| Event |
Target |
Typical |
Call for Beam Requests (Spring Cycle) |
6 weeks before Scheduling Committee Starts work |
January 15 |
| Beam Requests Due |
1 weeks before Scheduling Committee starts work |
Late-February |
Scheduling Committee Begins Work |
March 1 |
March 1 |
New Accelerator Schedule Draft Released |
1 month after Scheduling Committee begins work |
Target is Mid-April; typical is Mid-April |
Public Comment Session of Scheduling Committee |
1 month after Draft Schedule is released |
Target is Mid-April; typical is Mid-April |
New Accelerator Schedule Released as Final |
Day after Public comment session |
|
Call for Beam Requests (Fall cycle) |
6 weeks before Scheduling Committee starts work |
July 15 |
| Beam Requests Due |
1 week before Scheduling Committee starts work |
Mid-August |
Scheduling Committee begins work |
September 1 |
September 1 |
New Accelerator Schedule Draft Released |
1 month after Scheduling Committee begins work |
Target is early October; typical is Mid-October |
Public Comment Session of Scheduling Committee |
1 week after Draft Schedule is released |
Target is Mid-October; typical is late October |
New Accelerator Schedule Released as Final |
Day after Public comment session |
|