Plan for 4/13 and 4/14 FPP commissioning.
  1. Beam tuning and Moeller for 3.335 GeV beam. 20 hours

  2. Do alignment of chambers . About an hour of data.

  3. Do measurement at Q2 = 0.8 to measure helicity of beam to 3% or h = 0.4 +- 0.012 . At the same time remeasure (Ge/Gm to 4% . Measurement will take 6 hours. Assume 50% uptime for 12 hours total.

    Ebeam Q2 pp E' qe Tp qp Pt Pl
    3.35500 0.8 0.9908 2.929 16.40 0.426 56.593 -.1485 0.2002

    Q2 I(muA) ds/dW (cm2/sr) Rate(/sec) time (hr) Ac eff
    0.80 12.00 0.10843E-30 1946.43 6.0 0.3762 .1084

    Q2 c (deg) hAPlsin(c) hAPt Da D(Ge/Gm)/Ge/Gm Dh
    0.80 117.33 0.02676 -0.02235 0.00066 0.039 .012

  4. Do measurements at +-3% delta to measure the false asymmetries in different parts of the focal plane. To get error of 0.001 need 2.5 hours. 1/2 hour for magnet changes. Assuming 50% uptime then 11 hours total.


File translated from TEX by TTH, version 0.9. If problems having netscape print symbols do the following :

(1) Add the following line to your .Xdefaults (or .Xresources):

Netscape*documentFonts.charset*adobe-fontspecific:   iso-8859-1

(2) $ xrdb .Xdefaults or else restart the X server.
(3) Restart Netscape.