Person: Dipangkar Dutta (ddutta@jlab.org)
Status: Saved

ORG: PHALLC
Date:


JSA
THOMAS JEFFERSON NATIONAL ACCELERATOR FACILITY
12000 Jefferson Avenue
Newport News, VA 23606
Phone: (757) 269-7100

Beam Schedule 51806

Experiment Title: High Precision Measurement of the Proton Charge Radius
ID: E12-11-106
100%
N/A
N/A
Collapse All

Proposed Commissioning and Run Schedule

Enter data in preferred time sequence for energies, current, targets, beam conditions, etc, for the entire Run Plan including commissioning. Under "Special Requirements" below, note all critical scheduling needs, e.g., a certain set of energies must be run before another set, etc.

NOTE: INDICATE ALL MAJOR EQUIPMENT CHANGES, BREAKS, OR MAINTENANCE DAYS, ETC. ON SEPARATE LINES.
Days Setup Number from Radiation Budget Form Tag No. Special Requirements (including any variance from standard beam conditions)
2
4
Target commissioning
3.5
3
1.1 GeV beam with Hall-B Tagger and HyCal mounted on transporter
2
1
1.1 GeV beam with halo < 10^-7 of peak and Hycal on cart
2
2
2.2 GeV beam with halo < 10^-7 of peak and Hycal on cart

*Assume 100% efficiency for accelerator and experimental operations. ** Provide setup numbers as indicated on the Radiation Budget Form. The sum of the run days must be = the PAC-approved days. Consult Accelerator Liaison Physicist H. Areti for current beam capabilities.

Proposed Apparatus or Beam Development Run Schedule

Fill in one of these forms for each proposed development activity. Enter data in preferred time sequence for energies, current, targets, beam conditions, etc, for the entire Development Run. Under "Special Requirements" below, note all critical scheduling needs, e.g., a certain set of energies must be run before another set, etc.

Calibration of the HyCal with tagged photon beam which scans the entire HyCal detector

NOTE: INDICATE ALL MAJOR EQUIPMENT CHANGES, BREAKS, INSTALLATION OR SETUP, OR MAINTENANCE DAYS, ETC. ON SEPARATE LINES.

Days Setup Number** from Radiation Budget Form Special Requirements Include any variance from standard beam conditions, special developmental setups, special beamline or experimental equipment, and associated setup and installation times in the hall, etc
3.5
3
1.1 GeV beam with Hall-B Tagger and HyCal mounted on transporter

*Assume 100% efficiency for accelerator and experimental operations. ** Provide setup numbers as indicated on the Radiation Budget Form

Pre-Installation Requirements

For all changes, additions, and enhancements to the standard* equipment (including detector systems) and for new equipment, identify for each area listed below the following specific items: who will be doing the work (User/J Lab staff/contractor); the manweeks required for the work; when the work will be done; and the work location.

Beam line design to incorporate the new PRad vacuum box
stands for the PRad vacuum box
* See the Hall leader for a list and description of standard equipment. ** Complete requirements must be provided for equipment requiring JLab engineering and design. *** Complete drawings must be provided for equipment to be fabricated by JLab
INSTALLATION REQUIREMENTS

For each item below, identify days to complete installation, type of manpower (i.e. welder, electrician, programmer, etc.), manweeks of effort for each subsystem, and the man effort (User/J Lab staff/contractor).

Equipment to be installed Time (days) (Assuming 100% efficient operation) Type of Manpower Man-Weeks of Effort User/JLab Staff/Contractor
Alignment
Electrical
Mechanical
Detector
Target
Beamline (including Radcon)
PRad vacuum can
7 days
engineering
5
Hall-B Engineering
Modifications to Standard Equip
Slow Controls (EPICS)
Other
DECOMMISSIONING and DEINSTALLATION

List all items requiring decommissioning and/or deinstallation following your experiment. For each item indicate type of manpower (lift operator, welder, electrician, etc.), man-weeks of effort for each subsystem, and the man effort (User/J Lab staff/contractor).

Equipment to be removed Equipment Location Time (days) (Assuming 100% efficient operation) Type of Manpower Man-Weeks of Effort User/JLab Staff/Contractor
HyCal calorimeter
PRad vacuum box

Obtain hall leader's concurrence that the information in this Appendix is understood and adequate for schedule planning

Target Systems

Windowless hydrogen gas flow target
target installation - 7 days with vacuum and tech. manpower from the the target group

Data Acquisition

Indicate the anticipated data acquisition rates (peak and averages) as well as the anticipated total data going to media.

2
0.5
10000

User Staffing Profile

For each phase of the experiment (design, construction, testing, commissioning, running, deinstallation, and data reduction and analysis), indicate the number of onsite FTE users you anticipate, the incremental office and laboratory space required (i.e., space not already provided to collaboration members), and your desired location.

Collaboration FTEs at JLab Storage Space Laboratory Space How long is space needed? Comments
Design
Construction
Testing
Commissioning
8
Running
20
Deinstallation
8
Decommission
5
Data
3

If you require new office space, you need to contact the User Liaison Office at 757.269.6388 or users@jlab.org for additional information
Attachments
There are no attachments
Signatures
There are no signatures