2004 Schedule Prepared 1/15/04 Coolant
                Thickness Thickness I_beam Power (W) mul. scat. mass flow
Start End # days Expt.     Contact Expt.   Start End # days HMS SOS Target (cm) (r.l.,) (uA) at I_max mrad (g/s)
9-Feb 11-Apr 63 G0 Production G0 3.026/40   G0   9-Feb 11-Apr 63     LH2 20   40      
12-Apr 9-May 28 G0 Move      
10-May 20-May 11 Hall Installation       E02-019 x>1 13-Jun 3-Oct 54 20-60 20-60 LH2 4 0.46% 55-80 113 0.147 3.6
21-May 23-May 3 Hall Commissioning   4.015/80                 LD2 4 0.53% 55-80 131 0.159 4.2
24-May 10-Jun 18 TBA                     Al dummy 0.267 3% 40 123 0.408 4.1
11-Jun 12-Jun 2 Hall Commissioning   4.015/80                 Optics            
              3He 4 0.62% 40 69 0.289 2.3
13-Jun 20-Jun 8 E02-019 x>1, hi Q^2 4.015/80 Arrington/Lung               4He 4 0.63% 40 69 0.289 2.3
21-Jun 23-Jun 3 Facility Development                     C 0.64 3% 30-80 229 0.408 7.6
24-Jun 12-Aug 50 Hall Installation                     Cu 0.0862 6% 30-80 120 0.595 4.0
13-Aug 14-Aug 2 Hall Commissioning   5.75/80                 Au 0.0212 6% 30-80 55 0.594 1.8
15-Aug 10-Sep 27 E02-019 x>1 5.75/80  
11-Sep 11-Sep 1 Target Change       E03-103 Struct. Func.'s Light Nuclei 4-Oct 24-Oct 21 15-60   same as E02-019     20-50      
12-Sep 19-Sep 8 E02-019 x>1 5.75/80  
20-Sep 23-Sep 4 Maint./Restore       E01-107 Transparancy 18-Nov 23-Dec 30 10.5-20 27.3-53.9 LH2 4 0.46% 50 71 0.147 2.3
24-Sep 3-Oct 10 E02-019 x>1 5.75/80                 LD2 4 0.53% 50 82 0.159 2.6
54 E02-019 x>1               Al dummy 0.205 2.30% 40 95 0.354 3.1
              Optics            
4-Oct 13-Oct 10 E03-103 Struct. Func.'s Light Nuclei 5.75/80                 C 0.427 2% 50 153 0.327 5.0
14-Oct 14-Oct 1 Target Change                     Cu 0.0862 6% 50 75 0.595 2.5
15-Oct 24-Oct 10 E03-103 Struct. Func.'s Light Nuclei 5.75/80 Arrington               Au 0.0424 12% 50 110 0.865 3.6
21 E03-103 Struct. Func.'s Light Nuclei
Minimal Cryostack: LH2 4 0.46% 50-80 113 0.147  
25-Oct 17-Nov 24 HKS Install       LD2 4 0.53% 50-80 131 0.159  
18-Nov 24-Nov 7 E01-107 Transparancy 4.612/80 Garrow/Ent 3He 4 0.62% 40 69 0.289  
25-Nov 30-Nov 6 Thanksgiving       4He 4 0.63% 40 69 0.289  
1-Dec 5-Dec 5 E01-107 Transparancy 4.612/80   Al dummy 0.205 2.30% 40 95 0.354  
6-Dec 23-Dec 18 E01-107 Transparancy 5.749/80   Optics            
30 E01-107 Transparancy C 0.64 3% 30-80 229 0.408  
Cu 0.0862 6% 30-80 120 0.595  
24-Dec 3-Jan 11 Xmas       Au 0.0212 6% 30-80 55 0.594  
?            
?            
Concerns:
1) With the thick targets and small angles needed for the HMS (10.5 degree mode/pipe),
the SS gate valve will be a real problem unless it's replaced with an aluminum one. * Coolant mass flow calculated for LH2 and LD2 using H(15 atm, 15K)-H(3 atm, 19K)=31.0 J/g
2) The thick nuclear targets will activate the pivot area pretty badly. This may prevent * Coolant mass flow calculated for all other targets using H(3 atm, 4.5K)-H(1.2 atm, 6K)=30.3 J/g
maintenance/repair activities from being carried out for significant periods of time
after the beam is turned off. May be useful to try to schedule high dose runs just before breaks.
3) The solid targets requested by the different experiments have been consolidated in order to
reduce the number needed on the cryostack.