| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Gen Removal | 13.5 d | Mon 3/4/02 | Thu 3/21/02 | Contractor,Hall C Techs | 0% |
| 2 | Finish Tes & take optics data | 1 d | Mon 3/4/02 | Mon 3/4/02 | | 0% |
| 3 | Vent HMS | 2 hrs | Tue 3/5/02 | Tue 3/5/02 | | 0% |
| 4 | degauss & disconnect bz | 1 d | Tue 3/5/02 | Wed 3/6/02 | | 0% |
| 5 | Remove ds beamline | 1 d | Wed 3/6/02 | Thu 3/7/02 | | 0% |
| 6 | Move HMS to ~35 deg | 2 hrs | Tue 3/5/02 | Tue 3/5/02 | | 0% |
| 7 | Move dump blocks & shadow shield | 1 d | Thu 3/7/02 | Fri 3/8/02 | | 0% |
| 8 | Warmup target | 1 d | Tue 3/5/02 | Tue 3/5/02 | | 0% |
| 9 | As found Gen survey | 1 d | Wed 3/6/02 | Wed 3/6/02 | | 0% |
| 10 | Disconnect target | 2 d | Thu 3/7/02 | Fri 3/8/02 | Target group | 0% |
| 11 | Survey target on floor | 2 d | Wed 3/13/02 | Fri 3/15/02 | | 0% |
| 12 | Remove upper access walkway | 0.5 d | Mon 3/11/02 | Mon 3/11/02 | | 0% |
| 13 | Straighten chicane | 1 d | Wed 3/20/02 | Thu 3/21/02 | | 0% |
| 14 | Remove target | 2 d | Mon 3/11/02 | Wed 3/13/02 | | 0% |
| 15 | Remove tgt deck | 1 d | Wed 3/13/02 | Thu 3/14/02 | | 0% |
| 16 | Remove tgt equip. deck | 2 d | Thu 3/14/02 | Mon 3/18/02 | | 0% |
| 17 | Move HMS way out | 2 hrs | Mon 3/18/02 | Mon 3/18/02 | | 0% |
| 18 | Install standard Hall C girder | 4 d | Thu 3/14/02 | Wed 3/20/02 | | 0% |
| 19 | | | | | | |
| 20 | Remove scaffolding | 1 d | Mon 3/4/02 | Mon 3/4/02 | | 0% |
| 21 | FW to beamline | 1 hr | Fri 3/8/02 | Fri 3/8/02 | | 0% |
| 22 | Iterate octant alignment | 4 d | Mon 3/11/02 | Fri 3/15/02 | | 0% |
| 23 | Install cryoboom | 1 d | Fri 3/8/02 | Mon 3/11/02 | | 0% |
| 24 | | | | | | |
| 25 | Install B-can flex lines | 3 d | Tue 3/5/02 | Thu 3/7/02 | | 0% |
| 26 | Tee into trunk lines | 5 d | Mon 3/11/02 | Fri 3/15/02 | | 0% |
| 27 | Place HX & valve box cans on C-can platform | 1 d | Mon 3/25/02 | Mon 3/25/02 | | 0% |
| 28 | C-can platform plumbing | 5 d | Tue 3/26/02 | Mon 4/1/02 | | 0% |
| 29 | A-can repair | 15 d | Mon 3/18/02 | Fri 4/5/02 | | 0% |
| 30 | Install SMS power supply | 12 d | Tue 3/12/02 | Thu 3/28/02 | BWXT | 0% |
| 31 | G0 electric power | 2 d | Tue 3/12/02 | Thu 3/14/02 | Contractor | 0% |
| 32 | Energy Dump | 2 d | Tue 3/12/02 | Thu 3/14/02 | BWXT | 0% |
| 33 | LCW for SMS PS | 2 d | Thu 3/14/02 | Mon 3/18/02 | Accel. Mech. | 0% |
| 34 | SMS DC & Controls | 10 d | Thu 3/14/02 | Thu 3/28/02 | BWXT | 0% |
| 35 | Fire protection | 5 d | Thu 3/28/02 | Thu 4/4/02 | Contractor | 0% |
| 36 | SMS stand | 2 d | Thu 3/21/02 | Fri 3/22/02 | Hall C Techs | 0% |
| 37 | Align SMS stand | 1 d | Mon 3/25/02 | Mon 3/25/02 | Accel. Align. | 0% |
| 38 | | | | | | |
| 39 | ODH monitoring | 5 d | Thu 3/21/02 | Thu 3/28/02 | Hall C Electrical | 0% |
| 40 | Unload & rotate SMS | 1 d | Fri 3/22/02 | Fri 3/22/02 | | 0% |
| 41 | Move SMS into Hall | 1 d | Mon 3/25/02 | Mon 3/25/02 | | 0% |
| 42 | Rotate SMS & place on stand | 2 d | Tue 3/26/02 | Wed 3/27/02 | | 0% |
| 43 | Remove shipping fixtures | 2 d | Thu 3/28/02 | Fri 3/29/02 | | 0% |
| 44 | Place end caps | 1 d | Mon 4/1/02 | Mon 4/1/02 | | 0% |
| 45 | Install SMS platform | 3 d | Tue 4/2/02 | Thu 4/4/02 | | 0% |
| 46 | Install SMS cryolines | 2 d | Fri 4/5/02 | Mon 4/8/02 | | 0% |
| 47 | SMS Photogrammetry | 5 d | Tue 4/9/02 | Mon 4/15/02 | Contractor | 0% |
| 48 | Restore SMS can | 2 d | Fri 4/5/02 | Mon 4/8/02 | | 0% |
| 49 | Place SMS DC buss | 2 d | Fri 4/5/02 | Mon 4/8/02 | | 0% |
| 50 | Lay SMS control cables | 3 d | Tue 4/9/02 | Thu 4/11/02 | | 0% |
| 51 | Place tgt gas panel | 1 d | Thu 4/4/02 | Thu 4/4/02 | | 0% |
| 52 | Connect tgt gas panel to perim. Lines | 3 d | Fri 4/5/02 | Tue 4/9/02 | | 0% |
| 53 | Install 2' gate valve | 1 d | Fri 4/5/02 | Fri 4/5/02 | | 0% |
| 54 | Connect SMS cryolines | 2 d | Mon 4/8/02 | Tue 4/9/02 | | 0% |
| 55 | Place ds shield wall | 1 d | Wed 4/10/02 | Wed 4/10/02 | | 0% |
| 56 | Align FW to beamline | 2 d | Thu 4/11/02 | Fri 4/12/02 | | 0% |
| 57 | Align SMS | 3 d? | Mon 4/15/02 | Wed 4/17/02 | | 0% |
| 58 | Mate SMS & FW | 2 d | Thu 4/18/02 | Fri 4/19/02 | | 0% |
| 59 | | | | | | |
| 60 | Place target on SMS | 1 d | Mon 4/22/02 | Mon 4/22/02 | | 0% |
| 61 | Connect target control cables | 1 d | Tue 4/23/02 | Tue 4/23/02 | | 0% |
| 62 | Plumb target gas&cryo lines | 3 d | Tue 4/23/02 | Thu 4/25/02 | | 0% |
| 63 | Align target to SMS | 2 d | Fri 4/26/02 | Mon 4/29/02 | Accel. Align. | 0% |
| 64 | Purge tgt gas & cryolines | 4 d | Fri 4/26/02 | Wed 5/1/02 | | 0% |
| 65 | Install SMS-GV beamline | 2 d | Thu 4/18/02 | Fri 4/19/02 | | 0% |
| 66 | Pumpout & leakcheck SMS/tgt | 5 d | Fri 4/26/02 | Thu 5/2/02 | | 0% |
| 67 | Commission cryosystem | 3 d | Fri 5/3/02 | Tue 5/7/02 | | 0% |
| 68 | Target safety tests (Neon) | 7 d | Wed 5/8/02 | Thu 5/16/02 | | 0% |
| 69 | Target LH2 tests & commissioning | 15 d | Fri 5/17/02 | Thu 6/6/02 | | 0% |
| 70 | Purge SMS gas & cryolines | 7 d | Fri 6/7/02 | Mon 6/17/02 | | 0% |
| 71 | Install GV to dump beamline | 2 d | Fri 6/7/02 | Mon 6/10/02 | Hall C Techs | 0% |
| 72 | Install u.s. girder stands | 2 d | Mon 6/3/02 | Tue 6/4/02 | Accel. Mech. | 0% |
| 73 | Resurvey | 3 d | Fri 6/7/02 | Tue 6/11/02 | Accel. Align. | 0% |
| 74 | Cool down SMS | 23 d | Tue 6/18/02 | Thu 7/18/02 | BWXT | 0% |
| 75 | Install G0 cave | 5 d | Fri 7/19/02 | Thu 7/25/02 | Hall C Techs | 0% |
| 76 | Install long girder | 5 d | Wed 6/5/02 | Tue 6/11/02 | Accel. Mech. | 0% |
| 77 | Align long girder to beamline | 2 d | Wed 6/5/02 | Thu 6/6/02 | Accel. Align. | 0% |
| 78 | Cable long girder | 3 d | Wed 6/5/02 | Fri 6/7/02 | Accel. Elec. | 0% |
| 79 | Test long girder | 2 d | Mon 6/10/02 | Tue 6/11/02 | Accel. Elec. | 0% |
| 80 | Install u.s. beampipe | 11 d | Wed 6/12/02 | Wed 6/26/02 | Accel. Mech. | 0% |
| 81 | Install & align short girder | 7 d | Wed 6/12/02 | Thu 6/20/02 | | 0% |
| 82 | Install u.s. beampipes | 2 d | Fri 6/21/02 | Mon 6/24/02 | | 0% |
| 83 | Align u.s. beampipe | 1 d | Tue 6/25/02 | Tue 6/25/02 | Accel. Align. | 0% |
| 84 | Pump out u.s. beamline | 1 d | Wed 6/26/02 | Wed 6/26/02 | Accel. Mech. | 0% |
| 85 | SMS commissioning & tests | 25 d | Fri 7/19/02 | Thu 8/22/02 | BWXT | 0% |
| 86 | SOS Stair Mods | 15 d | Thu 6/27/02 | Wed 7/17/02 | | 0% |
| 87 | Commission G0 beam & girder | 9 d | Mon 8/26/02 | Thu 9/5/02 | Experimenters | 0% |