| Owl (0:00 - 8:00) | Day (8:00 - 16:00) | Swing (16:00 - 24:00) | |
| 2/25/2000 | |||
| Beam Commissioning | Beam Commissioning | SOS / HNSS | |
| Test Plan I & Test Plan II | Test Plan III | Commissioning | |
| 1.953 GeV | Test Plan IV | II.1 | |
| 2/26/2000 | |||
| SOS / HNSS | SOS / HNSS | SOS / HNSS | |
| Commissioning | Commissioning | Commissioning | |
| II.1 & II.2 | II.3 & II.4 | II.4 | |
| 2/27/2000 | |||
| SOS / HNSS | SOS / HNSS | SOS / HNSS | |
| Commissioning | Commissioning | Commissioning | |
| III.1 & III.2 | III.2 | Optional, III.2 | |
| 2/28/2000 | |||
| SOS / HNSS | SOS / HNSS | SOS / HNSS | |
| Commissioning | Commissioning | Commissioning | |
| III.2 & III.3 | III.3 | III.3 | |
| 2/29/2000 | |||
| SOS / HNSS | SOS / HNSS | SOS / HNSS | |
| Commissioning | Commissioning | Commissioning | |
| III.3 | III.3 | III.3 | |
| 3/1/2000 | |||
| SOS / HNSS | Beam Energy Change | Production | |
| Commissioning | Commission Test Pan II | ||
| III.3 | 1.864 GeV | Short Calibration | |
| 3/2/2000 | |||
| Production | Production | Production | |
| Short Calibration | Short Calibration | Short Calibration | |
| Notes | |||
| Repeat Beam Commissioning Test Plan II for each energy change or after | |||
| maintenance days. | |||
| Take sieve slit runs after each reset of magnets (SOS or Splitter or Split-Pole) | |||
| with SOS 3/4 trigger No PID for 200K triggers. | |||
| Take additional CH2 calibration run as necessary when beam energy shift | |||
| becomes an issue. | |||
| After 3/2/2000, the run plan structure becomes simple as shown for 3/2/2000. | |||
| Detailed daily run plan will be given by run coordinator at least a day ahead. | |||