Notes and Action Items from Hall C Compton meeting: 3/30/2009 Attendees: Ron, Katherine, Butch, Ernie, Chris, and Dave 0. We will meet by phone again next Monday (April 6) at 1:30 pm. 1. Last week, Katherine and Ron provided example drawings in the format JLab usually expects. Drawings showing the (x,y,z) positions of the Compton entrance and exit also provided. 2. Delivery of final drawings for dipoles, stands and vacuum chambers has been delayed until April 10 (Chris was diverted for other work). At present, machine drawings for the dipoles and stands exist. Layout drawings do not yet include beam diagnostics or vacuum system instrumentation. Some concern expressed at JLab about dipole height: stand fabrication will not start until this has been resolved to everyone's satisfaction. 3. Ernie still needs to touch base with John Heckman. Date for final vacuum design completion still TBD. 4. Interaction region: Final decision on whether Hall A design will fit in Hall C interaction region still pending based on final MIT layout. Dave G. needs to check with Jay about mirror geometry (5 mm from electron beam). During the meeting, it was decided (re-iterated) that MIT will handle the Interaction Region, while JLab will handle the laser enclosure. To first order, the Interaction Region design can be based on the Hall A design. Place of fabrication to be decided. Schedule from last week still holds: 1. Check Hall A concept, verify that it fits in Hall C region (finish April 10) 2. Fabricate Hall A cavity design (April-June 15). 3. Put Hall A design on laser table (June-July) 4. Iterate design (April-September) 5. Final fabrication (September-December)