IR FEL Monthly Report for May 1997
Navy IR Demo Contract WBS Elements
WBS 1 Project Management
May 1997 was the eleventh full month for the IR Demo project funded
by the Navy.
Management
The IR FEL Demo project through the month of May 1997 has a total
of $6,222K (less SRF and building) of performance scheduled.
The work performed through the current period is $5,376K or 67%
complete of 77% scheduled. The actual costs accrued through May
totals $6,251k. This results in a schedule variance of -$845k
(an decrease of $221k) and an increase in the negative cost variance
to $875k (an increase of $99k).
The Office of the Secretary of Defense released $6M of Fiscal
1997 funding to the Office of Naval Research to support the Navy
High Energy Laser (HEL) Program. Follow-up discussions are underway
between the Navy HEL Program Office, Jefferson Lab, and the DOE
Site Office concerning the allocation of the funding. A revised
Navy-DOE memorandum of Agreement supporting release of the new
funds to Jefferson Lab is in preparation. A portion of the Fiscal
97 funds would be used for precommissioning and commissioning
the baseline IR FEL Demo and to begin the design and fabrication
of an upgrade of the IR Demo. A revised proposal for the upgrade
reflecting the use of both Fiscal 97 and potential Fiscal 98 DOD
was prepared and forwarded to the Navy HEL Program office.
Lots of high level activity occurred in Washington this week concerning
potential FY98 funding for the FEL program. Senator Warner requested
a briefing from ONR management on FEL R&D for Naval applications.
A follow-up briefing will be held on Monday, June 2, with Adm.
Baciocco (the chair of MTAC), and representatives from SURA and
Jefferson Lab.
A teleconference was held during the month with the DOE Site Office
(Wayne Skinner), Jefferson Lab Finance Dept. (Jim LeMaire), the
Oak Ridge Field Office Finance Dept. and Gordon Smith to discuss
the end of project billing procedure. The purpose of the conference
was to work out procedures for ensuring that the construction
project is fully billed to the Navy before the end of September.
We began preparations for two important FEL program meetings coming
up next month. On June 9-10, MTAC will convene for its second
meeting at Jefferson Lab. Agenda items were discussed with the
SURA office prior to preparing a draft agenda for review by MTAC
and the Navy HEL program office. We will take the opportunity
during the June 25-26 LPC Workshop to hold a meeting of the Industrial
Advisory Board (IAB). A letter was distributed to the IAB listing
agenda items concerning industry commitments to the FEL project
and agreements for equipment consignments and loans to the User
Facility
Jefferson Laboratory welcomed a number of important visitors to
the Laboratory this month who were given briefings and tours of
the Lab's Facilities: Peter Rosen, Head of the High Energy and
Nuclear Physics Program Office for DOE and Andrew Sessler, Director
Emeritus of Lawrence Berkeley National Laboratory and president
elect of the American Physical Society. In addition, meetings
were held with Mark Pelaez, Vice President and Director of Engineering
of NNS, and Dr. Ralph Romero, Engineering Manager of Solarex,
Inc., about collaborations with the FEL program.
Important accomplishments for the month include the successful
re-start of photogun measurements on the Injector Test Stand.
Excellent progress was made on characterizing the performance
of the gun at 350kV. The wiggler arrived at Jefferson Lab and
after shipping problems was accepted from STI Optronics. Significant
progress continued on the fabrication of the User Facility and
the critical path electron beam transport components.
At the second Virginia Technology Summit, held in Richmond on
May 21, the FEL Program was given high visibility in presentations
by Senators Robb and Warner, the two gubernatorial candidates
from Virginia, and from the group leader for a task force on high-performance
manufacturing initiatives.
F. Dylla was invited to make a presentation at the Combustion
Science Workshop held this week in Chantilly, VA sponsored by
DOE-BES. Several attendees expressed interest in using the IR
FEL for combustion research.
Proposals were received from Dan Henkel (HMT) and Shanti Nair
(U. MA) for summer studies that would lead to formal proposals
to be submitted to DOE-BES for laser-metal interactions.
Mike Kelley, DuPont, chairman of the LPC, visited the Lab on May
14 to discuss draft agreements to cover the loan and consignment
of LPC supplied equipment for the FEL User Facility.
A total of 14 papers related to the FEL project were presented
by members of the Accelerator Division at this week's Particle
Accelerator Conference in Vancouver, Canada.
WBS 5.0 Instrumentation & Controls
Beam Instrumentation:
All 25 stripline BPMs have been delivered. These have been QA'd
and passed through the CEBAF electron beam welder to correct for
potential cracking on the electrical feedthru. Two of these were
damaged during the repair process, these are being fixed in the
CEBAF machine shop. The beam viewers are complete except for
the wiggler flag assembly. These will be fitted with 1.5 micron
aluminum foil and mounted in the accelerator enclosure as needed.
The Happek interferometer is scheduled for testing at Vanderbilt
in early July. The first of the two units is complete, the second
is nearly done. The M56 bunch length cavities are in production.
The electronics for these devices are essentially complete.
Safety Systems:
The personnel safety system installation is proceeding well.
The cable pull was completed on schedule and the racks are installed
and powered up. Most elements of the system will be complete
for the July 1 cooldown of the quarter cryomodule. The Machine
Protection System (MPS) design review is scheduled for June 26.
The Argonne MPS boards are being fabricated.
Controls:
The HP server computers are being setup in the software groups
offices. These will be moved to the new building in late June.
Software efforts continue.
DC Power:
System documentation continues. The trim rack power supply cables
are being fabricated in the service building.
Vacuum Controls:
The two vacuum control crate's designs are complete, fabrication
and wiring will begin in June. The ion pump power supply control
cards were delayed 2 weeks from a problem at the PC board vendor.
These boards will be sent directly to the assembly house for
stuffing.
WBS 6 Cryogenic Distribution
All major TL welding complete. All Vacuum Jackets are being pumped.
I&C engineering and fabrication are both complete. Installation
will be completed after 1/4 Cryomodule is in the FEL building.
4 of 5 U-tubes for CHL connection are complete. #5 is 75% complete.
U-tube designs for the 1/4 Cryomodule in the FEL building were
released. The shield return U-tube is 60% complete but on hold
for TL installation. Working final connections of gas lines at
Flex can. Gas lines in tunnel are complete. We are on schelule
for July 1 cooldown. Detail plans still need to be made.
WBS 7 Beam Transport
All remaining dipole magnets were able to start fabrication during
the month while some parts are already complete on some styles.
A first trial assembly of magnets where a Everson Electric attempted
to glue Mu metal and brass to pole pieces was not successful.
A plan is in place to prototype this assembly to achieve success.
The sextupole cores are about to be contracted while the trim
quad design package is in checking. The fabrication of the long
Panofsky-style quadrupoles for the recirculation dump was awarded
to New England Electric Co.
The remaining quads went through and passed magnetic tests.
Engineering concentrated the correctors for 43 locations. The
specification is 1% harmonic content while the standard design
used for the CEBAF, with 3% harmonics is not good enough. Prototyping
a design based on mu metal as a core material yielded acceptable
harmonic content but still had the disadvantage for operations
of exhibiting hysteresis. At month's end, discussions indicated
the most difficult high aspect ratio correctors in the arcs and
the phasing dipoles may be able utilize the mu metal design even
though hysteresis is present. This will have to be accepted by
the commissioning group before adoption.
Additional analysis indicated that reducing the maximum required
field integral on the remaining correctors (air core) by 44% is
a prudent change to the requirement. We will start the TOSCA
magnetic modeling once we have chosen a direction. At the same
time, a vendor is putting together a preliminary proposal to produce
most of the air core correctors.
In the vacuum system, parts for the vacuum chambers for the optical
chicane are out for bid and the chamber for the 180 degree dipoles
was signed off. Northrop Grumman completed details for the first
of six return bed chambers.
We made good progress on the assembly drawings for the optical chicane and
first-light beam line and on design of the insertable dumps.
Stands for the Optical Chicane and the injector were installed
in the enclosure.
WBS 8 RF Systems
Final testing and calibration of the Chopper cavity was completed. The Quarter cryomodule
heaters were tested and placed under CTF control. A new spare 50 KW klystron was received
last month with a loose input cable. The vendor has been contacted for instructions on how they
want it repaired. The first spare unit was returned. The 1427 MHz Drive Amplifier, Distribution
cables, connectors for the FEL Master Oscillator system are on
order and due to arrive in June. The Cathode Power Supply, High
Powered Amplifier, and 2 sets of Low Level RF racks were moved
to their final position in the FEL building.
The high voltage power supply gas-filled transmission line elbow
components are out for bid. The gun power supply high voltage
tank was installed in its final location. The legs were cut by
a couple of inches to align the output flange with the beam centerline.
Hipotronics has been working hard on fabrication and final assembly
of the klystron power supply during the month of May, but it
still looks like the delivery date will slip about two to three
weeks. (mid to late June) We are working with Sanford Jones
at Pollydata, Inc., to develop the Magnetostrictive tuner system.
Sanford will submit a proposal early June. We plan to make a
rudimentary test on the cold cryounit during June if possible.
The third (spare) 50 KW RF circulator is on site, and will be
run for acceptance test during June if possible.
WBS 9.2 Injector Move
Design of all components in the injector except the optical transport
line was completed in May. The layout design for the transport
design was completed and details begun. The laser clean room
was delivered and partially installed. The completion of the
clean room was delayed by two weeks due to delays from the subcontractors
to Clean Air Technology. The flooring and air handling unit were
delayed by at least two weeks. The plan is now to install Jefferson
Lab equipment in parallel with clean room completion so that the
overall schedule slip is lessened. The high voltage power supply
tank was installed but needed to be modified before it could be
moved into its final location. The modifications were completed
by month's end. The design for the crane rails for the gun and
cryounit were completed and all the parts ordered. The rail will
be ready for the cryounit move on June 16.
WBS 9.4 Wiggler
The wiggler was delivered from STI Optronics on May 12. All the
vertical shock indicators in the box were tripped. We believe
that the wiggler crate slid off its palate and fell several inches.
Measurements of the wiggler indicated no shift in the relative
position of the wiggler jaws and discussions with STI Optronics
did not lead us to believe that any damage could be done to the
wiggler. We therefore accepted delivery of the wiggler. It is
now ready for installation on the wiggler girder. The machine
shop was successful in producing wiggler vacuum chamber tubing
of very uniform cross section and flatness. This will be used
to test the welding techniques before final assembly. All drawings
for the wiggler vacuum chamber and its support as well as the
wiggler girder assembly drawing were signed off. The parts for
the wiggler vacuum chamber support were ordered. The are due
in mid June.
WBS 9.6 Optics
FEL
We received the hardware for mounting the upstairs optical transport
pipe. The stands for the optical tables supporting the cavity
assemblies and collimator arrived and were grouted in and one
of the tables was moved downstairs in anticipation of installation.
The mirror cans and diagnostic pickoffs will arrive in early
June. We can then make real progress to finish installation of
the optical transport. The stepper motor chassis and optical
hardware were built and turned over to the software engineer for
testing. This is proceeding well. The last fabrication process
on the optical cavity assemblies was completed. The optical collimator
design was completed, signed off, and is being fabricated at a
local machine shop. We received 5 micron mirrors from Rocky Mountain
Instruments, one set was shipped to China Lake for testing, the
other two sets were returned, as they did not meet specs.
ITS
The photocathode drive laser was operated ~ 407 hrs. in support
of gun experiments. The longest continuously operating period
was ~ 100 hrs. We now use two variable-speed EO modulators, built
using AR coated crystals, rather than index-matching fluid. The
bias on these modulators may be changed from the Control Room,
in order to optimize the net extinction ratio. There is also
remote control of the macropulse and micropulse frequency, this
was thoroughly exercised and worked well. The divide-by-two EO
modulator continues to be problematic; progress will be slow until
gun experiments conclude in June.
Injector, SRF, Facility, and Other
Activities Outside Navy IR Demo Contract
INJECTOR TEST STAND
Regarding the photocathode gun, the month began with a plethora
of technical difficulties, but it ended with a gun that was operating
well at 350 kV cathode stand-off voltage. Early on, the photocathode
efficiency would degrade rapidly to a uselessly low value. We
hypothesized that this was due to the presence of field emission,
and to reduce it we ultimately opened the gun and reinserted the
cathode-anode spacer to lower the electric field at the cathode
(but not the operating voltage, which remained at 350 kV). In
conjunction, we made a novel modification to the gimballed mount
of the gun which allowed disassembly without affecting the beamline
valve, thus preserving the beamline vacuum and thereby saving
considerable time.
After reassembly and baking, the gun performed very well at 350
kV. However, we remain unsure about the cause of the earlier
cathode degradation. Cursory examination of the degraded cathode
under a microscope revealed that it was "frosted" (the
arsenic was vaporized out of its surface), a condition that could
lead to field-emission sites. This was probably caused by heat
cleaning at too high temperature when we were attempting to heal
the field-emission sites by cleaning near 700 C. Consequently,
we retained our standard baking temperature of 580 C when preparing
the reconfigured gun for operation with beam.
The initial cathode degradation in the reconfigured gun was not
bad, from 7.2% to 4.3% in the first 24 hours of operation. The
dark current (field emission) was measured at 1.3 nA at 350 kV
cathode voltage; however, measurements indicate the emission current
doubles in magnitude for every 10 kV increase in cathode voltage,
as is consistent with the Fowler-Nordheim equation. We measured
bunch lengths at bunch charges of 1, 10, 60, and 135 pC at 350
kV. We also measured transverse emittance at 1, 30, 60, 100,
135 and 150 pC/bunch. However, we observed some beam scraping
during the transverse measurements and subsequently verified the
light box as the location using Geiger-Muller tube detectors.
By month's end, we had begun an investigation to determine ways
to reduce the scraping.
Further high-power radiofrequency (RF) testing of the cryounit
remained on hold pending development of suitable warm ceramic
windows. Qualification of the interlocks on the cryounit was
completed to aid in preventing accidental window breakage like
that which occurred during last month's unsuccessful qualification
tests. Two completed ceramic-warm-window assemblies were tested
in air up to 50 kW, during which they demonstrated good performance.
However, during preparation for final qualification in the vacuum
fixture, one of the warm windows cracked. This failure was not
associated with rf operations; its cause is not fully understood.
Meanwhile, construction of the FEL Facility has been proceeding
rapidly, and its cryogenic system will be ready for commissioning
1 July 1997. The injector cryounit needs to be installed there
by that time to constitute a load for the cryogenic system. In
view of the short time remaining, we reformulated our plans for
warm-window development. For the immediate need, we successfully
tested and qualified two ceramic warm windows to 10 kW in the
resonant ring and vacuum-test fixture. This will enable running
the injector with 1.1 mA average current and thereby support all
planned commissioning activities and beam-physics experiments
through achievement of first light. The windows are to be installed
in the cryounit on 2 June 1997. A short cold test of the cryounit
will follow to characterize window/waveguide performance.
Work will continue on production of 50 kW ceramic warm windows
for installation in the cryounit sometime after its move to the
FEL Facility. The short-term plan is to produce six 50 kW windows
based on the existing design, which has performed satisfactorily
under "normal" operating conditions; recent failures
are attributed to off-normal operations that led to run-away conditions,
depositing extreme amounts of RF power into the windows. Two
medium-term programs are ongoing to provide alternative solutions
for RF warm windows, the BeO Northrop Grumman windows, and redesign
of Jefferson Lab windows. Regarding the former, ceramics are
in-house, flanges are in production, and final assemblies are
due to be completed by the end of June. Regarding the latter,
the JLab design uses a thin wall, water cooled, copper waveguide
support for the ceramic braze joint. Ceramics have been ordered
from Wesco and will be ground locally. Prototype assemblies are
expected in August 1997.
WBS 3 - CRYOMODULE
ITS Operations
Two new ceramic warm windows were installed on the 1/4 cryomodule.
These windows are rated at a reduced power level of 10 kW and
will support first light operations. All cryomodule interlock
systems underwent a complete ground up qualification in preparation
for additional cryomodule operations. Both cavities were run without
incident. Waveguide vacuum conditioning was required and was accomplished
in 1-2 hours to reach the 10 kW power level. Waveguide vacuum
and thermal performance was consistent with stable 50 kW operations.
Warm Windows
An additional warm window was qualified to 10 kW operational levels
and installed with the existing window, qualified to 20 kW, on
the 1/4 cryomodule in the ITS cave. These windows have been tested
and will support first light operation. Work continues on producing
warm windows for 50 kW operations. These efforts continue to focus
on ceramic material performance and RF loss tolerant designs.
Ceramic material from several vendors is being tested and characterized
for window production. Additionally studies are ongoing to understand
the effects of the firing processes required during window fabrication.
At this time ceramic material has been identified with considerably
lower rf losses that should lead to satisfactory windows. Two
alternate designs being pursued with Northrop Grumman and personnel
from SLAC are proceeding and look promising.
Cryomodule Production
Cavity pair assembly and vertical testing has been completed.
All cavity pairs have been turned over to the cryounit assembly
area. The second cryounit assembly is close to completion and
turn over to the cryomodule assembly area. The remaining two cryounit
assemblies are proceeding without issue. Cryomodule assembly has
installed one beam pipe and is proceeding without issue. Cryomodule
assembly schedule remains tight but still doable.
WBS 2 -- BEAM PHYSICS
The main consequence of the experimental finding in the ITS that
there is scraping of the outer portions of high-charge bunches
inside the light box is a reduction in the measured transverse
emittance of these bunches. The outer parts of the beam are weighted
heavily in the coordinate and velocity moments that comprise the
transverse emittance. Consequently it is more difficult to compare
the experimental results with scraping to numerical simulations
wherein scraping is absent. In view of this development, we embarked
on a series of numerical simulations to assess whether scraping
can be significantly reduced or eliminated by varying the laser
spot size at the photocathode. For instance, one would expect
space charge to have less influence in a larger beam, so perhaps
increasing the spot size will reduce scraping. At month's end,
the investigation was in progress.
Simulations from cathode to wiggler were also done by including
the cathode-anode spacer for lower electric field at the cathode,
as is now the case in the ITS. The present status is that it
has been easy to find settings that deliver the required beam
at the wiggler, but the bunch lengths in the injection line are
longer than desired given the performance specifications of the
interferometric bunch-length diagnostics that will be installed
there. These simulations are continuing in an effort to find
solutions with acceptably short bunches in the injection line.
Considerable progress was made toward identifying a suitable start-up
scenario for high-current operation of the FEL. The accelerated
and decelerated currents are within 1.5 degrees of being out of
phase with each other, and this helps greatly to keep rf transients
tractable. There are several start-up scenarios that appear viable,
but perhaps the best option combines a gradual ramp-up of the
bunch frequency with a gradual ramp-up of the charge per bunch.
This aids in keeping rf transients quiescent in the injector,
which turns out to be the major concern.
The Particle Accelerator Conference was held 12-16 May 1997 in
Vancouver, BC, Canada. Fourteen papers related to the FEL were
presented by members of the Accelerator Division. Among these
were two on the theory of coherent synchrotron radiation (CSR),
and they were well received. We were able to discuss our plans
for simulations with other CSR investigators, most notably those
from DESY who have developed a simulation tool to characterize
the buncher chicanes planned for the TESLA FEL. The DESY people
have done excellent work and have been innovative in overcoming
some of the inherent complexities. However, their code uses "particles"
in the form of sheets in the vertical plane that move on orbits
that are predefined by way of assigning them specific initial
conditions. As they propagate, the sheets set up a model force
that influences orbits of test particles. A disadvantage of this
approach is that discreteness in the horizontal plane can generate
artificially high numerical noise. Moreover, self-consistency
is lost because there is no feedback from the evolving distribution
of test particles to the force generated by the sheets. By contrast,
we will use macroparticles in the bend plane, each with a Gaussian
density profile to ensure continuity of the beam and thereby suppress
numerical noise, and we will let them move self-consistently.
We (in particular, Rui Li) are trying to develop an efficient
algorithm for the force calculation, and discussions with the
DESY people at PAC suggested a refinement in our approach that
should lead to more efficient calculations. Once developed, we
will be able to simulate the IRFEL lattice and make predictions
to compare with results of the planned experiments. We also will
be able to assess the efficacy of alternative lattice designs
that have been proposed, e.g., by SLAC and Duke at the PAC, for
canceling the CSR force.
Regarding other PAC highlights, our work on the multislit transverse-emittance
diagnostic received considerable interest. That the team was
able to build and commission this device with beam from the photocathode
gun prior to the PAC is a noteworthy accomplishment. There is
also considerable interest in the accelerator and FEL communities
in developing x-ray sources by way of Thomson scattering from
electron bunches, and several papers were presented at PAC on
this subject. We (specifically Geoff Krafft) also presented a
paper concerning production of short (picosecond), bright x-ray
pulses that will occur as a by-product of lasing with the FEL,
showing that the FEL competes well with other potential sources
of short-pulse x-rays, and that upgrades of the machine will likewise
generate even brighter x-ray beams.
WBS 4 -- IRFEL COMMISSIONING/OPERATION
A task list and schedule was drafted to generate the remainder
of the commissioning plans prior to 1 Oct. 97. First-light commissioning
plans are already done. What remains is to develop the plans
to get full-power operation following first light. We settled
on an overall commissioning process in which a "commissioning
planner" coordinates the activities of "principal investigators"
and an "FEL experimental coordinator". The latter will
interface with the "program deputy", who in turn directs
the activities of the machine operators. Interfaces between these
principals, FEL management, and Division management have been
identified. Having settled on this overall commissioning process,
we made a first cut at defining commissioning "teamlets"
to turn on various IRFEL systems. This is one of the first steps
in lining up necessary manpower, an effort that will evolve continually
in the coming months.
Detailed plans were formulated for the content and manning of
upcoming gun experiments in the ITS. The content is essentially
unchanged from earlier plans that had been postponed due to the
field-emission problems discussed in the Injector Test Stand section
above. However, we are uncertain whether it would be prudent
to spend the time necessary for executing all of those original
plans, i.e., to characterize the longitudinal and transverse beam
properties at bunch charges pertaining to "zero current",
first light, and full-power operation, then to look at photocathode
lifetime, performance at higher voltage, performance at other
bunch charges, etc. Final decision on priorities awaits the outcome
of the experiments in progress, as well as input from our Navy
sponsor.
We made considerable progress establishing locations and types
of weak-field corrector magnets based on the measured performance
of various prototypes constructed to date. This activity is continuing,
and our goal is to finish it very soon, pending the outcome of
additional measurements in our Magnet Test Stand of existing prototypes
that have been slightly modified for what hopefully will be improved
field quality.
Facility
This month again showed rapid progress on the facility. The exterior siding was completed. By the end of the month the labs were ready for occupancy and drywall work was ready to begin downstairs and in the stairwell. Drywall work was completed in the injector area and the equipment room. Painting was completed in the gallery and labs. The stairwell and spire glass were installed. All HVAC units were connected to chilled water. HVAC return ducting was completed. Plumbing work was completed less the fixture installation. Tiling was 90% complete in the labs and gallery and started in the bathrooms. Electrical progress was also great.
Hookup of the HVAC units was underway at month's end. The wall
outlets had been powered and tested. The cryogenic lines finished
welding into the system after welding of the sleeves and installation
of the transfer lines in the sleeves. We finished hooking the
dump skid to the low-contamination water (LCW) pipes. Upstairs,
Jefferson Lab crews began installing the LCW pipes on the walls
after installing and painting the unistrut holders. The LCW hookup
to the South Linac occurred over Memorial Day. We performed the
cable pull from the Machine Control Center. A termination box
was mounted on the side of the building, and holes were punched
into the communications room. The communications rack was hooked
up in the communication room. Safety systems finished box duct
installation and began pulling cable and hooking in run/safe boxes,
etc. The pressure vessel for the gun HVPS was set in placed, cut
to the proper height and grouted in. RF staff placed racks in
final position above the waveguide penetrations. The elevator
installation was begun. The hydraulics were set in the room and
plumbed in. The shaft was installed in the main hole. The optical
tables for the accelerator vault were received. Delivery of stands
for the wiggler and the optical tables occurred. Approximately
20 optical-table, magnet, and wiggler stands were bolted in downstairs
along the first-light line. A landing pad was constructed, attached
to the outside of the facility's loading door, and load tested.
Dirt is finally dry enough to be mounded up around the building
with building grounds and sealing blankets being installed next
to the concrete. Design detailing on the clean room was completed
with finalization of the electrical wiring plan. Despite having
to co-exist around tilers, electricians, etc., the photo-injector
clean room was delivered, assembled, and installed except for
electrical hookup, and installation of the air handler. The facility
is on track to be complete in early July and at the present time
presents no significant limitations for the installation of FEL
hardware.
Upcoming Meetings and Reviews
SURA Maritime Technical Advisory Committee, June 9-10, 1997
Laser Processing Consortium Meeting, June 25-26, 1997
International FEL Conference, Beijing, August 18-22, 1997
SURA Science and Technology Review, Sept. 16-17, 1997