Pre-Installation Requirements
For all changes, additions, and enhancements to the standard*
equipment (including detector systems) and for new equipment,
identify for each area listed below the following specific items: who will be doing the work (User/J Lab staff/contractor); the
manweeks required for the work; when the work will be done; and the work location.
* See the Hall leader for a list and description of standard equipment.
** Complete requirements must be provided for equipment requiring JLab engineering and design.
*** Complete drawings must be provided for equipment to be fabricated by JLab
INSTALLATION REQUIREMENTS
For each item below, identify days to complete installation, type of manpower (i.e. welder, electrician, programmer, etc.),
manweeks of effort for each subsystem, and the man effort (User/J Lab staff/contractor).
|
Equipment to be installed |
Time (days) (Assuming 100% efficient operation) |
Type of Manpower |
Man-Weeks of Effort |
User/JLab Staff/Contractor |
Alignment |
|
|
|
|
|
Electrical |
|
|
|
|
|
Mechanical |
|
|
|
|
|
Detector |
|
|
|
|
|
Target |
|
|
|
|
|
Beamline (including Radcon) |
PRad vacuum can
|
7 days |
engineering |
5 |
Hall-B Engineering |
Modifications to Standard Equip |
|
|
|
|
|
Slow Controls (EPICS) |
|
|
|
|
|
Other |
|
|
|
|
|
DECOMMISSIONING and DEINSTALLATION
List all items requiring decommissioning and/or deinstallation following
your experiment. For each item indicate type of manpower
(lift operator, welder, electrician, etc.), man-weeks of effort for each
subsystem, and the man effort (User/J Lab staff/contractor).
Obtain hall leader's concurrence that the information in this Appendix is understood and adequate for schedule planning