Next Meeting
R. Legg, C. L. Bohn, G. Neil, B. Yunn, D. Douglas
We also do not have the diagnostics presently installed to easily say exactly what the problem is. We are presently still planning to do the sensitivity runs and use the best correctors feasible.
Items of Discussion
----------------------
New Issues
----------
Action Items
------------
Action Priority Items (assigned)
----------------------------------A-15 1 Commissioning Procedure Legg, Krafft 5/16/96 A-19 0 Web Documentation weekly A-24 1,2 Beam loss Bohn A-30 1 Burnthrough/Conflat Expansion Denard, Kloppel A-34 2 Consistent Linac phasing plan Yunn A-42 2 2nd gun for long term tests Bohn 10/1/96 A-44 1,2 Start Rui on emittance code Bohn 8/13/96 A-47 1 OTR beam interaction number by Denard 9/11 A-55 1 Laser Diagnostic Proc Benson 11/1/96 Action Items (pending)
------------P-05 1 Devise fine-tuning procedure for buncher gradient Krafft/Kehne P-08 1,2 How do we change energy? What is the energy range? Benson P-14 1 How is the gun/laser operated? Benson P-15 Discussion on robustness of controls Legg P-19 2 Consistent linac/bunching phase sets Yunn P-20 1 Lock plans (who in particular) Johannes? P-21 1 Save/restore plans Benesch P-25 1,2 RF control sensitivities/ Merminga Microphonics Diff for FEL/ Pathlength effect P-29 2 FEL/linac interaction Merminga P-30 2 Tracking including realistic wiggler fields Douglas P-37 1 42 MeV dump design and interlocking Wiseman Agenda for Next Meeting ----------------------- Item Person Responsible Time ---- ------------------ ---- * Review agenda/corrections to minutes Legg 5 min. * How the rf will go CW Merminga 20 min * Milestones for ER test plans Legg 20 min * New issues All 10 min * Agenda for next meeting All 5 min.