HNSS_Commissioning Schedule

HNSS_Commissioning Schedule

  Owl (0:00 - 8:00) Day (8:00 - 16:00) Swing (16:00 - 24:00)
2/25/2000      
Beam Commissioning Beam Commissioning SOS / HNSS
Test Plan I & Test Plan II Test Plan III Commissioning
1.953 GeV Test Plan IV II.1
     
2/26/2000      
SOS / HNSS SOS / HNSS SOS / HNSS
Commissioning Commissioning Commissioning
II.1 & II.2 II.3 & II.4 II.4
     
2/27/2000      
SOS / HNSS SOS / HNSS SOS / HNSS
Commissioning Commissioning Commissioning
III.1 & III.2 III.2 Optional, III.2
     
2/28/2000      
SOS / HNSS SOS / HNSS SOS / HNSS
Commissioning Commissioning Commissioning
III.2 & III.3 III.3 III.3
     
2/29/2000      
SOS / HNSS SOS / HNSS SOS / HNSS
Commissioning Commissioning Commissioning
III.3 III.3 III.3
     
3/1/2000      
SOS / HNSS Beam Energy Change Production
Commissioning Commission Test Pan II  
III.3 1.864 GeV Short Calibration
     
3/2/2000      
Production Production Production
     
Short Calibration Short Calibration Short Calibration
     
       
       
       
       
       
       
  Notes    
       
  Repeat Beam Commissioning Test Plan II for each energy change or after
  maintenance days.
       
  Take sieve slit runs after each reset of magnets (SOS or Splitter or Split-Pole)
  with SOS 3/4 trigger No PID for 200K triggers.
       
  Take additional CH2 calibration run as necessary when beam energy shift
  becomes an issue.
       
  After 3/2/2000, the run plan structure becomes simple as shown for 3/2/2000.
  Detailed daily run plan will be given by run coordinator at least a day ahead.

Last Updated on 2/22/00
By Liguang Tang