x>2 proposal

SRC: x > 2

May 08 runplan





Final document handed to Kees: summary, kinematic coverage and projected results



  1. List of possible issues






  2. kinematics





    Kinematic table:

       kin#    
        E (GeV)    
        th (deg)    
        E'    
        x-range    
        Q2-range    
        time_3He    
        time_alltgt    
       
       4.1
    4.581
    12.5
    4.280
    1.1-3.0
    0.90-0.96
    2.0
    9.3
       4.2
    4.581
    14.0
    4.240
    1.3-3.0
    1.12-1.19
    2.4
    9.3
       4.3
    4.581
    15.5
    4.195
    1.4-2.9
    1.36-1.44
    3.0
    12.1
       4.4
    4.581
    17.0
    4.015
    1.2-2.0
    1.56-1.66
    3.0
    11.9
       4.5
    4.581
    17.0
    4.200
    1.7-3.6
    1.63-1.73
    6.0
    17.6
       4.6
    4.581
    18.5
    3.955
    1.3-2.0
    1.82-1.93
    6.0
    27.2
       4.7
    4.581
    18.5
    4.165
    1.9-3.7
    1.91-2.03
    12.0
    35.3
       4.8
    4.581
    20.0
    4.055
    1.8-3.0
    2.17-2.31
    24.0
    70.5
       4.9
    4.581
    21.5
    3.995
    1.9-3.0
    2.47-2.62
    42.0
    123.4
       4.10
    4.581
    23.0
    3.940
    2.0-3.0
    2.78-2.96
    42.0
    123.4
       
       
    Total prod.
    440.0 (18.3 days)
       
    or
       
    316.6 (13.2 days) without 4.10




    Overhead and total beam time estimate:

       scenario    
        #1 (all kin)    
        #2 (no 4.10)    

    tgt-change
    8.3
    7.5
    kin-change
    20.0
    18.0
    cryo-change
    16.0
    16.0

    dummy
    28.5
    20.1
    optics
    5.0
    4.5

    energy meas.
    2.0
    2.0
    BCM calib.
    2.0
    2.0
    check-out
    8.0
    8.0

    Total overhead
    89.8
    78.1

    Total prod.
    440.0
    316.6

    Beam time
    529.8 (22 days)
    394.7 (16.5 days)




  3. Projected results








































Patricia Solvignon