Free Electron Laser Commissioning Meeting

Friday, 12 Dec 97
Recorder: C. Bohn

Next Meeting


Date: 19 Dec 97
Time: 0830-0930
Place: FEL Facility Break Room

Agenda for Next Meeting


Item Person Responsible Time ---- ------------------ -------- Status of Action Items All 5 min Progress Report on Commissioning Legg/Bohn 5 min Scheduling Update Bohn 10 min Summary of SRF/RF Limits Merminga 15 min Beam Optics Spread Sheet Douglas 15 min New Issues All 5 min Agenda for next week All 5 min

This Week's Attendees


J. Bennett, S. Benson, C. Bohn, J. Boyce, D. Douglas, D. Engwall, G. Krafft, R. Legg, R. Li, R. May, L. Merminga, P. Piot, Q.-S. Shu, A. Todd (Northrop-Grumman), B. Yunn

Closed Action Items


The following actions from last meeting's report were closed out:

Items of Discussion


All "operators" need to visit the FEL Control Room and view B. Legg's movie on how to set up the injector preparatory to running beam. The wise operator will do so early next week, at latest, because...

The two replacement vacuum valves that protect the cryomodule were shipped from VAT in Switzerland on Wednesday, not last Friday as had been hoped. According to J. Preble, as reported late this morning, they were still in Customs in Memphis, TN, and are to come directly to us from there. We now anticipate receipt Monday morning, with installation slated for late Tuesday, followed by cryomodule cooldown. Commissioning activities with beam would then resume Wednesday.

Projected shift assignments and tasks up to Christmas break are written on the scheduling board in the FEL Facility Break Room. Affected parties also got an e-mail from R. Walker. The Commissioning Coordinator thanks you in advance, on behalf of the Lab, for getting tuneup beam to the straight-ahead dump before Christmas (and he especially thanks you for your dedication).

There has been considerable commissioning activity not involving electron beam. S. Benson and L. Merminga provided the following highlights since last meeting:

C. Bohn summarized the post-Christmas commissioning strategy, which is as follows:

Resume beam commissioning 26 Jan 98
Groundrules:

Commissioning strategy A detail: The 26 Jan 98 date is a little soft -- it could be a few days earlier, but it was selected for reference because it falls on a Monday.

R. May led an extensive discussion about when to make the FEL vault an RCA. His proposal is to do it next week when we go into 3-shift operation. Arguments pro and con were heard. The Commissioning Coordinator considers it his responsibility to make the decision, and he will do so on Monday after soliciting a bit more advice. For the record, May acknowledged that we have been complying with an existing OSP, treating the FEL vault in the same manner as a CEBAF vault during entry after running beam, and this satisfies regulations. The idea to impose RCA is basically one of reasonable conservatism for safety, and overall convenience from the standpoint of reducing the rope count in the vault.

D. Douglas presented his draft top-level procedure for threading the electron beam around the whole machine in preparation for energy recovery. In essence it ties together the various procedures for setting up sections of the machine. But there some additional aspects, chief of which is phasing the beam for deceleration. Douglas's plan calls for using a diagnostic downstream of the x-chamber to measure and adjust the beam's rf phase and M_56. This idea needs fleshing out, especially because the diagnostic is presently undefined. It could conceivably be the current loop, but the loop is not yet installed, nor is its performance well understood at this point. Dave agreed and will further ponder it next month.

B. Yunn has supplied "lots of pictures from PARMELA" that should be helpful in properly setting up the injector for first light.

New Issues


None.

New Action Items


Old Action Items


Procedures in Work


First Light Setup

Emittance Growth from CSR

Thread Beam around Machine, Top-Level           Douglas, finalize 31 Jan 98
RF Stability during Energy Recovery             Merminga, 23 Jan 98