Highlights:
Our lattice designer (Dave Douglas) released Version
1.1 of the accelerator driver design to engineering this week.
Congratulations to Dave for achieving this milestone.
Management:
Final preparations for next week's Laser Processing
Consortium/FEL User's Meeting workshop which will be held at Jefferson
Lab on Jan. 18-19th.
We continued preparation of the cost and schedule
documentation for the Phase 2 of the FEL upgrade project which we are
planned to integrate with Phase 1 after the Phase
2 funding has arrived (hopefully next month).
WBS 3 (Beam Physics):
A POISSON model for the gun was resurrected and is available for gun design modification studies.
The pre-release Revision 1.1 machine design was
released to WBS 9 for layout and engineering. This version nominally
incorporates the near-concentric optical cavity,
resolves various interferences, allows additional space for compaction
management elements, supports injection/extraction
line geometry providing the desired beam quality, and uses parts that can
be
common with the UV system. It is optimized for
the probable initial operating energy of 145 MeV.
WBS 4 (Injector):
The use of the new reverse flow heater on the
current wafer gave a uniform QE in the area that has consistently had good
QE
but lacked uniformity. The portion of the
wafer with a low QE failed to recover to a higher level indicating
more than a heater
issue.
The preliminary design for a cathode shield and
internal cesiation scheme has been completed for the upgrade gun design.
Conceptual design for the gun chamber has been
presented and awaits review. The rate monitor was received and installed
in
the system for mapping the focused cesiator.
The system is being set up for bake out.
WBS 5 (SRF):
Waveguide tooling design has been completed by
the vendor.
Vendor proposal for modification to design has
been reviewed and approved.
Thermal shield procurement package has been completed
and the purchase request signed.
WBS 6 (RF):
Continuing discussions with Glassman High Voltage
on the upgrade of the Gun's high voltage power supply. No progress in the
installation and test efforts for zones 3 and
4 because we did not get a repaired LCW system until the end of the week.
We are pleased to report that he LCW was brought back on line Friday apparently without contamination.
The debug of the RF operational systems was completed for the upcoming run.
WBS 8 (Instrumentation):
The updates to the Laser Safety System (LSS) was
completed this week, and all 4 of the operational user labs
were certified. All of the certification procedures
have also been updated to reflect the changes to the system -
there is now a key in each lab that enables it
to be operated in a "Hutch" mode allowing users to be present
during experiments providing the FEL beam is
enclosed and interlocked. This system will also allow for
switchyards to be installed so that multiple
hutches can be installed in a given lab with no additional changes to
the LSS. Many thanks to the four operators and
to Ron Lauze' for participating in the certifications. This activity
doubled as an eight hour training period so they
are now qualified to operate the FEL.
The alignment mode changes are complete and documented.
This change will allow the "short pulse" users
macro pulses up to 60 Hz, the previous limit
was 2 Hz. The expanded Beam Mode will be certified on the 1/12/01
run. Entry status lamps were added to the control
room and to each of the user lab doors. With the expanded
modes of operation these (12) stoplights will
make it easy for the FEL users to know when one can go into a lab
and whether goggles are required. Additional
video monitors were added in the control room for monitoring the
user labs and mirror cans/ beam dumps.
Work continues on the optical BPMs. There are
four prototypes built for this upcoming run, these will be used with
picomotors to create a lock on the optical transport
system. The error signals will be used to drive each of the
mirror cans to a zero offset.
Parts continue to be purchased for the upgrade
to the vacuum system. Good progress continues with the 3" BPMs and the
3"
shielded beam viewers.
WBS 9 (Transport):
Dipoles
o George Biallas discussed designing the Injection
and Extraction dipoles (GU & GV) with DULY Research at their
office.
o Their magnetic analysis showed that the mu
metal pole is a magnetic short if carried to the edge of the return leg
and
creates a smaller good field region.
When the mu metal is placed only inside the coils, the good field
region expands
significantly. We will search
for an optimum point somewhere within the coil bundle where the good field
region is maximized.
o Their analysis also shows that there is a natural
field gradient in the field at the plane perpendicular to the beam at the
center plane of the magnet.
This means that the magnet is so narrow and the gap so big that the end
field drop-offs
that begin within the magnet gap
are intersecting at the narrow end of the magnet. We discussed closing
the
gap enough at the narrow end of
the magnet to cancel the end effect.
o They suggested the use of permanent magnets
for this application which a simplistic analysis showed has excellent
field uniformity. This could
be the basis of an additional task.
o George Biallas discussed designing the First
Reverse Bend, (GX), the Second Reverse Bend (GQ) and the 180
degree bend (GY) with Advanced Energy
Systems at their office.
o The most significant issue with the design
of the 180 degree dipole is the insertion of the path length correctors
into the
ends. As specified, at 35,000
G-cm, it is superposing a 1.75 KG dipole (for 20 cm length) on to the ends
of a
magnet that is 7.5 KG already.
This implies adding to the local return leg and pole tip iron thickness
by almost 25 %.
Since this specified field is for
the worst case of a 180° phase advance at 210 MeV. We agreed
to clarify how the
correctors would be used.
o Dave Douglas has formally issued the
"cut iron" engineering version of his beam transport layout to be drawn
to
check for interference.
Quadrupoles
3 inch bore magnets
We finally received an extensively researched
quote on the quadrupole from our principle coils supplier.
While the yoke
quotation was expensive, the coil and assembly
quotation were within our estimates. So far, the use of the best
quotations falls
within out estimates.
Trim Quad for the Arcs
Magnetic design work has started.
o Measurement Probe: The fiberglass plastic parts for the probe body are being annealed.
Sextupoles and Octupoles
Magnetic design work has started.
Vacuum
o We ordered the shielded bellows for the vacuum
piping.
WBS 10 (Wiggler):
Progress is being made on finalizing the wiggler assembly.
WBS 11 (Optics):
With receipt and initial checkout of the deformable
high reflecting mirror design that came out of our contract at
AES, we completed the design of the internal
components of the optical cavity mirror test stand. Except for a few
minor corrections, the prints are signed off
and will be going out for bid.
We have started the design of the optical cavity
assemblies. So far, it is clear we can switch between three
wavelength ranges. At this time we are
trying to make it an UHV enclosure, so we can carry over the design to
the UV FEL.
We installed other O-BPM optics on the upstream
optical table, to monitor the FEL position near the outcoupler,
and near mirror can 2, which is in the vault.
We upgraded the optics at the end-of-line, specifically a larger pickoff
wedge was installed, and we changed the optics
for the ModeMaster and O-BPM to more appropriate sizes.
We received 6 of New Focus' OEM single-channel
picomotor controllers, the very first released to the public.
They will be integrated into a new chassis for
control of the mirrors associated with the O-BPM system.
The vacuum installation group swapped the LSS
shutter with the "hole harp", an intracavity aperture for mode
control. They did a good job, as did the
I&C group with the new cabling. This should be ready for the
run.
Work done specifically to prepare for operations included:
Swapping out the 1 micron mirrors for 3 micron
mirrors.
Replacing the black-anodized mirror holders in
the collimator linear stage with unanodized mirrors.
Operations/Commissioning:
We prepared for "hot check-out" next week by subsystem
check outs this week as noted in the discussions above with the
injector, rf, instrumentation and optical systems.