Free Electron Laser Commissioning/Diagnostic Meeting

Tuesday, July 8, 1997
Recorder: R. Legg

Next Meeting


Date: July 15, 1997
Time: 3:00 - 4:00
Place: Bldg 89, Large Conference Room

Attendees


J. Bennett, R. Legg, C.L. Bohn, G.A. Krafft, K Jordan G. Neil, D. Kehne, G. Biallas, J. Boyce, P. Piot D. Douglas, Q.S. Shu, R. Walker, L. Merminga

Addenda/Errata to Previous Minutes


Items of Discussion
-----------------

New Issues
----------

Action Items
------------

* Action Priority Items (assigned)
------------------------------

A-15   1  Commissioning Procedure                       Legg, Krafft    7/16/97
A-19   0  Web Documentation                                             weekly
A-24  1,2 Beam loss                                     Bohn
A-34   2  Consistent Linac phasing plan                 Yunn
A-44  1,2 Start Rui, Jinhu? on emittance code           Douglas         8/13/97

Action Items (pending)
------------

P-05  1   Devise fine-tuning procedure for buncher gradient		Krafft/Kehne
P-08 1,2  How do we change energy? What is the energy range?		Benson
P-19  2   Consistent linac/bunching phase sets				Yunn
P-20  1   Lock plans (who in particular)				Johannes?
P-21  1   Save/restore plans						Benesch
P-25 1,2  RF control sensitivities/					Merminga
	    Microphonics Diff for FEL/
	    Pathlength effect
P-29  2   FEL/linac interaction						Merminga

Agenda for Next Meeting
-----------------------

                Item                              Person Responsible     Time
                ----                              ------------------     ----
    *	Review agenda/corrections to minutes	        Legg	         5 min.
    *	Commissioning Meta-plan				Douglas/Legg 	 30 min
    *   New issues					all		 10 min	
    *	Agenda for next meeting		                All		 5 min.