1.) Chamber:
Quotes for the charge collector from CERN were received an a PO
was generated. Rui has promised an end of June delivery date.
Survey:
The charge collector will have survey targets (copper traces) located on the
back. The image below shows three of them at the top of the
image.
The complete layout of the targets may be seen in the
pdf file.
Our goal will be to complete detector construction by July and
prepare for beam tests in August.
2.)Readout electronics
I spoke again with Walter Snoey reguarding a delivery date for
the VFAT boards. He said that several 100 VFAT chips have been
made. Several out of 100 chips do not pass their quality tests.
They have mounted the chips chips which did pass onto several
(more than 10 less than 100 ) boards. Although they are
having problems with yield, he feels I should be able to get up
to 6 boards for beam tests in August.
3.) rotator
Collimator arrives in summer 08. Should we look into how the
rotator can be mounted to the collimator?
LaTech report