DT # Description Date Recipient
D1008 Scintillator Load Test. 09/01/2005 P. Brindza
D1096 Gluex detector prototype flatness. 02/13/2007 D. Carman, S. Taylor, B. Kross
D1177 Sag check on Pb barrel colorimeter 07/31/2008 Tim Whitlatch
D1204 Hall D GlueX detector profiler. 12/08/2008 W. Crahen, B. Kross, M. Stevens
D1245 Check on slab elevation and control on Hall D site 10/13/2009 R.Yasky, T.Frye, T.Witherspoon, S.Chandra, T.Whitlatch
D1246 Hall D solenoid coil inspections. 10/21/2009 T. Carstens, F. Martin
D1253 Check on Hall D slab elevation 12/09/2009 R.Yasky, T.Frye, T.Witherspoon
D1267 Check on photon control on Hall D site 03/09/2010 R.Yasky, T.Frye, T.Witherspoon, T.Whitlatch
D1281 Check on photon beampipe. 04/30/2010 R.Yasky, T.Frye, T.Witherspoon, T.Whitlatch
D1285 Check on Tunnel Extension mud slab elevation 05/14/2010 C. Bitgood, T. Witherspoon, T. Whitlatch, R. Yasky
D1294 Check on cyropipe penetrations 06/29/2010 R.Yasky, T.Witherspoon, T.Whitlatch
D1297 Check on solenoid pier plates 07/06/2010 R.Yasky, T.Witherspoon, T.Whitlatch
D1304 Second check on solenoid pier plates 07/15/2010 R.Yasky, T.Witherspoon, T.Whitlatch
D1310 Third check on solenoid pier plates 08/17/2010 R.Yasky, C. Bitgood, T.Witherspoon, T.Whitlatch
D1311 Check on Tunnel Extension / Tagger floor elevation 08/23/2010 C. Bitgood, T. Witherspoon, T. Whitlatch, R. Yasky
D1312 Check on Tunnel Extension / Tagger walls 08/23/2010 C. Bitgood, T. Witherspoon, T. Whitlatch, R. Yasky
D1314 Fourth check on solenoid pier plates 08/26/2010 R.Yasky, C. Bitgood, T.Witherspoon, T.Whitlatch
D1337 Final solenoid pier survey after concrete. 10/29/2010 R.Yasky, C. Bitgood, T.Witherspoon, T.Whitlatch
D1347 Check on Hall D collimator area walls and floor 11/16/2010 R.Yasky, C. Bitgood, T.Witherspoon, T.Whitlatch
D1348 Check on Hall D rail trenches. 11/16/2010 R.Yasky, C. Bitgood, T.Witherspoon, T.Whitlatch
D1380 Check on Tagger photon beampipe 02/17/2011 R.Yasky, C. Bitgood, T.Witherspoon
D1381 Check on Hall D photon beampipe 02/22/2011 R.Yasky, C. Bitgood, T.Witherspoon
D1382 Second Check on Tagger photon beampipe 03/04/2011 R.Yasky, C. Bitgood, T.Witherspoon
D1383 Third check on Tagger photon beampipe (after concrete) 03/17/2011 R.Yasky, C. Bitgood, T.Witherspoon
D1392 Check on Hall D photon beampipe 04/18/2011 R.Yasky, C. Bitgood, T.Witherspoon, T. Whitlatch