SNS Data Transmittals
----------------------

DT # Description Date Recipient
Z716 SNS Cryo. vacuum vessel 11/06/2001 Brian Carpenter, Tim Whitlatch
Z717 12Gev Cryo. spaceframe 11/06/2001 Brian Carpenter, Tim Whitlatch
Z723 12 Gev Space Frame re-inspection 12/18/2001 Whitlach, Carpenter
Z724 SNS 0.61 Beta space frame inspection 12/18/2001 Whitlach, Carpenter
Z731 SNS cavity transport rail inspection. 01/14/2002 Brian Carpenter, Tim Whitlach
Z735 12 Gev cryomodule supply end cap 1&2 QC 01/29/2002 T. Whitlach, B. Carpenter
Z737 Inspection of SNS Vacuum Vessel 01 02/04/2002 Tim Whitlatch and Brian Carpenter
Z738 12 Gev cryomodule retun end cap 1&2 QC 02/06/2002 T. Whitlach, B. Carpenter
Z741 Inspection of SNS Vacuum Vessel  01 rail location at wheel placement 02/22/2002 Tim Whitlatch and Brian Carpenter
Z742 SNS 0.61 Beta space frame inspection 02/22/2002 Whitlach, Carpenter
Z743 SNS cryomodule supply end cap 01 QC 02/22/2002 T. Whitlach, B. Carpenter
Z744 SNS 0.61 Beta space frame inspection 02/28/2002 Whitlach, Daly
Z747 SNS cryomodule return end can 01 QC 03/13/2002 E. Daly, B. Carpenter
Z755 12Gev Space Frame 2 re-inspection 04/09/2002 Tim Whitlatch, Brian Carpenter
Z767 Inspection of SNS Vacuum  Vessel 02 05/09/2002 Tim Whitlatch and Brian Carpenter
Z777 SNS cryomodule return end  cap 02 QC 05/30/2002 E. Daly, B. Carpenter
Z778 SNS cryomodule supply end  cap 02 QC 05/30/2002 E. Daly, B. Carpenter
Z784 SNS cryomodule supply end cap #3. 06/07/2002 Ed Daly,Brian Carpenter
Z785 SNS cryomodule return end cap #3. 06/07/2002 Ed Daly,Brian Carpenter
Z792 12 GeV lollipop inspection 07/15/2002 K. Macha, J. Fischer
Z793 Inspection of SNS Space frame 02 07/16/2002 Tim Whitlatch and Brian Carpenter
Z795 SNS cryomodule return end  cap 05 07/23/2002 Ed Daly,Brian Carpenter
Z796 SNS cryomodule supply end  cap 04 07/23/2002 Ed Daly,Brian Carpenter
Z803 Inspection of SNS supply and return end cans 2-7 with bayonets controlling roll 08/26/2002 E.Daly, J.Preble, B. Carpenter
Z806 Inspection of SNS Space frame 03 08/29/2002 Tim Whitlatch and Brian Carpenter
Z808 Inspection of SNS supply and  return end cans 8 and 9. 09/11/2002 E. Daly, B. Carpenter
Z809 SNS Bridging rings 8, 13, 15, and 19 09/12/2002 E. Daly, B. Carpenter
Z813 Inspection of SNS Space frame 04 09/20/2002 Tim Whitlatch and Brian Carpenter
Z814 Inspection of SNS Vacuum   Vessel 03 09/23/2002 Tim Whitlatch and Brian Carpenter
Z819 SNS Spaceframe 2 re-inspection 10/03/2002 Tim Whitlatch and Brian Carpenter
Z821 Inspection of SNS Vacuum   Vessel 04 10/21/2002 Tim Whitlatch and Brian Carpenter
Z825 Inspection of SNS Space  frame 05 10/31/2002 Tim Whitlatch and Brian Carpenter
Z827 SNS cryomodule supply end   cap 07 after re-manufactured 11/01/2002 Ed Daly,Brian Carpenter
Z829 Supply end   cap 05 after re-manufactured 11/26/2002 Ed Daly,Brian Carpenter
Z830 SNS cryomodule return end   cap 06 after re-manifactured 11/26/2002 Ed Daly,Brian Carpenter
Z834 SNS cryomodule return end    cap 10 01/08/2003 Ed Daly,Brian Carpenter
Z835 Inspection of SNS Vacuum    Vessel 06 01/09/2003 Tim Whitlatch and Brian Carpenter
Z836 Inspection of SNS Vacuum    Vessel 06 01/09/2003 Tim Whitlatch and Brian Carpenter
Z855 Inspection of SNS Vacuum     Vessel hi beta 01 04/10/2003 Tim Whitlatch and Brian Carpenter
Z861 (Revision)Inspection High Beta space frame 01 SNS 05/01/2003 Tim Whitlatch and Brian Carpenter
Z862 Inspection of SNS Vacuum    Vessel 09 05/07/2003 Tim Whitlatch and Brian Carpenter
Z867 SNS Hi Beta Module 1 Flange movement 06/03/2003 Joe Preble, Frank Humphrey
Z869 SNS cryomodule return end     cap 05 re-inspection 06/16/2003 Ed Daly,Brian Carpenter
Z871 Supply end   cap 05 after re-manufactured 06/16/2003 Ed Daly,Brian Carpenter
Z872 SNS cryomodule return end    cap 10 06/16/2003 Ed Daly,Brian Carpenter
Z875 SNS HB SpaceFrame 02 07/02/2003 Tim Whitlatch, Brian Carpenter
Z883 SNS mb space frame 08 08/04/2003 Tim Whitlatch and Brian Carpenter
Z891 SNS MB04/05 arm survey 09/03/2003 J. Hogan, T. Whitlach, M. Wiseman
Z899 SNS MB06 arm survey 09/30/2003 J. Hogan, T. Whitlach, M. Wiseman
Z901 Cryomodule Assembly room pier distances 10/02/2003 J. Preble, J. Hogan
Z902 SNS offset fixture inspection 10/10/2003 J. Preble, B. Carpenter
Z912 SNS MB07 arm survey 12/15/2003 J. Preble, J. Hogan, J. Fischer, T. Whitlach
Z915 SNS HB space frame 07 inspection 01/13/2004 T. Whitlach, B. Carpenter
Z920 SNS HB vacuum vessel 07 inspection 03/18/2004 T. Whitlach, B. Carpenter
Z927 SNS HB space frame 12 inspection 05/06/2004 T. Whitlach, B. Carpenter
Z931 SNS HB vacuum vessel 04 inspection 05/27/2004 T. Whitlach, B. Carpenter