| From |
|
To |
Activity |
|
|
|
|
28 Feb |
Preceding experiment (Gao) ends
|
| 1 Mar |
- |
14 Mar |
Remove 3He target
|
|
|
|
8 Mar |
Accelerator development
|
|
|
9 Mar |
- |
10 Mar |
Accelerator maintenance
|
|
|
| 15 Mar |
- |
1 Apr |
Install cryotarget
|
|
|
|
22 Mar |
Accelerator development
|
|
|
23 Mar |
- |
24 Mar |
Accelerator maintenance
|
|
|
|
|
25 Mar |
Accelerator development
|
|
|
| 2 Apr |
- |
6 Apr |
Commission. 3.362 GeV, 50 uA, strained cathode. Ends with Day shift 6 Apr.
|
| 6 Apr |
- |
28 May |
HAPPEX production. 3.362 GeV, 50 uA, strained
cathode. Begins with Swing shift 6 Apr.
- 6 Apr - 17 Apr
- Run coordinator: Bob Michaels
Analysis coordinator: Rich Holmes
|
|
13 Apr |
- |
14 Apr |
Accelerator maintenance
|
|
|
- 17 Apr - 27 Apr
- Run coordinator: Rich Holmes
Analysis coordinator: Brian Humensky
|
|
27 Apr |
- |
28 Apr |
Accelerator maintenance
|
|
|
- 27 Apr - 7 May
- Run coordinator: Etienne Burtin
Analysis coordinator: Bill Kahl
- 7 May - 18 May
- Run coordinator: Rhett Woo
|
|
|
|
11 May |
Accelerator development
|
|
|
12 May |
- |
13 May |
Accelerator maintenance
|
|
|
- 18 May - 28 May
- Run coordinator: David Lhuillier
|
| 29 May |
- |
4 Jul |
Accelerator down for polarized source upgrade
|
| 5 Jul |
- |
7 Jul |
Restore
|
| 8 Jul |
- |
30 Jul |
HAPPEX production. 3.362 GeV, 50 uA, strained
cathode.
|
|
- 8 Jul - 15? Jul
- Run coordinator: Krishna Kumar
Analysis coordinator: Baris Tonguc
|
|
|
|
20 Jul |
Accelerator development
|
|
|
21 Jul |
- |
22 Jul |
Accelerator maintenance
|
|
|
| 31 Jul |
- |
3 Aug |
Commission. 3.362 GeV, 50 uA, strained
cathode. (Not yet allocated.)
|
|
|
4 Aug |
Accelerator development
|
| 5 Aug |
- |
6 Aug |
Accelerator maintenance
|
|
|
7 Aug |
Commission. 0.811 GeV, 50 uA, strained cathode. (Not yet allocated.)
|
|
|
8 Aug |
Begin Gilman/Holt and G/H/M experiments
|