- Engineering (Bill Vulcan)
- Looking into ordering a rad hardened 486 pc with cpu, memory, etc.
- ROC 4 should be moved into the SOS hut the next downtime
- Trigger timing may move due to this! Cables are kept same length though
- All new cameras were put in
- Have lost cameras in HMS and SOS, and in the Shield Hut
- Reset Fast Raster switch is located in the Counting House where everyone can see it
- CSF E97-006Progress, (Marko Zeier)
- Showed ABU's e97006 figures
- Ran at about 70% total data
- Report on Experiment E94-110(Rolf Ent)
- Q3 is causing HMS problems
- Wants to know what the set current and readback current difference is, requests Steve Lassiter to look into this.
- E94-139 Collaboration meeting is scheduled for Sept. 30
- Beam current (BCI) needs to be installed, will be ready for Sept. 17
- Working on shift schedule to finish E94-110
- HNSS update (Liguang Tang)
- HNSS hardware is done
- SSD is completed
- Hodoscope support hardware has been welded
- Scintallators are done and in place
- All 75 tubes are in, waiting for the extra 10 to come in
- By the end of the month, everything will be put together
- Everything in target chamber has been tested
- Ferris wheel bid came in below cost
- Rails came in above cost
- Drawings have been completed, they need to be looked over
- All interface issues were worked out by Orsay
- Went over schedule through December
- Cool down will be Sept. 18, latest start of e97-006 on Sept. 20
- Thia will start back up on Oct. 5, and will have 7 days instead of 5 days
- Dec. 8 through Dec. 23 will be the HNSS installation period
- Thursday Sept. 2 will be the Gen Readiness Review meeting