Free Electron Laser Commissioning Meeting

Friday, 7 Nov 97
Recorder: C. Bohn

Next Meeting


Date: 14 Nov 97
Time: 0830-0930
Place: FEL Facility Break Room

Agenda for Next Meeting


Item Person Responsible Time ---- ------------------ -------- Review of Minutes/Errata All 5 min Scheduling Update Bohn 15 min Progress Report on Injector Commissioning Legg 5 min DQ Dipoles (and other relevant magnet stuff) Douglas 10 min Master Oscillator System Status and Data Musson 15 min New Issues All 5 min Agenda for next week All 5 min

This Week's Attendees


J. Bennett, J. Bisognano, C. Bohn, J. Boyce, D. Douglas, D. Engwall, A. Grippo, R. Legg, R. Li, L. Merminga, G. Neil, P. Piot, J. Preble, Q.-S. Shu, R. Walker, M. Wiseman, B. Yunn

Addenda/Errata to Previous Minutes


The following actions from last week's report were closed out:

In addition, L. Merminga announced that she has finalized the procedure "Cryomodule Setup -- Set Cavities to Nominal Gradient".

Items of Discussion


The MCC-like scheduling boards are now mounted in the FEL Facility Break Room. Immediately following this morning's meeting they were filled out with the shift tasks projected for the next two weeks.

R. Legg and J. Preble presented this week's injector commissioning highlights:

J. Boyce discussed plans to use tune-up beam from the FEL to produce polarized targets in support of Nuclear Physics' GEN experiment. The plan is documented in Jefferson Lab Tech Note #97-041 entitled "A User Station for the FEL Beam Dump". It involves installing a dewar in the first-light dump line, with the dewar containing a solid ammonia target cooled by liquid argon or liquid nitrogen. After irradiating the frozen ammonia crystals with low-current electron beam to produce paramagnetic centers, the crystals can then be immersed in a strong magnetic field and exposed to microwave radiation, both in situ in the CEBAF experimental hall, to achieve the desired polarization. Optimal timing for use of the FEL for target production is early February. Accordingly, installation of the apparatus in the dump line is anticipated for January 1998. Our commissioning plan is to have tune-up beam at the first-light dump before Christmas 1997.

Boyce pointed out that 10 MeV electrons would suffice. G. Neil suggested that, while commissioning the injector, we may find that sufficient electron current penetrates through the copper block constituting the injector dump. If so, the dewar could then simply be positioned after the copper block. Consensus was to keep that option open as a potential back-up, but to continue planning as a baseline for installing the dewar in the first-light dump line. Doing so helps to motivate steady progress in commissioning, and is in keeping with existing hardware designs.

G. Neil advised that the vacuum pump designed into the first-light dump line is insufficient, and indicated that a 120 l/s pump is needed. M. Wiseman said the Mechanical Engineering Group is aware of the concern and is looking into it. (This appears as a new action item below.)

D. Douglas went through his draft procedure for "Beam Transport Setup from Cryomodule to First-Light Dump". It appeared to be complete, except for overlooking the need to do longitudinal phase-space diagnostics. The two interferometric bunch-length monitors, including both hardware and software, are due here from the University of Georgia on or about 5 Dec 97. In turn, they probably will be unavailable for use in commissioning with tune-up beam prior to Christmas, but they likewise are unnecessary for that task. As we turn up the average current in early 1998 to produce electron beam for first light, the bunch-length monitors will then be essential, and they should be commissioned beforehand per the Diagnostic Integration Plan. Douglas will augment his procedure to include longitudinal measurements.

New Issues


New Action Items


Old Action Items


Procedures in Work


First Light Setup

Emittance Growth from CSR

Thread Beam around Machine, Top-Level           Douglas, 1 Dec 97