R Legg will post/distribute D. Kehne's plan and schedule a meeting to discuss it.
Action Items
------------
Action Priority Items (assigned)
----------------------------------
A-04 1 Unit gradient precision Bohn, Liu A-05 2 Injector energy precision Douglas A-06 1 10 MeV dump optics Douglas A-09 1 Dump Instrumentation Legg 6/04/96 A-10 2 Back leg diagnostic placement Douglas A-15 1 Commissioning Procedure Legg, Krafft 5/16/96 A-19 0 Web Documentation Jordan weekly A-20 1 10->42 MeV dump Douglas A-24 1,2 Beam loss Bohn A-29 1 Software Planning for Longer Term Jordan (?) A-30 1 Burnthrough/Conflat Expansion Denard, Kloppel A-34 2 Consistent Linac phasing plan Yunn A-35 1 simultaneous transverse and longitudinal Kehne/Engwall 8/6/96 A-39 1 report on ARR plan Legg 8/23. A-41 2 Modeling of lower than 10 MeV injector kehne, Liu 10/1/96 A-42 2 2nd gun for long term tests Bohn 10/1/96 A-44 1,2 Start Rui on emittance code Bohn 8/13/96 A-45 1 decide on dump diagnostics Legg/Krafft 9/4 A-46 1 specify the field quality in the dipole shut off to run straight ahead Douglas 9/11 A-47 1 OTR beam interaction number by Denard 9/11 A-54 1 FEL Turn-On Proc S. Benson 11/1/96 A-55 1 Laser Diagnostic Proc Benson 11/1/96 A-56 1 Proposal to vary laser intensity Benson 10/22/96 A-57 1 What is equivalent macropulse to CEBA viewers Legg 10/15/96Action Items (pending)
P-02 1 Laser phase modulator Jordan P-04 2 Is an energy compression scheme needed? Douglas P-05 1 Devise fine-tuning procedure for buncher gradient Krafft/Kehne P-08 1,2 How do we change energy? What is the energy range? Benson P-09 2 Do we need bunching after the module Douglas P-14 1 How is the gun/laser operated? Benson P-15 Discussion on robustness of controls Legg P-18 1,2 Technote by Yunn summarizing machine impedance Yunn P-19 2 Consistent linac/bunching phase sets Yunn P-20 1 Lock plans (who in particular) Johannes? P-21 1 Save/restore plans Benesch P-25 1,2 RF control sensitivities/ Merminga Microphonics Diff for FEL/ Pathlength effect P-28 1,2 Scrapers: Where and How? Bohn, Li P-29 2 FEL/linac interaction Merminga P-30 2 Tracking including realistic wiggler fields Douglas P-32 2 Are two sextupole families enough to tune M56 Douglas P-35 1 Coordinated ITS beam running/SRF commissioning plan Legg/Bohn/Harwood P-37 1 42 MeV dump design and interlocking WisemanAgenda for Next Meeting
Item Person Responsible Time ---- ------------------ ---- * Review agenda/corrections to minutes Legg 5 min. * Updates to task list All 10 min. * Setup outline for injector line Douglas 20 min * New Issues ALL 10 min * Agenda for next meeting All 5 min.