IR FEL Monthly Report for July 1997

Navy IR Demo Contract WBS Elements

WBS 1 Project Management

July 1997 was the thirteenth full month for the IR FEL Demo project funded by the Navy.

Cost Performance Scheduling

We have expanded the discussion of cost performance/scheduling in this monthly report as the project nears completion.

The original project total available budget was $8,082K. During August 1996, a funds transfer was negotiated with LANL for $37,645 for an FEL modelling task, reducing the total available budget to Jefferson Lab to $8,044k. However the project remains scheduled and measured against the original budget of $8,082k. Any actual cost comparison has to include the project cost plus the cost of the agreement with LANL.

The IR FEL Demo project through the month of July 1997 has a total of $7,636k (less SRF and the building) of performance scheduled. The work performed through the current period is $6,844k or 85% complete versus 94% scheduled. The actual costs accrued through July totals $7,058k. This results in a negative schedule variance of $792k and a negative cost variance of $214k.

As of the end of July 1997, $7,827k has been costed and/or obligated ($7,058 in actual costs and $769 in current obligations.) The remaining unobligated balance is $217k. A plan is in place to fully obligate/cost these funds not later than September 30th. The existing cost variance will decrease to zero as the schedule approaches completion.

Two months remain to accomplish the remaining scheduled work of $1.238 million in the project's Performance Assessment "Earned Value System." To finish on schedule means that $619k of work, on an average, remains to be accomplished each month. This represents a decrease of $14k per month over the June average of $633k. The obligations given do include the lab's overhead costs.

We expect to complete the remaining scheduled work ($1.238M) at a cost equal to or less than the remaining budget ($986k, the sum of current obligations and unobligated balance). The remaining work is expected to be accomplished for less than the original earned value assessment when many fractionally complete small peg points are claimed. In addition, actual procurement and check out costs for some subsystems will be less than the original earned value estimates (Apr. 96).

Management

The project team's attention in July was focused on installation activities. The FEL Building was turned over to the project early in July. The majority of the injector components from the injector test stand were re-installed. The cryogenic systems WBS was completed with the successful cooldown of the transfer lines and the injector cryounit. Substantial components of the RF and I&C systems were installed. The linac cryomodule was completed and on Aug. 1 installed in the FEL Facility.

Plans are being reviewed and revised on a weekly basis for integrating the start-up of FEL commissioning tasks with the completion of the construction and installation tasks. On July 28th, the DOE-Navy Memorandum of Understanding was signed for the FY97/98 IR Demo Commissioning/Upgrade project. Jefferson Laboratory was given authority to spend $3.7M of funds for this project over the period of August 1997 through September 1998. Within the scope of the new project and new project funds are four task areas: (1) Commissioning Preparations; (2) Commissioning; (3) a second cryomodule system for an energy upgrade; and (4) design and construction of key components of a power scaleable (R5) optical cavity. The scope of the Commissioning Preparations task includes key additions to the baseline hardware configuration that will allow the IR Demo to be commissioned with more expedience and with higher confidence.

Prospects for additional near-term funds from the Navy evaporated in July with the mark-up of the FY98 Defense Appropriations Bill in the House. No additional funds will be included for the Project in the FY98 appropriations.

SURA received the June 9-10 MTAC meeting report from Adm. Baciocco. The committee made recommendations to SURA and Jefferson Laboratory for dealing with the current lack of Navy support for FY 98 funding and optimizing the use of the soon to be released FY 97 funding.

Considerable progress was made with internal and external reviewing of the pre-proposals that have been submitted for initial use of the IR Demo. We have received 15 of 18 proposals that are in process. After final review the pre-proposals will be forwarded to the DOE-BES program office for comments.

Discussions were held with Vice Provost (Calvin Lowe) of Hampton University concerning relocation of molecular beam epitaxy and materials analysis equipment to the FEL and ARC Building laboratories.

Our LPC representative from IBM (Jake Pacansky) has arranged for shipment of IBM surplus vacuum chambers and optical tables for use in the FEL User Lab.

F. Dylla visited the Vanderbilt Free Electron Laser Facility on July 18 to continue discussions on research collaborations. Vanderbilt is currently testing one of our diagnostic systems and discussions were initiated last year on joint research proposals on laser materials interactions in the infrared.

Arlene Serber and Jim Palmer, Vice Presidents of Newport News Shipbuilding's subsidiary, Newport News Nuclear, visited the lab Monday to discuss continued FEL collaborations between Newport News Shipbuilding and Jefferson Lab.

At the SPIE Conference in San Diego, CA in July, Rui Li presented a paper entitled "Shielded Transient Self-Interaction of a Bunch Entering a Circle from a Straight Path", and Michelle Shinn presented a paper entitled, "Optical Design Issues for this Jefferson Lab IR Demo Project".

Jefferson Lab was invited to co-sponsor a Workshop on Scientific Applications of 4th Generation Light Sources that will be held on 28-29 Oct. 97 at Argonne National Laboratory.

WBS 5.0 Instrumentation & Controls

A clean area was setup in lab 1 for installation of 1.5 micron Al foil on OTR beam viewers prior to installation into the accelerator. The camera mounting frames will also be assembled in the clean area. Soleniod assemblies are being finished up for the pneumatic devices. Assembly of the charge-coupled-device cameras for the electron-beam viewers is also being worked. A collaboration with Princeton is being investigated, this would entail a loan of their 20 channel cryo-cooled InSb detector array to use the coherent radiation synchrotron radiation emitted by bunched-electrons to study and monitor the longitudinal beam dynamics.

Design work continues on the Analog Monitoring System (AMS). This system is a 128 to 16 multiplexer which routes the desired signal to either the CEBAF control center over fiber optics or allows local viewing in the FEL control room with a scope. The initial design for the front-end buffer boards is complete and prototyped, this yields a flat response out to 5 MHz from the RF gallery to the control room. The 3dB point is about 10 MHz. The backplane design uses previous work done for the beam-position monitors in CEBAF's Hall B with only a minor modifications. Cabling and terminations for the clean room in the FEL Facility are complete, and the photocathode drive laser can now be operated through the control system. The control room patch panels are installed on each of the table tops along with scopes and monitors.

Connections for reading the temperature instrumentation diodes in the cryomodule are in progress. The hardware and software should be in place by next week. The cooldown diode readout will use the new servers.

The new servers have their final file configuration and are going to be used to support the cryomodule cooldown. The ITS server is still being used to support the injector RF reinstallation and the initial drive laser recommisioning. The ITS server will be de-commissioned in early September. Both the CEBAF LAN and the controls LAN are operating reliably.

The personnel safety system continues to make progress toward the mid-August operational date. The Machine Protection final design review material was handed out to the review committee, the review will be held in August.

The vacuum system hardware is nearing completion, the cables will be pulled in Aug.

Numerous updates have been made to the web pages: http://www.jlab.org/accel/fel/ documentation/evans/felbair1.html. This site is updated daily reflecting state of installation and nailing down of details.

WBS 6 Cryogenic Distribution

The FEL transfer line complete. The 1/4 cryomodule (cryounit) is at 2K with a 65% liquid level. The system is stable and preliminary investigation shows we are below the heat load budget. This WBS is now complete.

WBS 7 Beam Transport

Most parts for the 27 dipole magnets (and the parts for the 8 sextupoles) were completed during the month with a few parts and the coils for the 180 degree dipoles still outstanding. Seven optical chicane dipoles are on hand. Two styles of Panofsky trim quad are still in fabrication.

In the corrector area, three mu metal styles are signed off with only coils for two styles still in procurement with the remaining parts in manufacturing. Air core correctors resolved to three styles that are at the latter end of detailing.

In the vacuum system, welded chambers for the x and y positions and the bodies for optical chicane chambers were completed. The chambers for the reverse bends and the chambers for the 180 dipoles are were well started.

The design of arc stands was completed. Design of the recirculation dump line and a quad telescope on the end of the second arc are the only outstanding layout design tasks.

Installation activity concentrated on the back leg and the injection area. Most cable pulling is complete.

Overall summary: dipole measurement, chamber welding and correctors remain on the critical path.

WBS 8 RF Systems

In the Injector, the waveguides, circulator, and klystron cart for the first cavity of the quarter cryomodule were installed and tested for leaks. The waveguides for the buncher cavity were also installed and leak tested. The Low Level RF racks for the Injector and Drive Laser were connected to the network and given preliminary tests. In the Linac, testing of the Low Level RF control system continued. The full cryomodule was installed and is ready to be aligned and cooled down. The second spare 50 kW klystron failed its acceptance test this month. We are waiting for instructions from the vendor for additional testing and return instructions. Hipotronics solved the numerous small problems they had with the 225 kW variable DC power supply. One unit passed the specification tests, was shipped, and is ready for installation in the FEL building this week. The other unit was repaired and is ready for its specification tests. It is expected to be shipped in August. The 1427 MHz Oscillator and Drive Amplifier for the FEL Master Oscillator system were installed this month. The master oscillator distribution cables were connected and preliminary tests started. Final installation on the LCW supply will be started in August. The Buncher cavity was installed and aligned. The buncher water skid and controllers are ready for final installation and testing.

We have most of the hardware installed for the first 50 kW RF system and for the 8 kW RF systems. We are starting to make systems and interlock tests. The gun high voltage power supply gas filled transmission line elbow inner and outer conductor are now complete. We are ready to start high voltage breakdown tests. The gun power supply assembly is complete, the 208 volt feed for the high voltage driver is installed, and the vessel interlocks are installed. We will start high voltage testing early August.

WBS 9.2 Injector Move

This WBS is essentially complete except for testing and acceptance of injector power supply transmission line hardware, and re-connection of gun-cryounit beam line hardware, and installation of several components in the drive laser transport line. The drive laser is fully operational in the FEL Facility clean room.

WBS 9.4 Wiggler

The wiggler girder components were aligned using both the standard alignment fixtures and using a boresighting technique. The latter technique guarantees high accuracy but must be calibrated against the regular methods so that alignment can be carried out with the system under vacuum. The wiggler girder was then installed and found to be too high. The support plates were being modified at month's end. A simplified weld design was attempted for the wiggler vacuum chamber but it did not work out. The more complicated old design will be tried out next. The wiggler vacuum chamber support was fit up. A clearance problem was found and fixed. The wiggler viewer design was completed. Northrop Grumman agreed to use its apparatus to carry out a pulsed wire measurement of the wiggler girder. This will be done in August.

WBS 9.6 Optics

This month was a busy one for installation of the optical transport in the accelerator enclosure. First, the optical tables were aligned to within < 1mm of the correct position. We set up He-Ne lasers to mark the beam path, and then mounted mirror can stands and mirror cans. In the process, we found the unevenness of the ceiling necessitated taking stands back down and modifying them. This accomplished, by month's end most of the mirror cans were in their final position. We have also received the collimator and most of it's sub-assemblies, this will be checked out in the Optics Lab, with installation planned in late August/early September. Our transport mirror vendor (Spawr) produced a set of incorrectly polished mirrors, these have been returned. However, we do have enough mirrors to complete installation of all first-light components, so this is not a problem. We determined that neither the LCW nor the HVAC were responsible for the ~ 28Hz vibration the Mach-Zehnder interferometer detects. The nearest source of vibration are the motors on the cooling water towers for the CHL, particularly since one seemed to be out of balance. This has been remedied, so we will check again at the next opportunity. We began assembly of the optical cavity assemblies in one of the facility clean rooms, there have been some delays as the bellows assemblies for the optical cavity assemblies were cleaned and baked as part of their processing for high vacuum. We also began testing the accuracy of the LVDTs on the gimbal mounts. Unlike the linear stage, the gimbal mount transport seems to have negligible backlash, as reported earlier. However, we are seeing hysteresis in the LVDT readings. The problem may be in the way the LVDT was mounted; tests continue. We received the new style picomotor controller, and it's initial checkout shows that it is quite nice. We will use it for both the drive laser optical transport and the FEL optical transport. In other work, the design of mirror cassettes moved into detailing phase.

Injector, SRF, Facility, and Other Activities Outside Navy IR Demo Contract

INJECTOR TEST STAND

WBS 3 - CRYOMODULE

The cryomodule has been completed. All vacuum and helium systems have been qualified for operational use. Documentation and labeling of instrumentation has been completed. The cryomodule is ready for installation into the FEL building on Aug. 1.

Warm Windows

Window production continues on three fronts. 1) The additional production of the present design has progressed with the completion of required ceramics with the required machining being performed at a local shop. Additional flanges have been machined and copper plated and are ready for final assembly. Final assembly is in the queue for in-house resources. 2) The windows developed and manufactured with Northrop Grumman continue to progress. Flanges have been completed and final braze procedures are being developed. Final assembly is in the queue for in-house resources. 3) The cooled waveguide window prototype design is nearing completion. Some parts are on order and all drawings are being reviewed for fabrication. Completion of prototype windows is scheduled for September.

WBS 2 -- BEAM PHYSICS

Additional PARMELA simulations of the beam dynamics from the photocathode to the wiggler with the present "long" gun configuration (cathode-anode spacer in place) were done, with the result that an injector setup was found that gave the short bunch length at the injection point that was desired for using the interferometric bunch-length monitors being procured from the University of Georgia. At "long" bunch lengths, the power from the device would be "low" and rapidly changing as a function of the wavelength. Nevertheless, for conceivable bunch lengths, there is adequate power to perform relative measurements, i.e., to monitor bunch length. Cross-calibration to an absolute measurement made with a back-phasing technique is planned. Analysis of the data collected during the last series of experiments with the photocathode gun is continuing. Regarding longitudinal properties of the 135 pC bunches, the data concerning energy spread versus longitudinal position, as well as the data concerning bunch length, agree remarkably well with code (PARMELA) predictions. However, several issues remain, most notably a disagreement regarding transverse beam size. Specifically, the transverse rms beam size at the gun's aperture appears to be much larger than predicted by PARMELA, and tails are seen to form at the edge of the bunch. Data reduction continues. Plans are to present the results of these experiments at the FEL Conference in China next month. The design and associated beam-dynamics studies of the energy-recovery dump downstream of the cryomodule were completed and finalized. Various questions concerning magnet characterization and alignment were investigated and answered as they arose. This is now a routine activity as we progress through construction of the machine. Examples included alignment requirements and procedures for the injection-line quadrupoles, and the wiggler and wiggler-girder quadrupoles. Details are provided in weekly reports.

Progress on development of a simulation code that includes the physics of coherent synchrotron radiation (CSR) is proceeding, although progress this month was slowed due to our preparation of related manuscripts for the SPIE Conference held at month's end in San Diego, CA, at which R. Li presented a paper entitled "Shielded Transient Self-Interaction of a Bunch Entering a Circle from a Straight Path", and for next month's FEL Conference. At the FEL Conference we will present new analytic results developed mostly this month concerning noninertial forces that arise off-axis from the design orbit. We also drafted an extensive manuscript envisioned for submission to Physical Review E that we will finalize soon after the FEL Conference. Our plans remain to have the simulation code ready in time to support experiments planned for the IRFEL early next year.

WBS 4 -- IRFEL COMMISSIONING/OPERATION

We thoroughly scrutinized plans for measuring magnets prior to their installation in the FEL beamline. The status of procurements, as well as resource and space limitations for magnet measurements, are such that some magnets will have to be measured after 1 Oct. 97. We organized the entire process to be compatible with the commissioning schedule, i.e., with priority on completion of the injection line, followed by completion of the straight path for first light, and then completion of the recirculation arcs. We are anticipating that, on 1 Oct. 97, that the majority of hardware shown on the system top level drawing will be in place, several magnets and possibly the vacuum chamber for the second recirculation arc may be missing, depending on actual delivery dates of this hardware. On approximately Oct. 1, we will begin commissioning the gun on swing and owl shifts, leaving day shifts open for installation activities until they are all complete. Our plan to be pulling electrons off the photocathode in mid-October, as well as the timing of the rest of our commissioning activities, remains unchanged. The top-level procedure for energy recovery was formulated, to include measurement of dispersion and variation of path length with momentum from the wiggler to the energy-recovery beam dump. The process resulted in clarification of specifications for several pieces of hardware and software necessary for the task. The first draft of a procedure for fine phasing of the cryomodule was prepared. The algorithm first determines zero crossings for improved sensitivity, and then determines crest and anti-crest to check for nonlinearities and develop some statistics.

The on-line Accelerator Readiness Review (ARR) tracking system is now about 90% complete. Plans continue to be such that only one ARR review meeting will be held, in the January-February 1998 time frame, to complete the sign-off of the FEL ARR. Performance integration plans are under development for the major systems of the machine. The RF Performance Integration Plan and the Magnet Performance Integration Plan are completely outlined, and the writing of their drafts is well underway. Basically, these plans identify the appropriate subsystem owners and principal investigators and integrate their efforts toward achieving related specifications. The process helps ensure test plans required for commissioning are completely identified and written. The design and operating strategy for the FEL analog monitoring system (AMS) was finalized. The AMS will use eight 16x16 crosspoint switches manufactured by Analog Devices to accept input from 128 lines and generate output to 16 lines. The switches have built-in BNC connectors and software to allow PC control that is easily adaptable to the Lab's EPICS control system. All channels will have a root-mean-square converter on them with a signal into EPICS, thereby allowing any of the 128 signals to be archived. The bandwidth of the AMS is limited to 1 MHz in the Machine Control Center by the fiber-optic link to the FEL Facility, but in the Facility itself the bandwidth will exceed 5 MHz. The drawback is that it has no positive verification of the channel selected; however, there is a calibration signal and the hardware is commercial, so reliability should be better. Extensive testing of the system is planned. Successful tests of the multislit transverse-emittance monitor during experiments with the photocathode gun led us to consider designing and mounting one of these devices at the gun's light box as an aid in monitoring the gun's performance during commissioning and operations. However, in view of cost and schedule, we are putting this on hold until we can bring it through design, fabrication, and installation without stalling higher-priority projects already programmed. Nonetheless, we are also firming up the projected cost and schedule for the additional instrument. It is not required for commissioning but would be a nice augmentation of the baseline diagnostic suite.

Facility

This month the facility became essentially operational. Our locks went on the doors. The phones went in. The computer networks became operational. The RF low level controls were cycled for the first time on a portable computer. The photoinjector drive laser was placed in the clean room, successfully connected to the chiller, brought into operation, and connected to the network. Much optical setup work remains, however. The transport telescope was hung. Cubicles were placed in each lab to house users and student researchers. The optical transport line was hung, leveled, and light brought to the optical control room for the first time.

The injector stands were placed and grouted. The gun was set in the injector, aligned and hooked up to the light box. The buncher cavity was positioned as was the injector solenoid. The wiggler was surveyed on its table to the quadrupoles but placement of the wiggler table was delayed a week when a hardware interference was discovered. Magnet power cabling is rapidly going in. Helium was supplied to the cryounit and cooled the unit to 2K successfully. The cryomodule was brought to the building and surveyed into position.

Grounds work is still underway at the facility. The sidewalks and entrance tiling were completed. Parking areas were constructed and the street got new asphalt. Piping for LCW, N2, and instrument air was 95% complete both upstairs and down. Electricians hooked up a large number of electrical equipment racks. HVAC balancing continued through the month. Rubber pads were placed in the stairwells and painting was completed. Punch list work continues on the facility. The only major items remaining are certification of the fire alarms and elevator. Both systems are functional but have some work remaining before acceptance.

The Hilti bolts for the drive laser transport were laid out and installed. The telescope box was installed and the design of all the downstairs stands was completed. The two new mirror cans were assigned to the Jefferson Lab machine shop for fabrication. All the flanges for the transport line were ordered. All the optical equipment for the laser clean room was moved into the facility. The laser was run successfully after several problems with the chiller system were resolved. The server used in the ITS was installed in the FEL facility and the laser is now under computer control. The gun, light box and buncher were installed and aligned. The interlocks and controls for the high voltage power supply were wired up and the power supply was ready for high voltage test in air by month's end.

The drive laser and associated optics and electronics was moved to the FEL building. New plumbing and utilities have been hooked up to it and it has been checked out. The electronics have been placed for the most part in equipment racks and the cabling and interfacing between it and the VME crates is reestablished. We had some problems with bacterial contamination in the water, for the most part that is remedied. We also had problems lowering the relative humidity to the point where it is safe to set up the EO modulators, addition of a dehumidifier lowered the relative humidity to a reasonable level.

Upcoming Meetings and Reviews

International FEL Conference, Beijing, August 18-22, 1997

SURA Science and Technology Review, Sept. 16-17, 1997

Construction Project Close-out Meeting, Oct. 1-2, 1997

Scientific Opportunities for Fourth Generation Light Source, October 27-29, 1997