Microsoft Project Exported Information

g0_feb02





Project Start:
Project Finish:
Fri 3/1/02
Thu 9/5/02


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
Gen Removal
13.5 dMon 3/4/02Thu 3/21/02Contractor,Hall C Techs0%
2
Finish Tes & take optics data
1 dMon 3/4/02Mon 3/4/02 0%
3
Vent HMS
2 hrsTue 3/5/02Tue 3/5/02 0%
4
degauss & disconnect bz
1 dTue 3/5/02Wed 3/6/02 0%
5
Remove ds beamline
1 dWed 3/6/02Thu 3/7/02 0%
6
Move HMS to ~35 deg
2 hrsTue 3/5/02Tue 3/5/02 0%
7
Move dump blocks & shadow shield
1 dThu 3/7/02Fri 3/8/02 0%
8
Warmup target
1 dTue 3/5/02Tue 3/5/02 0%
9
As found Gen survey
1 dWed 3/6/02Wed 3/6/02 0%
10
Disconnect target
2 dThu 3/7/02Fri 3/8/02Target group0%
11
Survey target on floor
2 dWed 3/13/02Fri 3/15/02 0%
12
Remove upper access walkway
0.5 dMon 3/11/02Mon 3/11/02 0%
13
Straighten chicane
1 dWed 3/20/02Thu 3/21/02 0%
14
Remove target
2 dMon 3/11/02Wed 3/13/02 0%
15
Remove tgt deck
1 dWed 3/13/02Thu 3/14/02 0%
16
Remove tgt equip. deck
2 dThu 3/14/02Mon 3/18/02 0%
17
Move HMS way out
2 hrsMon 3/18/02Mon 3/18/02 0%
18
Install standard Hall C girder
4 dThu 3/14/02Wed 3/20/02 0%
19      
20
Remove scaffolding
1 dMon 3/4/02Mon 3/4/02 0%
21
FW to beamline
1 hrFri 3/8/02Fri 3/8/02 0%
22
Iterate octant alignment
4 dMon 3/11/02Fri 3/15/02 0%
23
Install cryoboom
1 dFri 3/8/02Mon 3/11/02 0%
24      
25
Install B-can flex lines
3 dTue 3/5/02Thu 3/7/02 0%
26
Tee into trunk lines
5 dMon 3/11/02Fri 3/15/02 0%
27
Place HX & valve box cans on C-can platform
1 dMon 3/25/02Mon 3/25/02 0%
28
C-can platform plumbing
5 dTue 3/26/02Mon 4/1/02 0%
29
A-can repair
15 dMon 3/18/02Fri 4/5/02 0%
30
Install SMS power supply
12 dTue 3/12/02Thu 3/28/02BWXT0%
31
G0 electric power
2 dTue 3/12/02Thu 3/14/02Contractor0%
32
Energy Dump
2 dTue 3/12/02Thu 3/14/02BWXT0%
33
LCW for SMS PS
2 dThu 3/14/02Mon 3/18/02Accel. Mech.0%
34
SMS DC & Controls
10 dThu 3/14/02Thu 3/28/02BWXT0%
35
Fire protection
5 dThu 3/28/02Thu 4/4/02Contractor0%
36
SMS stand
2 dThu 3/21/02Fri 3/22/02Hall C Techs0%
37
Align SMS stand
1 dMon 3/25/02Mon 3/25/02Accel. Align.0%
38      
39
ODH monitoring
5 dThu 3/21/02Thu 3/28/02Hall C Electrical0%
40
Unload & rotate SMS
1 dFri 3/22/02Fri 3/22/02 0%
41
Move SMS into Hall
1 dMon 3/25/02Mon 3/25/02 0%
42
Rotate SMS & place on stand
2 dTue 3/26/02Wed 3/27/02 0%
43
Remove shipping fixtures
2 dThu 3/28/02Fri 3/29/02 0%
44
Place end caps
1 dMon 4/1/02Mon 4/1/02 0%
45
Install SMS platform
3 dTue 4/2/02Thu 4/4/02 0%
46
Install SMS cryolines
2 dFri 4/5/02Mon 4/8/02 0%
47
SMS Photogrammetry
5 dTue 4/9/02Mon 4/15/02Contractor0%
48
Restore SMS can
2 dFri 4/5/02Mon 4/8/02 0%
49
Place SMS DC buss
2 dFri 4/5/02Mon 4/8/02 0%
50
Lay SMS control cables
3 dTue 4/9/02Thu 4/11/02 0%
51
Place tgt gas panel
1 dThu 4/4/02Thu 4/4/02 0%
52
Connect tgt gas panel to perim. Lines
3 dFri 4/5/02Tue 4/9/02 0%
53
Install 2' gate valve
1 dFri 4/5/02Fri 4/5/02 0%
54
Connect SMS cryolines
2 dMon 4/8/02Tue 4/9/02 0%
55
Place ds shield wall
1 dWed 4/10/02Wed 4/10/02 0%
56
Align FW to beamline
2 dThu 4/11/02Fri 4/12/02 0%
57
Align SMS
3 d?Mon 4/15/02Wed 4/17/02 0%
58
Mate SMS & FW
2 dThu 4/18/02Fri 4/19/02 0%
59      
60
Place target on SMS
1 dMon 4/22/02Mon 4/22/02 0%
61
Connect target control cables
1 dTue 4/23/02Tue 4/23/02 0%
62
Plumb target gas&cryo lines
3 dTue 4/23/02Thu 4/25/02 0%
63
Align target to SMS
2 dFri 4/26/02Mon 4/29/02Accel. Align.0%
64
Purge tgt gas & cryolines
4 dFri 4/26/02Wed 5/1/02 0%
65
Install SMS-GV beamline
2 dThu 4/18/02Fri 4/19/02 0%
66
Pumpout & leakcheck SMS/tgt
5 dFri 4/26/02Thu 5/2/02 0%
67
Commission cryosystem
3 dFri 5/3/02Tue 5/7/02 0%
68
Target safety tests (Neon)
7 dWed 5/8/02Thu 5/16/02 0%
69
Target LH2 tests & commissioning
15 dFri 5/17/02Thu 6/6/02 0%
70
Purge SMS gas & cryolines
7 dFri 6/7/02Mon 6/17/02 0%
71
Install GV to dump beamline
2 dFri 6/7/02Mon 6/10/02Hall C Techs0%
72
Install u.s. girder stands
2 dMon 6/3/02Tue 6/4/02Accel. Mech.0%
73
Resurvey
3 dFri 6/7/02Tue 6/11/02Accel. Align.0%
74
Cool down SMS
23 dTue 6/18/02Thu 7/18/02BWXT0%
75
Install G0 cave
5 dFri 7/19/02Thu 7/25/02Hall C Techs0%
76
Install long girder
5 dWed 6/5/02Tue 6/11/02Accel. Mech.0%
77
Align long girder to beamline
2 dWed 6/5/02Thu 6/6/02Accel. Align.0%
78
Cable long girder
3 dWed 6/5/02Fri 6/7/02Accel. Elec.0%
79
Test long girder
2 dMon 6/10/02Tue 6/11/02Accel. Elec.0%
80
Install u.s. beampipe
11 dWed 6/12/02Wed 6/26/02Accel. Mech.0%
81
Install & align short girder
7 dWed 6/12/02Thu 6/20/02 0%
82
Install u.s. beampipes
2 dFri 6/21/02Mon 6/24/02 0%
83
Align u.s. beampipe
1 dTue 6/25/02Tue 6/25/02Accel. Align.0%
84
Pump out u.s. beamline
1 dWed 6/26/02Wed 6/26/02Accel. Mech.0%
85
SMS commissioning & tests
25 dFri 7/19/02Thu 8/22/02BWXT0%
86
SOS Stair Mods
15 dThu 6/27/02Wed 7/17/02 0%
87
Commission G0 beam & girder
9 dMon 8/26/02Thu 9/5/02Experimenters0%

Resources


IDNameGroupMax UnitsPeak Units
1Contractor 100%200%
2  100%0%
3Hall C Techs 100%200%
4Accel. Mech. 100%200%
5BWXT 100%200%
6Hall C Electrical 100%100%
7Accel. Align. 100%100%
8Target group 100%100%
9Accel. Elec. 100%100%
10Experimenters 100%100%

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
1Gen RemovalContractor108 hrsMon 3/4/02Thu 3/21/020%
1Gen RemovalHall C Techs108 hrsMon 3/4/02Thu 3/21/020%
10Disconnect targetTarget group16 hrsThu 3/7/02Fri 3/8/020%
30Install SMS power supplyBWXT96 hrsTue 3/12/02Thu 3/28/020%
31G0 electric powerContractor16 hrsTue 3/12/02Thu 3/14/020%
32Energy DumpBWXT16 hrsTue 3/12/02Thu 3/14/020%
33LCW for SMS PSAccel. Mech.16 hrsThu 3/14/02Mon 3/18/020%
34SMS DC & ControlsBWXT80 hrsThu 3/14/02Thu 3/28/020%
35Fire protectionContractor40 hrsThu 3/28/02Thu 4/4/020%
36SMS standHall C Techs16 hrsThu 3/21/02Fri 3/22/020%
37Align SMS standAccel. Align.8 hrsMon 3/25/02Mon 3/25/020%
39ODH monitoringHall C Electrical40 hrsThu 3/21/02Thu 3/28/020%
47SMS PhotogrammetryContractor40 hrsTue 4/9/02Mon 4/15/020%
63Align target to SMSAccel. Align.16 hrsFri 4/26/02Mon 4/29/020%
71Install GV to dump beamlineHall C Techs16 hrsFri 6/7/02Mon 6/10/020%
72Install u.s. girder standsAccel. Mech.16 hrsMon 6/3/02Tue 6/4/020%
73ResurveyAccel. Align.24 hrsFri 6/7/02Tue 6/11/020%
74Cool down SMSBWXT184 hrsTue 6/18/02Thu 7/18/020%
75Install G0 caveHall C Techs40 hrsFri 7/19/02Thu 7/25/020%
76Install long girderAccel. Mech.40 hrsWed 6/5/02Tue 6/11/020%
77Align long girder to beamlineAccel. Align.16 hrsWed 6/5/02Thu 6/6/020%
78Cable long girderAccel. Elec.24 hrsWed 6/5/02Fri 6/7/020%
79Test long girderAccel. Elec.16 hrsMon 6/10/02Tue 6/11/020%
80Install u.s. beampipeAccel. Mech.88 hrsWed 6/12/02Wed 6/26/020%
83Align u.s. beampipeAccel. Align.8 hrsTue 6/25/02Tue 6/25/020%
84Pump out u.s. beamlineAccel. Mech.8 hrsWed 6/26/02Wed 6/26/020%
85SMS commissioning & testsBWXT200 hrsFri 7/19/02Thu 8/22/020%
87Commission G0 beam & girderExperimenters72 hrsMon 8/26/02Thu 9/5/020%