TITLE

ES&H Manual

 

DOCUMENT ID

6141 Material Handling Equipment:

Rigging, Cranes, and Hoists

 

1.0           Purpose

This document defines the training, procurement, inspection, and maintenance requirements for rigging, cranes, and hoists used on behalf of TJNAF. These requirements are in addition to those outlined in Chapter 6140, Material Handling Equipment Program.

TJNAF bases these requirements on those contained in DOE-STD-1090: Hoisting and Rigging Standard (Formerly Hoisting and Rigging Manual) and Chapter 2410, Appendix T1: Hazard Issues List.

2.0           Scope

This chapter and its appendices apply to the operation and use of overhead and mobile cranes, hoists, and rigging hardware operated by employees or subcontractors. 

 

Items of note

-       Work involving the use of mobile cranes often includes a forklift and forklift attachment(s). Refer to Chapter 6145, Material Handling – Forklifts and Attachments for related requirements.

-       The movement of hazardous waste using a crane and/or hoist must be accomplished under supervision of the TJNAF Hazardous Waste Coordinator (HWC).

 

Required Material Handling Training by Job Classification

Course

Wire Rope Inspector

Crane Operator

Master Rigger

Wire Rope Inspection

SAF304

X

X

X

Overhead Crane Operator

SAF403

 

X

X

ITI Master Rigger

SAF702M

 

 

X

Medical Monitoring for Hazardous Work

MED01

 

X*

X

* per Chapter 6800, Appendix T1: Medical Monitoring

3.0           Responsibilities

Note:   Management authority may be delegated to a task-qualified TJNAF employee at the discretion of the responsible manager.

3.1            Material Handling Manager (MHM)

·       Authorizes repairs and maintenance requirements for cranes and hoists.

·       Oversees annual inspection of hoisting equipment and operator training for overhead cranes and hoists.

 

3.2            Supervisors and Technical Representatives (TR)

·       Act as the “Management Representative” and designate a competent and qualified employee (e.g., Lift Director/Person –in –Charge) for the task.

·       Use DOE-STD 1090: Hoisting and Rigging Standard to determine lift category or consult the MHM.

 

TRs also:

·       Direct the subcontractor to submit a Material Handling Lift Plan two or more days before a planned crane or other lift by a machine involving a suspended load. Ensure the equipment operator and rigger qualifications are included in the Lift Plan. Refer to Chapter 6141, Appendix T4: Hoisting and Rigging Operations for planning the lift.

·       Monitor the performance of subcontractor’s crane/hoist operations and notify MHM of any concerns.

 

3.3            Qualified Crane and Hoist Operators — includes anyone approved to use a crane, hoist, or associated equipment for the benefit of Jefferson Lab

·       Complete classroom and practical training (Crane Operator Certification or equivalent as determined by the MHM).

·       Perform inspection of crane/hoist and associated equipment before use in accordance with 6141, Appendix T1: Inspection Procedures for Rigging, Cranes, and Hoists.

 

3.4            Occupational Medicine

Evaluate potential operators to ensure they are physical and visual fit to safely operate cranes and hoists. Refer to ES&H Manual Chapter 6800, Appendix T1: Medical Monitoring.

4.0           Technical Appendices

4.1            Appendix T1: Overhead Crane & Hoist Operators, Riggers and Signalers Training Requirements

·       Crane and/or hoist operators are appointed by their supervisor or TR with approval by the MHM.

·       Qualified operators are trained in the proper operation of equipment they’ll be using and subsequently approved for such by the MHM.

·       Steps to become a qualified crane operator are included.

4.2            Appendix T2: Procurement Requirements - Overhead & Mobile Cranes, Hoists, and Rigging

Information regarding the purchase or lease of overhead and mobile cranes, hoists & rigging; contracted equipment; and, associated subcontracted services, over and above those for material handling equipment, are provided therein.

4.3            Appendix T3: Inspection Procedures for Overhead & Mobile Cranes, Hoists, and Rigging

Procedures for routine inspection and regular maintenance of overhead cranes, hoists, and rigging used on behalf of TJNAF are delineated in T3.  These are based on Occupational Safety and Health Administration (OSHA) and the American Society of Mechanical Engineers national consensus standards. Use a Wire Rope Inspection Report Form to record the findings of such inspections.

4.4            Appendix T4: Operating Hoisting and Rigging Equipment (including a lift plan)

Overhead or mobile crane operations at Jefferson Lab are accomplished in accordance with DOE-STD-1090: Hoisting and Rigging Standard.  When subcontracted crane services are utilized, a Material Handling Lift Plan must be submitted to the MHM for approval before any lift involving a mobile crane. A Material Handling Lift Plan must be completed for any suspended load lifted by other machines. A Lift Plan is also required for any critical lifts using a crane or forklift.

All lifts require solid planning! Developing and documenting a lift plan is recommended for all lifts; however, documentation is not required for lifts classified as Ordinary.

A Lift Plan should be used for non-routine lifts using overhead cranes, or incorporated into a Temporary Operational Safety Procedure. Appendix T4 provides the steps necessary to ensure safe operations of this equipment. The approved lift planning process is accessible via the Jefferson Lab Lift Plan Form. It is important to note that the MHM has the authority to accept Lift Plans in other formats from subcontracted material handling service companies.

 

Note: A lift plan is required whenever a forklift is used to suspend a load under the “Forks”

 

4.5            Appendix T6:  Below-the-Hook Lifting Devices

At Jefferson Lab below-the-hook lifting devices (BTHLD) are designed, built, and purchased to perform specific functions.  This appendix outlines the requirements for the design, production, use, and modification of BTHLDs.

5.0           References

·       29 CFR 1910.179, Overhead and gantry cranes

·       29 CFR 1910.180, Crawler locomotives and truck cranes

·       29 CFR 1910.184, Slings

·       29 CFR 1926.251, Rigging equipment for material handling

·       29 CFR 1926, Subpart CC – Cranes and Derricks in Construction

·       ASME B30.5 Mobile Crane Operations Responsibilities

·       DOE-STD-1090-2020, Hoisting and Rigging Standard

6.0           Revision History

 rev

summary

date

1.8

updated

-  outdated hyperlinks;

-  Note in section 3.0

-  section 4.0 title, wording, and the overall format

revised

- training table in section 2.0

- header and footer formats

general editorial updates, including

- removing verbiage; fixing bullets & the use of acronyms and abbreviations

- format of this section, changing the title to Revision History and making the summary into tabular format

no approval necessary

03.30.2022

1.7

periodic review; updated header and footer, changed SOTR to TR, no new approval needed.

03.25.2021

1.6

updated TPOC from B.Sperlazza to M.Loewus

01.24.2018

1.5

updated TPOC from D.Kausch to B.Sperlazza per B.Sperlazza

02.09.2017

1.4

eliminated two positions previously identified as the MHSR and the MHER, the responsibilities of these positions are now performed by the MHM; revised 3.2.1 to clearly state the intent of the previous poorly worded paragraph; added the requirement to use a Lift Plan for any load suspended by a machine other than a crane

12.17.2015

1.3

periodic review; minor edits; no substantive changes

12.04.2014

1.2

added Required Safety Training table

05.20.2014

1.1

update to format and web links only

03.22.2012

1.0

updated to reflect current laboratory operations

04.12.2010

 

 

 

ISSUING AUTHORITY

TECHNICAL POINT-OF-CONTACT

APPROVAL DATE

REVIEW DATE

REVIEW CYCLE

rev

 

 

ES&H Division

Mark Loewus

01.24.2018

03.30.2022

3 years

1.8

 

This document is controlled as an online file.  It may be printed but the print copy is not a controlled document. 

It is the user’s responsibility to ensure that the document is the same revision as the current online file.  This copy was printed on 1/27/2023.