Owl Shift, Saturday, August 24, 2002 Shift Leader: Eugene, Workers: Sam, Marianna 12:15 Yar wanted controlled access. MCC has problems with PSS, they cannot let us in until PSS expert comes and fixes the problem. 2:30 Still no beam. Sam went down the Hall to check communication with LMS. 4:00 Last word from MCC. They finally tuned injector. Their plan is to establish CW beam for the Hall C. They estimate this exercise as one hour. If they succeed, then they will try to deliver us 5 pass beam. If not, we might be out of the game. 4:05 Sam is in the hall again. He cannot talk to LMS PC remotely.