Attending: Ashot, Dustin, Dave L, Raphael, Itaru, Phillip, Dan Dale, Abdellah, Yar, Mark, Eric
Phone: Sam, Liping, Dan Sober

Announcements:
Dan D: UKY tech scheduled to be on site for a month of soldering.

Ashot: We’re missing ~60 HV sockets, along with the missing 50 crystals and PMTs. Looks like someone’s making a prototype, so keep your eyes open.
Oleg’s visa is extended until November so he’ll be around to finish the soldering.

Dan: Discussion of October run goals. We’re scheduled after DVCS. Assignment of prerun tasks.

Engineering (from Dave K):
PrimEx deck scheduled to go in on September 4.
Work proceeding on lift.

Hardware:
Ashot: Discussion of hardware plan. See latest schedule for details.