Free Electron Laser Commissioning Meeting
Friday, 24 Apr 98
Recorder: C. Bohn
***** SEE PERSONNEL SAFETY AND MACHINE PROTECTION POLICIES UNDER
NEW ISSUES BELOW *****
Next Meeting
- Date: 1 May 98
- Time: "0845"-0945
- Place: FEL Facility Break Room
Agenda for Next Meeting
Item Person Responsible Time
---- ------------------ --------
Status of Open Action Items All 5 min
Scheduling and Commissioning Program Bohn/All 50 min
New Issues All 5 min
This Week's Attendees
S. Benson, G. Biallas, C. Bohn, J. Boyce, D. Douglas, F. Dylla,
J. Fugitt, A. Grippo, L. Harwood, K. Jordan, R. Li, L. Merminga, D. Oepts,
P. Piot, M. Shinn, Q.-S. Shu, R. Walker
Closed Action Items
- Fugitt/Bohn: Start Operator Limit log in FEL binder.
- Status: A list of operator limits is posted in the FEL binder in the MCC. It
will be continuously augmented and revised.
- All FEL'ers: Read Accelerator Operations Directives, a copy
of which can be obtained/borrowed from R. Lauze.
- Status: There is a list of FEL Operator Prerequisites posted in the
FEL binder in the MCC, of which reading the AOD is one.
- Merminga: Determine whether a change in procedure is needed
for ramping up the current, and if so, revise the existing procedure.
- Status: The procedure is, in essence, to start high-current runs with the
cryomodule cavities on crest, then gradually move them to 9.6 degrees off
crest. This is now an item in the FEL Metaprocedure.
- Mahoney: Prepare procedure "MPS/BLM Checkout for First
Light".
- Status: This is not closed, but is a longer-term process. A draft is
written, J. Coleman assists personally with BLM setup and checkouts, and as
operational experience is gained, Coleman and Mahoney will be updating the
procedure.
Items of Discussion
This week was devoted principally to miscellaneous measurements of beam
quality, as well as improving the injector setup, but it also included a
few cw runs up to mA-level average current at 38 MeV energy to the
straight-ahead dump. We are generally measuring six-dimensional
phase-space parameters of the beam that are within factors of 2-3 of
theoretical, a favorable situation given that we just turned on the
machine. It means there are no apparent show-stoppers to lasing, but fine
tuning is needed beforehand. Specific measurements performed this week
include rms normalized transverse emittance at the cryounit exit (7-8
mm-mrad vs. 3.5 mm-mrad from PARMELA), rms bunch length at the center of
the cryomodule (about 2 ps, vs. 1 ps desired at the wiggler), rms energy
spread at the center of the first optical chicane (0.5% vs. 0.15% desired
at the wiggler), and a rough sense that the emittance at the wiggler is not
too far from the 9 mm-mrad desired in that most of the electron beam can be
threaded through the mm- size holes in the three wiggler viewers. Getting
a sufficient array of beam diagnostics working and using them to configure
the quality of the electron beam at the wiggler location are now our
highest-priority tasks. They will occupy the bulk of our commissioning
time in the next two weeks, in which will be interspersed some cw runs at
high average current to exercise the machine and get more data on cathode
lifetime.
Shift assignments for the next two weeks are (remember to
use the CEBAF operator!):
27 April - 1 May 1998:
- Owl -- Oepts, CEBAF operator, Shu on standby
- Day -- Li, CEBAF operator, Douglas on standby
- Swing -- Benson, CEBAF operator, Krafft on standby
4-8 May 1998:
- Owl -- Preble, CEBAF operator, Piot on standby
- Day -- Biallas, CEBAF operator, Douglas on standby
- Swing -- Krafft, CEBAF operator, Shinn on standby
S. Benson presented a synopsis of electron-beam requirements for first
lasing. They are documented in the talks for the "IR Demo Commissioning
Workshop" held here during 24-25 Jul 96, so rather than repeat all the
numbers, I'll give some of the principal ones: normalized rms transverse
emittance <8.7 mm-mr, rms longitudinal emittance <33 keV-deg, beta function
at wiggler 33+/-6 cm, energy spread <0.15%, peak current >22 A, rms bunch
length <1 ps. It may still be possible to have sufficient gain for lasing
even if some of these are not met, so long as others are better. Benson
has developed a spread sheet to calculate gain given the beam parameters,
and it will be our tool by which we determine when to install the wiggler
and go for it. We will not install the wiggler until we have sufficient
electron-beam quality and sufficiently stable and reproducible machine
operation. We will not install the wiggler on "1 May 98", but we will be
sensibly expeditious.
C. Bohn summarized a list of test plans and procedures to prepare for
lasing that came out of an off-line meeting Wednesday. The list is
incorporated at the end of these minutes, along with principals and due
dates. The principals will be seeking help and advice as they write their
respective documents.
There was some discussion about policies concerning personnel
safety and
machine protection. Bohn worked through the various questions in
consultation with A. Hutton this morning, and the ensuing policies are
documented under New Issues below.
Continuing from the last two weeks' discussions, a list of remaining
MUST-priority prerequisites to lasing, and their status, is:
1. Stable, easily recoverable 1.1 mA, 38 MeV beam with
sufficiently good beam quality.
Status: See Items of Discussion above.
2. Working diagnostics:
- Happek bunch-length monitor (or backup).
Status: Still not sure when Happek will be delivered. We
are implementing a backup plan that will be useful in any case: G. Krafft is in
process of procuring a CSR monitor for use at one of the synchrotron light
ports in the first optical chicane. It can be used to "minimize" and
monitor bunch length, and it can be calibrated against the zero-phasing
technique. Energy spread can be measured at the first optical chicane with a
viewer there and MaxVideo. The M_56 cavity provides additional
longitudinal phase-space information.
- Multislit transverse-emittance monitors (#1 is working
routinely, #2 is not working).
Status: There is some question as to whether the
Multislit #2 viewers are sufficiently well aligned. The beam needs
to be orthogonal to the multislit to within 5 mrad for the device
to work. Despite spanning through the entire accessible parameter
space, attempts to correct the orbit at the viewers were not
successful, which leads to the question. Work is still needed here.
- Quad/Viewer transverse emittance diagnostic at wiggler.
Status: Tonight's swing shift is devoted largely to this item.
3. Adequate injector setup.
Status: Continuing. Not obvious we have a real problem here.
4. Detailed procedures and test plans well communicated to MCC staff.
Status: Ongoing. See, for example, list at end of these minutes.
5. Working optical transport, including Laser Safety System for
the Optical Control Room.
Status: Largely, but not fully, complete.
6. Radiation monitor at wiggler location (to protect wiggler).
Status: Detector ready and will be tested shortly.
New Issues
Two irregularities in FEL operations occurred in the 24 hours preceding
this meeting. First, during day shift yesterday the FEL console was left
unattended with the drive laser shutter open. Second, during owl shift
today one of the BLMs was intentionally masked and the beam was taken to cw
without seeking approval from the FEL Commissioning Coordinator (FEL CC).
These facts generated some broad discussion about general safety matters,
and clarification is needed. After the meeting, Bohn met with A. Hutton
and the outcome of the meeting is the following two policies:
- The MCC crew chief is in charge of personnel safety. The FEL
PSS will continue to be operated from the MCC. CEBAF operators will man
the Safety Console and will provide SSO functions.
- The FEL crew chief will exercise prudent judgment in matters
of machine protection and is permitted to operate the FEL within the
constraints of the FEL Operator Limits Page (FEL OLP) posted in the FEL binder
in the MCC. FEL CC will maintain the FEL OLP. If the FEL crew chief sees
benefit in operating outside one or more of these limits, that person must
first contact the FEL CC for authorization and then document the fact
that authorization was obtained. (Note: The FEL crew chief is the
individual assigned as prime to the shift, and is neither the individual
assigned as "standby" nor the assisting CEBAF operator.)
New Action Items
- Krafft/Dylla: Ascertain when Happek and crew are going to show
up with their device, or whether we should send someone there to help
them along.
- Benson/Douglas/Walker (et. al.): Write test plans and
procedures per list below.
Old Action Items
- Walker: Work with Operations Department to develop an FEL
Alarms Handler software page for use in monitoring the FEL from the MCC
Control Room.
- Status: Done in draft, but will take time to finalize.
(due 29 May 98)
Test Plans in Work
- Improve Current Instability (dI/I) Benson, 28 Apr 98
- Measure Beam Stability Benson, 15 May 98
(dE/E, dx, dy, dx', dy')
- Measure Timing Jitter Benson, 29 Apr 98
Procedures in Work
Set Up Longitudinal Phase Space Douglas, 15 May 98
Set Up Transverse Phase Space Douglas, 15 May 98
Set Up Beam Steering Douglas, 15 May 98
Checklist for CW to Pulsed and Vice Versa Walker, 24 Apr 98
Emittance Growth from CSR
- Tomographic Phase-Space Map Piot, 30 June 98
- Back Leg Thread Douglas, 30 June 98
Procedures Needed for Recirculation
Thread Beam around Machine, Top-Level Douglas, finalize 30 June 98
RF Stability during Energy Recovery Merminga, 30 June 98