B/A/C          
02/04/02 Monday 1.139/High  E99-114   5.759/50   e6   5.759/50/p   E01-006   5.759/0.10/p    B/A/C          
02/05/02 Tuesday 1.139/High  E99-114   5.759/50   e6   5.759/50/p   E01-006   5.759/0.10/p    B/A/C          
02/06/02 Wednesday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    B/A/C          
02/07/02 Thursday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    B/A/C          
02/08/02 Friday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    B/A/C          
02/09/02 Saturday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    B/A/C          
02/10/02 Sunday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    B/A/C          
02/11/02 Monday Maintenance  –   –   –   –   –   –             
02/12/02 Tuesday Maintenance  –   –   –   –   –   –             
02/13/02 Wednesday Restore  –   –   –   –   –   –             
02/14/02 Thursday Restore  –   –   –   –   –   –             
02/15/02 Friday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    A/C/B          
02/16/02 Saturday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    A/C/B          
02/17/02 Sunday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    A/C/B          
02/18/02 Monday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    A/C/B          
02/19/02 Tuesday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    A/C/B          
02/20/02 Wednesday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    A/C/B          
02/21/02 Thursday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    C/B          
02/22/02 Friday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    C/B          
02/23/02 Saturday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    C/B          
02/24/02 Sunday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    C/B          
02/25/02 Monday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    C/B          
02/26/02 Tuesday 1.139/High  E99-114   3.481/50/p   e6   5.759/50/p   E01-006   5.759/0.10/p    C/B          
02/27/02 Wednesday 1.139/High  DVCS Test   5.759/50   e6   5.759/50/p   E01-006   5.759/0.10/p    A/C/B          
02/28/02 Thursday 1.139/High  DVCS Test   5.759/50   e6   5.759/50/p   E01-006   5.759/0.10/p    A/C/B          
03/01/02 Friday 1.139/High  DVCS Test   5.759/50   e6   5.759/50/p   E01-006   5.759/0.10/p    A/C/B          
03/02/02 Saturday 1.139/High  Install E98-108   –   e6   5.759/50/p   E01-006   5.759/0.10/p    A/C/B          
03/03/02 Sunday 1.139/High  Install E98-108   –   e6   5.759/50/p   E01-006   5.759/0.10/p    A/C/B          
03/04/02 Monday 1.139/High  Install E98-108   –   e6   5.759/50/p   Gen R/G0 I                
03/05/02 Tuesday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I                
03/06/02 Wednesday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I                
03/07/02 Thursday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I                
03/08/02 Friday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I                
03/09/02 Saturday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I                
03/10/02 Sunday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I                
03/11/02 Monday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I               8 9  
03/12/02 Tuesday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I                
03/13/02 Wednesday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I                
03/14/02 Thursday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I                
03/15/02 Friday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I                
03/16/02 Saturday 1.139/High  E98-108   5.759/100   e6   5.759/50/p   Gen R/G0 I                
03/17/02 Sunday Facility Dev.  G0 Beam Tests      G0 Beam Tests      G0 Beam Tests                
03/18/02 Monday Facility Dev.  G0 Beam Tests      G0 Beam Tests      G0 Beam Tests                
03/19/02 Tuesday Down  Maintenance      Maintenance      Gen R/G0 I                
03/20/02 Wednesday Down  Maintenance      Maintenance      Gen R/G0 I                
03/21/02 Thursday Down  Maintenance      Maintenance      Gen R/G0 I                
03/22/02 Friday Down  Maintenance      Maintenance      Gen R/G0 I                
03/23/02 Saturday Down  Maintenance      Maintenance      Gen R/G0 I                
03/24/02 Sunday Down  Maintenance      Maintenance      Gen R/G0 I                
03/25/02 Monday Down  Maintenance      Maintenance      Gen R/G0 I                
03/26/02 Tuesday Down  Maintenance      Maintenance      Gen R/G0 I                
03/27/02 Wednesday Down  Maintenance      Maintenance      Gen R/G0 I                
03/28/02 Thursday Down  Maintenance      Maintenance      Gen R/G0 I                
03/29/02 Friday Down  Maintenance      Maintenance      Gen R/G0 I                
03/30/02 Saturday Down  Maintenance      Maintenance      Gen R/G0 I                
03/31/02 Sunday Down  Maintenance      Maintenance      Gen R/G0 I                
04/01/02 Monday Down  Maintenance      Maintenance      Gen R/G0 I                
04/02/02 Tuesday Down  Maintenance      Maintenance      Gen R/G0 I                
04/03/02 Wednesday Down  Maintenance      Maintenance      Gen R/G0 I                
04/04/02 Thursday Down  Maintenance      Maintenance      Gen R/G0 I                
04/05/02 Friday Down  Maintenance      Maintenance      Gen R/G0 I                
04/06/02 Saturday Down  Maintenance      Maintenance      Gen R/G0 I                
04/07/02 Sunday Down  Maintenance      Maintenance      G0 Install                
04/08/02 Monday Down  Maintenance      Maintenance      G0 Install                
04/09/02 Tuesday Down  Maintenance      Maintenance      G0 Install                
04/10/02 Wednesday Down  Maintenance      Maintenance      G0 Install                
04/11/02 Thursday Down  Maintenance      Maintenance      G0 Install                
04/12/02 Friday Down  Maintenance      Maintenance      G0 Install                
04/13/02 Saturday Down  Maintenance      Maintenance      G0 Install                
04/14/02 Sunday Down  Maintenance      Maintenance      G0 Install                
04/15/02 Monday Down  Maintenance      Maintenance      G0 Install                
04/16/02 Tuesday Down  Maintenance      Maintenance      G0 Install                
04/17/02 Wednesday Down  Maintenance      Maintenance      G0 Install                
04/18/02 Thursday Down  Maintenance      Maintenance      G0 Install                
04/19/02 Friday Down  Maintenance      Maintenance      G0 Install                
04/20/02 Saturday Down  Maintenance      Maintenance      G0 Install                
04/21/02 Sunday Down  Maintenance      Maintenance      G0 Install                
04/22/02 Monday Down  Maintenance      Maintenance      G0 Install                
04/23/02 Tuesday Down  Maintenance      Maintenance      G0 Install                
04/24/02 Wednesday Down  Maintenance      Maintenance      G0 Install                
04/25/02 Thursday Down  Maintenance      Maintenance      G0 Install                
04/26/02 Friday Down  Maintenance      Maintenance      G0 Install                
04/27/02 Saturday Down  Maintenance      Maintenance      G0 Install                
04/28/02 Sunday Down  Maintenance      Maintenance      G0 Install                
04/29/02 Monday Restore  Maintenance      Maintenance      G0 Install                
04/30/02 Tuesday Restore  Maintenance      Maintenance      G0 Install                
05/01/02 Wednesday Restore  Maintenance      Maintenance      G0 Install                
05/02/02 Thursday 1.100/High  E01-001   2.262/50   Maintenance      G0 Install                
05/03/02 Friday 1.100/High  Ge/Gm   2.262/50   Maintenance      G0 Install                
05/04/02 Saturday 1.100/High  E01-001   2.262/50   Maintenance      G0 Install                
05/05/02 Sunday 1.100/High  E01-001   2.262/50   Maintenance      G0 Install                
05/06/02 Monday 1.100/High  E01-001   2.262/50   e2 Comm.   1.162/50/p   G0 Install   B/A             
05/07/02 Tuesday 1.100/High  E01-001   5.562/50   e2 Comm.   1.162/50/p   G0 Install   B/A             
05/08/02 Wednesday 1.100/High  E01-001   5.562/50   e2   1.162/50/p   G0 Install   B/A             
05/09/02 Thursday 1.100/High  E01-001   5.562/50   e2   1.162/50/p   G0 Install   B/A             
05/10/02 Friday 1.100/High  E01-001   5.562/50   e2   1.162/50/p   G0 Install   B/A             
05/11/02 Saturday 1.100/High  E01-001   5.562/50   e2   1.162/50/p   G0 Install   B/A             
05/12/02 Sunday 1.100/High  E01-001   3.362/50   e2   1.162/50/p   G0 Install   B/A             
05/13/02 Monday 1.100/High  E01-001   3.362/50   e2   1.162/50/p   G0 Install   B/A             
05/14/02 Tuesday 0.930/High  E01-001   1.912/50   e2   4.702/50/p   G0 Install   B/A             
05/15/02 Wednesday 0.930/High  E01-001   1.912/50   e2   4.702/50/p   G0 Install   A/B             
05/16/02 Thursday 0.930/High  E01-001   2.842/50   e2   4.702/50/p   G0 Install   A/B             
05/17/02 Friday 0.930/High  E01-001   2.842/50   e2   4.702/50/p   G0 Install   A/B             
05/18/02 Saturday 0.930/High  E01-001   2.842/50   e2   4.702/50/p   G0 Install   A/B             
05/19/02 Sunday 0.930/High  E01-001   2.842/50   e2   4.702/50/p   G0 Install   A/B             
05/20/02 Monday 0.930/High  E01-020   2.842/100   e2   4.702/50/p   G0 Install   A/B             
05/21/02 Tuesday 0.930/High  D(e,e'p)   2.842/100   e2   4.702/50/p   G0 Install   A/B             
05/22/02 Wednesday 0.930/High  E01-020   2.842/100   e2   4.702/50/p   G0 Install   A/B             
05/23/02 Thursday 0.930/High  E01-020   2.842/100   e2   4.702/50/p   G0 Install   A/B             
05/24/02 Friday 0.930/High  G0 Beam Tests      –      G0 Install                
05/25/02 Saturday Down  –      –      –                
05/26/02 Sunday Down  –      –      –                
05/27/02 Monday Holiday  –      –      –                
05/28/02 Tuesday Restore  –      –      G0 Install                
05/29/02 Wednesday Restore  –      –      G0 Install                
05/30/02 Thursday Restore  –      –      G0 Install                
05/31/02 Friday 0.930/High  E01-020   2.842/100   e2   4.702/50/p   G0 Install   A/B             
06/01/02 Saturday 0.930/High  E01-020   2.842/100   e2   4.702/50/p   G0 Install   A/B             
06/02/02 Sunday 0.930/High  E01-020   2.842/100   e2   4.702/50/p   G0 Install   A/B             
06/03/02 Monday 0.930/High  E01-020   2.842/100   e2   4.702/50/p   G0 Install   A/B             
06/04/02 Tuesday 0.930/High  E01-020   2.842/100   e2   4.702/50/p   G0 Install   A/B             
06/05/02 Wednesday 0.930/High  E01-020   2.842/100   e2   4.702/50/p   G0 Install   A/B             
06/06/02 Thursday 0.930/High  E01-020   2.842/100   e2   4.702/50/p   G0 Install   A/B             
06/07/02 Friday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   A/B             
06/08/02 Saturday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   B/A             
06/09/02 Sunday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   B/A             
06/10/02 Monday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   B/A             
06/11/02 Tuesday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   B/A             
06/12/02 Wednesday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   B/A             
06/13/02 Thursday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   B/A             
06/14/02 Friday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   B/A             
06/15/02 Saturday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   A/B             
06/16/02 Sunday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   A/B             
06/17/02 Monday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   A/B             
06/18/02 Tuesday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   A/B             
06/19/02 Wednesday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   A/B             
06/20/02 Thursday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   A/B             
06/21/02 Friday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   A/B             
06/22/02 Saturday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   B/A             
06/23/02 Sunday 0.930/High  E01-020   4.702/100   e2   4.702/50/p   G0 Install   B/A             
06/24/02 Monday 0.930/High  E01-020   4.702/100   PRIMEX Tests   4.702/50/p   G0 Install   B/A             
06/25/02 Tuesday 0.930/High  E01-020   4.702/100   PRIMEX Tests   4.702/50/p   G0 Install   B/A             
06/26/02 Wednesday 0.930/High  E01-020   4.702/100   PRIMEX Tests   4.702/50/p   G0 Install   B/A             
06/27/02 Thursday 0.930/High  E01-020   4.702/100   g7 Beam Tests   4.702/50/p   G0 Install   B/A             
06/28/02 Friday Facility Dev.  Facility Dev.      Facility Dev.      Facility Dev.                
06/29/02 Saturday Facility Dev.  Facility Dev.      Facility Dev.      Facility Dev.                
06/30/02 Sunday Facility Dev.  Facility Dev.      Facility Dev.      Facility Dev.                
07/01/02 Monday Facility Dev.  G0 Beam Tests      G0 Beam Tests      G0 Beam Tests                
07/02/02 Tuesday TBA  –      –      –                
07/03/02 Wednesday TBA  –      –      –                
07/04/02 Thursday Holiday  –      –      –                
07/05/02 Friday Down  –      –      –                
07/06/02 Saturday Down  –      –      –                
07/07/02 Sunday Down  –      –      –                
07/08/02 Monday Down  Install Septa      Maintenance      G0 Install               7  
07/09/02 Tuesday Down  Install Septa      Maintenance      G0 Install                
07/10/02 Wednesday Down  Install Septa      Maintenance      G0 Install                
07/11/02 Thursday Down  Install Septa      Maintenance      G0 Install                
07/12/02 Friday Down  Install Septa      Maintenance      G0 Install                
07/13/02 Saturday Down  Install Septa      Maintenance      G0 Install                
07/14/02 Sunday Down  Install Septa      Maintenance      G0 Install                
07/15/02 Monday Down  Install Septa      Maintenance      G0 Install                
07/16/02 Tuesday Down  Install Septa      Maintenance      G0 Install                
07/17/02 Wednesday Down  Install Septa      Maintenance      G0 Install                
07/18/02 Thursday Down  Install Septa      Maintenance      G0 Install                
07/19/02 Friday Down  Install Septa      Maintenance      G0 Install                
07/20/02 Saturday Down  Install Septa      Maintenance      G0 Install                
07/21/02 Sunday Down  Install Septa      Maintenance      G0 Install                
07/22/02 Monday Down  Install Septa      Maintenance      G0 Install                
07/23/02 Tuesday Down  Install Septa      Maintenance      G0 Install                
07/24/02 Wednesday Down  Install Septa      Maintenance      G0 Install                
07/25/02 Thursday Down  Install Septa      Maintenance      G0 Install                
07/26/02 Friday Down  Install Septa      Maintenance      G0 Install                
07/27/02 Saturday Down  Install Septa      Maintenance      G0 Install                
07/28/02 Sunday Down  Install Septa      Maintenance      G0 Install                
07/29/02 Monday Down  Install Septa      Maintenance      G0 Install                
07/30/02 Tuesday Down  Install Septa      Maintenance      G0 Install                
07/31/02 Wednesday Down  Install Septa      Maintenance      G0 Install                
08/01/02 Thursday Down  Install Septa      Maintenance      G0 Install                
08/02/02 Friday Down  Install Septa      Maintenance      G0 Install                
08/03/02 Saturday Down  Install Septa      Maintenance      G0 Install                
08/04/02 Sunday Down  Install Septa      Maintenance      G0 Install                
08/05/02 Monday Down  Install Septa      Maintenance      G0 Install                
08/06/02 Tuesday Down  Install Septa      Maintenance      G0 Install                
08/07/02 Wednesday Down  Install Septa      Maintenance      G0 Install                
08/08/02 Thursday Down  Install Septa      Maintenance      G0 Install                
08/09/02 Friday Down  Install Septa      Maintenance      G0 Install                
08/10/02 Saturday Down  Install Septa      Maintenance      G0 Install                
08/11/02 Sunday Down  Install Septa      Maintenance      G0 Install                
08/12/02 Monday Down  Install Septa      Maintenance      G0 Install                
08/13/02 Tuesday Down  Install Septa      Maintenance      G0 Install                
08/14/02 Wednesday Down  Install Septa      Maintenance      G0 Install                
08/15/02 Thursday Down  Install Septa      Maintenance      G0 Install                
08/16/02 Friday Down  Install Septa      Maintenance      G0 Install                
08/17/02 Saturday Down  Install Septa      Maintenance      G0 Install                
08/18/02 Sunday Down  Install Septa      Maintenance      G0 Install                
08/19/02 Monday Restore  Install Septa      Maintenance      G0 Install                
08/20/02 Tuesday Restore  Install Septa      Maintenance      G0 Install                
08/21/02 Wednesday Restore  Install Septa      Maintenance      G0 Install                
08/22/02 Thursday 1.000/High  Install Septa      Maintenance      G0 Beam Tests   3.056/40             
08/23/02 Friday 1.000/High  Install Septa      Maintenance      G0 Beam Tests   3.056/40             
08/24/02 Saturday 1.000/High  Install Septa      Maintenance      G0 Beam Tests   3.056/40             
08/25/02 Sunday 1.000/High  Install Septa      Maintenance      G0 Beam Tests   3.056/40             
08/26/02 Monday 1.000/High  Install Septa      Maintenance      G0 Beam Tests   3.056/40             
08/27/02 Tuesday 1.000/High  Install Septa      Maintenance      G0 Beam Tests   3.056/40             
08/28/02 Wednesday 1.000/High  Install Septa      Maintenance      G0 Beam Tests   3.056/40             
08/29/02 Thursday 1.000/High  Install Septa      Maintenance      G0 Beam Tests   3.056/40             
08/30/02 Friday 1.000/High  Install Septa      Maintenance      G0 Beam Tests   3.056/40             
08/31/02 Saturday Holiday  Holiday      Holiday      Holiday                
09/01/02 Sunday Holiday  Holiday      Holiday      Holiday                
09/02/02 Monday Holiday  Holiday      Holiday      Holiday                
09/03/02 Tuesday Down  Install Septa      Maintenance      G0 Install                
09/04/02 Wednesday Down  Install Septa      Maintenance      G0 Install                
09/05/02 Thursday Down  Install Septa      Maintenance      G0 Install                
09/06/02 Friday Down  Install Septa      Maintenance      G0 Install                
09/07/02 Saturday Down  Install Septa      Maintenance      G0 Install                
09/08/02 Sunday Down  Install Septa      Maintenance      G0 Install                
09/09/02 Monday Down  Install Septa      Maintenance      G0 Install                
09/10/02 Tuesday Down  Install Septa      Maintenance      G0 Install                
09/11/02 Wednesday Down  Install Septa      Maintenance      G0 Install                
09/12/02 Thursday Down  Install Septa      Maintenance      G0 Install                
09/13/02 Friday Down  Install Septa      Maintenance      G0 Install                
09/14/02 Saturday Down  Install Septa      Maintenance      G0 Install                
09/15/02 Sunday Down  Install Septa      Maintenance      G0 Install                
09/16/02 Monday Restore  Maintenance      Maintenance      G0 Install                
09/17/02 Tuesday Restore  Maintenance      Maintenance      G0 Install                
09/18/02 Wednesday Restore  Maintenance      Maintenance      G0 Install                
09/19/02 Thursday Restore  Maintenance      Maintenance      G0 Install                
09/20/02 Friday 0.750/High  Septa Comm.   0.792/50   g7 Comm   3.042/50   G0 Install       A/B          
09/21/02 Saturday 0.750/High  Septa Comm.   0.792/50   g7 Comm   3.042/50   G0 Install       A/B          
09/22/02 Sunday 0.750/High  Septa Comm.   0.792/50   g7 Comm   3.042/50   G0 Install       A/B          
09/23/02 Monday 0.750/High  Septa Comm.   0.792/50   g7 Comm   3.042/50   G0 Install       B/A          
09/24/02 Tuesday 0.750/High  Septa Comm.   1.542/50   g7 Comm   3.042/50   G0 Install       B/A          
09/25/02 Wednesday 0.750/High  Septa Comm.   1.542/50   g7   3.042/50   G0 Install       A/B          
09/26/02 Thursday 0.750/High  Septa Comm.   1.542/50   g7   3.042/50   G0 Install       A/B          
09/27/02 Friday 0.750/High  Septa Comm.   2.292/50   g7   3.042/50   G0 Install       A/B          
09/28/02 Saturday 0.750/High  Septa Comm.   2.292/50   g7   3.042/50   G0 Install       A/B          
09/29/02 Sunday 0.750/High  Septa Comm.   3.792/50   g7   3.042/50   G0 Install       A/B          
09/30/02 Monday 0.750/High  Septa Comm.   3.792/50   g7   3.042/50   G0 Install       A/B          
10/01/02 Tuesday 0.604/High  Maintenance/Repair      g7   3.054/50   G0 Install       B/A         1 6  
10/02/02 Wednesday 0.604/High  Maintenance/Repair      g7   3.054/50   G0 Install       B/A          
10/03/02 Thursday 1.000/High  D photodisintegration   4.056/50/p   g7   3.056/50   G0 Install       B/A          
10/04/02 Friday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       B/A          
10/05/02 Saturday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       B/A          
10/06/02 Sunday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       B/A          
10/07/02 Monday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       B/A          
10/08/02 Tuesday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       A/B          
10/09/02 Wednesday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       A/B          
10/10/02 Thursday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       A/B          
10/11/02 Friday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       A/B          
10/12/02 Saturday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       A/B          
10/13/02 Sunday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       A/B          
10/14/02 Monday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       A/B          
10/15/02 Tuesday 1.000/High  E00-007   4.056/50/p   g7   3.056/50   G0 Install       A/B          
10/16/02 Wednesday Maintenance  –      –      G0 Install                
10/17/02 Thursday Restore  –      –      G0 Install                
10/18/02 Friday 0.990/High  E01-020   5.006/100   g7   3.056/50   G0 Install                
10/19/02 Saturday 0.990/High  D(e,e'p)   5.006/100   g7   3.056/50   G0 Install       A/B          
10/20/02 Sunday 0.990/High  E01-020   5.006/100   g7   3.056/50   G0 Install       A/B          
10/21/02 Monday 0.990/High  E01-020   5.006/100   g7   3.056/50   G0 Install       A/B          
10/22/02 Tuesday 0.990/High  E01-020   5.006/100   g7   3.056/50   G0 Install       A/B          
10/23/02 Wednesday 0.990/High  E01-020   5.006/100   g7   3.056/50   G0 Install       A/B          
10/24/02 Thursday 0.990/High  E01-020   5.006/100   g7   3.056/50   G0 Install       A/B          
10/25/02 Friday Setup  –   –   –   –   –                
10/26/02 Saturday G0 Comm  –   –   –   –   G0 Commission   3.026/40    C/A/B          
10/27/02 Sunday G0 Comm  –   –   –   –   G0 Commission   3.026/40    C/A/B          
10/28/02 Monday 0.990/High  E01-020   5.006/100   g7   4.016/50   G0 Commission   3.026/40    C/A/B          
10/29/02 Tuesday 0.990/High  E01-020   5.006/100   g7   4.016/50   G0 Commission   3.026/40    C/A/B          
10/30/02 Wednesday 0.990/High  E01-020   5.006/100   g7   4.016/50   G0 Commission   3.026/40/p    C/A/B          
10/31/02 Thursday 0.990/High  E01-020   5.006/100   g7   4.016/50   G0 Commission   3.026/40/p    A/B/C          
11/01/02 Friday 0.990/High  E01-020   5.006/100   g7   4.016/50   G0 Commission   3.026/40/p    A/B/C         1 6  
11/02/02 Saturday 0.990/High  E01-020   5.006/100   g7   4.016/50   G0 Commission   3.026/40/p    A/B/C          
11/03/02 Sunday 0.990/High  E01-020   5.006/100   g7   4.016/50   G0 Commission   3.026/40/p    A/B/C          
11/04/02 Monday 0.990/High  E01-020   5.006/100   g7   2.036/50   G0 Commission   3.026/40/p    A/B/C          
11/05/02 Tuesday 0.990/High  E01-020   5.006/100   g7   2.036/50   G0 Commission   3.026/40/p    A/B/C          
11/06/02 Wednesday 0.990/High  E01-020   5.006/100   g7   2.036/50   G0 Commission   3.026/40/p    A/B/C          
11/07/02 Thursday 0.990/High  E01-020   5.006/100   g7   2.036/50   G0 Commission   3.026/40/p    A/B/C          
11/08/02 Friday 0.990/High  E01-020   5.006/100   g7   2.036/50   G0 Commission   3.026/40/p    A/B/C          
11/09/02 Saturday 0.990/High  E01-020   5.006/100   g7   2.036/50   G0 Commission   3.026/40/p    B/C/A          
11/10/02 Sunday 0.990/High  E01-020   5.006/100   g7   2.036/50   G0 Commission   3.026/40/p    B/C/A          
11/11/02 Monday 0.990/High  E01-020   5.006/100   g7   2.036/50   G0 Commission   3.026/40/p    B/C/A          
11/12/02 Tuesday 0.990/High  E01-020   5.006/100   g7   2.036/50   G0 Commission   3.026/40/p    B/C/A          
11/13/02 Wednesday 0.990/High  E01-020   5.006/100   g7   2.036/50   G0 Commission   3.026/40/p    B/C/A          
11/14/02 Thursday 0.990/High  E01-020   5.006/100   Install e1   2.036/50   G0 Commission   3.026/40/p    C/A          
11/15/02 Friday 0.990/High  E01-020   5.006/100   Install e1   2.036/50   G0 Commission   3.026/40/p    C/A          
11/16/02 Saturday 0.990/High  Facility Dev.   5.006/100   Commission e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
11/17/02 Sunday 0.990/High  Facility Dev.   5.006/100   Commission e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
11/18/02 Monday 0.990/High  Install pol 3He target      Commission e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
11/19/02 Tuesday 0.990/High  Install pol 3He target      Commission e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
11/20/02 Wednesday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
11/21/02 Thursday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
11/22/02 Friday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
11/23/02 Saturday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    C/B          
11/24/02 Sunday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    C/B          
11/25/02 Monday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    C/B          
11/26/02 Tuesday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    C/B          
11/27/02 Wednesday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    C/B          
11/28/02 Thursday Holiday  Holiday      Holiday      Holiday                
11/29/02 Friday Holiday  Holiday      Holiday      Holiday                
11/30/02 Saturday Holiday  Holiday      Holiday      Holiday                
12/01/02 Sunday Holiday  Holiday      Holiday      Holiday               1 6  
12/02/02 Monday Restore  Install pol 3He target      –      –                
12/03/02 Tuesday Restore  Install pol 3He target      –      –                
12/04/02 Wednesday Restore  Install pol 3He target      –      –                
12/05/02 Thursday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    C/B          
12/06/02 Friday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    C/B          
12/07/02 Saturday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    C/B          
12/08/02 Sunday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    C/B          
12/09/02 Monday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
12/10/02 Tuesday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
12/11/02 Wednesday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
12/12/02 Thursday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
12/13/02 Friday 0.990/High  Install pol 3He target      e1   1.046/50/p   G0 Commission   3.026/40/p    B/C          
12/14/02 Saturday 0.990/High  Install pol 3He target      e1   2.036/50/p   G0 Commission   3.026/40/p    B/C          
12/15/02 Sunday 0.990/High  Install pol 3He target      e1   2.036/50/p   G0 Commission   3.026/40/p    B/C          
12/16/02 Monday 0.990/High  Install pol 3He target      e1   2.036/50/p   G0 Commission   3.026/40/p    C/B          
12/17/02 Tuesday 0.990/High  Install pol 3He target      e1   2.036/50/p   G0 Commission   3.026/40/p    C/B          
12/18/02 Wednesday 0.990/High  Install pol 3He target      e1   2.036/50/p   G0 Commission   3.026/40/p    C/B          
12/19/02 Thursday Facility Dev  Install pol 3He target      Facility Dev      Facility Dev                
12/20/02 Friday Facility Dev  Install pol 3He target      Facility Dev      Facility Dev                
12/21/02 Saturday Holiday  Holiday      Holiday      Holiday                
12/22/02 Sunday Holiday  Holiday      Holiday      Holiday                
12/23/02 Monday Holiday  Holiday      Holiday      Holiday                
12/24/02 Tuesday Holiday  Holiday      Holiday      Holiday                
12/25/02 Wednesday Holiday  Holiday      Holiday      Holiday                
12/26/02 Thursday Holiday  Holiday      Holiday      Holiday                
12/27/02 Friday Holiday  Holiday      Holiday      Holiday                
12/28/02 Saturday Holiday  Holiday      Holiday      Holiday                
12/29/02 Sunday Holiday  Holiday      Holiday      Holiday                
12/30/02 Monday Holiday  Holiday      Holiday      Holiday                
12/31/02 Tuesday Holiday  Holiday      Holiday      Holiday