2009 August Accelerator Schedule

Updated October, 2009

Date Weekday Accelerator Hall A Hall A Hall B Hall B Hall C Hall C Priority PASS Notes
    GeV/pass/Pol Experiment GeV/mA Experiment GeV/nA Experiment GeV/mA Hall A/B/C 1-10
08/01/09 Saturday Down  HAPPExIII Install            HKS Install                
08/02/09 Sunday Down  HAPPExIII Install            HKS Install                
08/03/09 Monday Down  HAPPExIII Install            HKS Install                
08/04/09 Tuesday Down  HAPPExIII Install            HKS Install                
08/05/09 Wednesday Down  HAPPExIII Install            HKS Install                
08/06/09 Thursday Down  HAPPExIII Install            HKS Install                
08/07/09 Friday Down  HAPPExIII Install            HKS Install                
08/08/09 Saturday Down  HAPPExIII Install            HKS Install                
08/09/09 Sunday Down  HAPPExIII Install            HKS Install                
08/10/09 Monday Down  HAPPExIII Install            HKS Install                
08/11/09 Tuesday Down  HAPPExIII Install            HKS Install                
08/12/09 Wednesday Down  HAPPExIII Install            HKS Install                
08/13/09 Thursday Down  HAPPExIII Install            HKS Install                
08/14/09 Friday Down  HAPPExIII Install            HKS Install                
08/15/09 Saturday Down  HAPPExIII Install            HKS Install                
08/16/09 Sunday Down  HAPPExIII Install            HKS Install                
08/17/09 Monday Restore                              
08/18/09 Tuesday Restore                              
08/19/09 Wednesday Collab Tests                             7  
08/20/09 Thursday Collab Tests                              
08/21/09 Friday 1.14  Commission   1.204/100/p   eg1-dvcs   5.764/50/p   HKS Comm   2.344/50    A/C/B     1/5/2      
08/22/09 Saturday 1.14  E05-109   1.204/100/p   eg1-dvcs   5.764/50/p   HKS Comm   2.344/50    A/C/B     1/5/2      
08/23/09 Sunday 1.14  Happex III   1.204/100/p   eg1-dvcs   5.764/50/p   HKS Comm   2.344/50    C/A/B     1/5/2      
08/24/09 Monday 1.14  Commission   1.204/100/p   eg1-dvcs   5.764/50/p   HKS Comm   2.344/50    C/A/B     1/5/2      
08/25/09 Tuesday 1.14  Commission   3.484/100/p   eg1-dvcs   5.764/50/p   HKS Comm   2.344/50    C/A/B     3/5/2      
08/26/09 Wednesday 1.14  E05-109   3.484/100/p   eg1-dvcs   5.764/50/p   HKS Comm   2.344/50    B/C/A     3/5/2      
08/27/09 Thursday 1.14  E05-109   3.484/100/p   eg1-dvcs   5.764/50/p   HKS Comm   2.344/50    B/C/A     3/5/2      
08/28/09 Friday 1.14  E05-109   3.484/100/p   eg1-dvcs   5.764/50/p   HKS Comm   2.344/50    A/C/B     3/5/2      
08/29/09 Saturday 1.14  E05-109   3.484/100/p   eg1-dvcs   5.764/50/p   HKS Comm   2.344/50    A/C/B     3/5/2      
08/30/09 Sunday 1.14  E05-109   3.484/100/p   eg1-dvcs   5.764/50/p   HKS Comm   2.344/50    A/C/B     3/5/2      
08/31/09 Monday 1.14  E05-109   3.484/100/p   eg1-dvcs   5.764/50/p   HKS Comm   2.344/50    C/A/B     3/5/2      