2000 September Accelerator Schedule

As Published October 20, 1999

Date Weekday Accelerator Hall A Hall A Hall B Hall B Hall C Hall C Priority Notes
    GeV/pass/Pol Experiment GeV/mA Experiment GeV/nA Experiment GeV/mA Hall 1-5
09/01/00 Friday Down Maintenance eg1 installation Gen Install  
09/02/00 Saturday Down Maintenance eg1 installation Gen Install  
09/03/00 Sunday Down Maintenance eg1 installation Gen Install  
09/04/00 Monday Down Maintenance eg1 installation Gen Install  
09/05/00 Tuesday Restore Maintenance eg1 installation Gen Install  
09/06/00 Wednesday Restore Maintenance eg1 installation Gen Install  
09/07/00 Thursday Restore Maintenance eg1 installation Gen Install  
09/08/00 Friday 0.780/High Maintenance Commission 1.604/5/p Commission 0.824/50/p B 15
09/09/00 Saturday 0.780/High Maintenance Commission 1.604/5/p Commission 0.824/50/p C  
09/10/00 Sunday 0.780/High Maintenance eg1 1.604/5/p Commission 0.824/50/p B  
09/11/00 Monday 0.780/High Maintenance eg1 1.604/5/p Commission 0.824/50/p C  
09/12/00 Tuesday 0.780/High Maintenance eg1 1.604/5/p Commission 0.824/50/p B  
09/13/00 Wednesday 0.780/High Maintenance eg1 1.604/5/p Commission 0.824/50/p C  
09/14/00 Thursday 0.780/High Maintenance eg1 1.604/5/p Commission 0.824/50/p B  
09/15/00 Friday 0.780/High Maintenance eg1 1.604/5/p E93-038 0.824/50/p C  
09/16/00 Saturday 0.780/High Maintenance eg1 1.604/5/p E93-038 0.824/50/p C  
09/17/00 Sunday 0.780/High Maintenance eg1 1.604/5/p E93-038 0.824/50/p C  
09/18/00 Monday 0.780/High Maintenance eg1 1.604/5/p E93-038 0.824/50/p C  
09/19/00 Tuesday 0.780/High Maintenance eg1 1.604/5/p E93-038 0.824/50/p C  
09/20/00 Wednesday 0.780/High Maintenance eg1 1.604/5/p E93-038 0.824/50/p C  
09/21/00 Thursday 0.780/High Maintenance eg1 1.604/5/p E93-038 0.824/50/p C  
09/22/00 Friday 0.780/High Maintenance eg1 1.604/5/p E93-038 0.824/50/p C  
09/23/00 Saturday 0.780/High Maintenance eg1 1.604/5/p E93-038 0.824/50/p C  
09/24/00 Sunday 0.780/High Maintenance eg1 1.604/5/p E93-038 0.824/50/p C  
09/25/00 Monday Development Maintenance Maintenance Maintenance  
09/26/00 Tuesday Maintenance Maintenance Maintenance Maintenance  
09/27/00 Wednesday Maintenance Maintenance Maintenance Maintenance  
09/28/00 Thursday Restore Maintenance Maintenance Maintenance  
09/29/00 Friday 0.780/High commission 2.384/100 eg1 1.604/5/p E93-038 0.824/50/p A/B/C  
09/30/00 Saturday 0.780/High commission 2.384/100 eg1 1.604/5/p E93-038 0.824/50/p A/B/C  

Continue to October 2000