Previous 1997 Accelerator Schedule (January-June)

As published 2/11/97


Date Weekday Accelerator Hall A
Experiment
Hall A
Energy
Hall B
Experiment
Hall B
Energy
Hall C
Experiment
Hall C
Energy
1/6/97 Monday Down Install - Install - Install T20 -
1/7/97 Tuesday Down Install - Install - Install T20 -
1/8/97 Wednesday Down Install - Install - Install T20 -
1/9/97 Thursday Down Install - Install - Install T20 -
1/10/97 Friday Down Install - Install - Install T20 -
1/11/97 Saturday Down Install - Install - Install T20 -
1/12/97 Sunday Down Install - Install - Install T20 -
1/13/97 Monday Down Install - Install - Install T20 -
1/14/97 Tuesday Down Install - Install - Install T20 -
1/15/97 Wednesday Down Install - Install - Install T20 -
1/16/97 Thursday Down Install - Install - Install T20 -
1/17/97 Friday Down Install - Install - Install T20 -
1/18/97 Saturday Down Install - Install - Install T20 -
1/19/97 Sunday Down Install - Install - Install T20 -
1/20/97 Monday Down Install - Install - Install T20 -
1/21/97 Tuesday Down Install - Install - Install T20 -
1/22/97 Wednesday Down Install - Install - Install T20 -
1/23/97 Thursday Down Install - Install - Install T20 -
1/24/97 Friday Down Install - Install - Install T20 -
1/25/97 Saturday Down Install - Install - Install T20 -
1/26/97 Sunday Down Install - Install - Install T20 -
1/27/97 Monday Down Install - Install - Install T20 -
1/28/97 Tuesday Down Install - Install - Install T20 -
1/29/97 Wednesday Down Install - Install - Install T20 -
1/30/97 Thursday Down Install - Install - Install T20 -
1/31/97 Friday Down Install - Install - Install T20 -
2/1/97 Saturday Down Install - Install - Install T20 -
2/2/97 Sunday Down Install - Install - Install T20 -
2/3/97 Monday Down Install - Install - Install T20 -
2/4/97 Tuesday Down Install - Install - Install T20 -
2/5/97 Wednesday Down Install - Install - Install T20 -
2/6/97 Thursday Down Install - Install - Install T20 -
2/7/97 Friday Down Install - Install - Install T20 -
2/8/97 Saturday Development Install - Install - Install T20 -
2/9/97 Sunday Development Install - Install - Install T20 -
2/10/97 Monday Development Install - Install - Install T20 -
2/11/97 Tuesday Development Install - Install - Install T20 -
2/12/97 Wednesday Development Install - Install - Install T20 -
2/13/97 Thursday Development Install - Install - Install T20 -
2/14/97 Friday Development Commission - Install - Install T20 -
2/15/97 Saturday Restore Commission - Install - Install T20 -
2/16/97 Sunday Restore Commission - Install - Install T20 -
2/17/97 Monday Restore Install - Install - Install T20 -
2/18/97 Tuesday Restore Install - Install - Install T20 -
2/19/97 Wednesday Restore Install - Install - Install T20 -
2/20/97 Thursday Up Commission 0.8 GeV Commission 2.4 GeV Install T20 4 GeV BSY
2/21/97 Friday Up Commission 0.8 GeV Commission 2.4 GeV Install T20 4 GeV BSY
2/22/97 Saturday Up Commission 0.8 GeV Commission 2.4 GeV Install T20 4 GeV BSY
2/23/97 Sunday Up Commission 0.8 GeV Commission 2.4 GeV Install T20 4 GeV BSY
2/24/97 Monday Up Install - Commission 2.4 GeV Install T20 4 GeV BSY
2/25/97 Tuesday Up Install - Commission 4.0 GeV Install T20 4 GeV BSY
2/26/97 Wednesday Up Install - Commission 4.0 GeV Install T20 4 GeV BSY
2/27/97 Thursday Up Commission 0.8 GeV Commission 4.0 GeV Install T20 4 GeV BSY
2/28/97 Friday Up Commission 0.8 GeV Commission 4.0 GeV Install T20 4 GeV BSY
3/1/97 Saturday Up Commission 0.8 GeV Commission 4.0 GeV Install T20 4 GeV BSY
3/2/97 Sunday Up Commission 0.8 GeV Commission 4.0 GeV Install T20 4 GeV BSY
3/3/97 Monday Development Install - Install - Install T20 -
3/4/97 Tuesday Maintenance Install - Install - Install T20 -
3/5/97 Wednesday Development Install - Install - Install T20 -
3/6/97 Thursday Up Commission 2.4 GeV Install - Install T20 -
3/7/97 Friday Up Commission 2.4 GeV Install - Install T20 -
3/8/97 Saturday Up Commission 2.4 GeV Install - Install T20 -
3/9/97 Sunday Up Commission 2.4 GeV Install - Install T20 -
3/10/97 Monday Up Commission 2.4 GeV Install - Install T20 -
3/11/97 Tuesday Development Install - Install - Install T20 -
3/12/97 Wednesday Development Install - Install - Install T20 -
3/13/97 Thursday Up FPP tests 2.4 GeV Install - Install T20 -
3/14/97 Friday Up FPP tests 2.4 GeV Install - Install T20 -
3/15/97 Saturday Up FPP tests 2.4 GeV Install - Install T20 -
3/16/97 Sunday Up FPP tests 2.4 GeV Install - Install T20 -
3/17/97 Monday Up FPP tests 2.4 GeV Install - Install T20 -
3/18/97 Tuesday Maintenance Maintenance - Install - Install T20 -
3/19/97 Wednesday Development Maintenance - Install - Install T20 -
3/20/97 Thursday Up Commission 2.4 GeV Install - Install T20 -
3/21/97 Friday Up Commission 2.4 GeV Install - Install T20 -
3/22/97 Saturday Up Commission 2.4 GeV Install - Install T20 -
3/23/97 Sunday Up Commission 2.4 GeV Install - Install T20 -
3/24/97 Monday Up Commission 2.4 GeV Install - Install T20 -
3/25/97 Tuesday Development Install - Install - Install T20 -
3/26/97 Wednesday Development Install - Install - Install T20 -
3/27/97 Thursday Polarization FPP tests 2.4 GeV Install - Install T20 -
3/28/97 Friday Polarization FPP tests 2.4 GeV Install - Install T20 -
3/29/97 Saturday Polarization FPP tests 2.4 GeV Install - Install T20 -
3/30/97 Sunday Polarization FPP tests 2.4 GeV Install - Install T20 -
3/31/97 Monday Polarization FPP tests 2.4 GeV Install - Install T20 -
4/1/97 Tuesday Maintenance Install - Maintenance - Install T20 -
4/2/97 Wednesday Development Install - Maintenance - Polarization 0.8 GeV
4/3/97 Thursday Up Install - Commission 1.6 GeV Commission 3.2 GeV
4/4/97 Friday Up Install - Commission 1.6 GeV Commission 3.2 GeV
4/5/97 Saturday Up Install - Commission 1.6 GeV Commission 3.2 GeV
4/6/97 Sunday Up Install - Commission 1.6 GeV Commission 3.2 GeV
4/7/97 Monday Up Install - Commission 1.6 GeV Commission 3.2 GeV
4/8/97 Tuesday Up Install - Commission 4.0 GeV* Commission 1.6 GeV
4/9/97 Wednesday Up Install - Commission 4.0 GeV* Commission 1.6 GeV
4/10/97 Thursday Up Install - Commission 4.0 GeV* Commission 1.6 GeV
4/11/97 Friday Up Install - Commission 4.0 GeV* Commission 1.6 GeV
4/12/97 Saturday Up Install - Commission 4.0 GeV* Commission 1.6 GeV
4/13/97 Sunday Up Install - Commission 4.0 GeV* Commission 1.6 GeV
4/14/97 Monday Up Install - Commission 4.0 GeV* Commission 1.6 GeV
4/15/97 Tuesday Maintenance Install - Maintenance - Maintenance -
4/16/97 Wednesday Development Install - Maintenance - Polarization 0.8 GeV
4/17/97 Thursday Up Commission 4.0 GeV Commission 2.4 GeV Kox/Beise 1.6 GeV
4/18/97 Friday Up Commission 4.0 GeV Commission 2.4 GeV Kox/Beise 1.6 GeV
4/19/97 Saturday Up Commission 4.0 GeV Commission 2.4 GeV Kox/Beise 1.6 GeV
4/20/97 Sunday Up Commission 4.0 GeV Commission 3.2 GeV Kox/Beise 1.6 GeV
4/21/97 Monday Up Commission 4.0 GeV Commission 3.2 GeV Kox/Beise 2.4 GeV
4/22/97 Tuesday Up Commission 4.0 GeV Commission 3.2 GeV Kox/Beise 2.4 GeV
4/23/97 Wednesday Up Commission 4.0 GeV Commission 4.0 GeV Kox/Beise 2.4 GeV
4/24/97 Thursday Up Commission 4.0 GeV Commission 4.0 GeV Kox/Beise 2.4 GeV
4/25/97 Friday Up Commission 4.0 GeV Commission 4.0 GeV Kox/Beise 2.4 GeV
4/26/97 Saturday Up Commission 4.0 GeV Commission 4.0 GeV Kox/Beise 2.4 GeV
4/27/97 Sunday Up Commission 4.0 GeV Commission 4.0 GeV Kox/Beise 2.4 GeV
4/28/97 Monday Up Commission 4.0 GeV Commission 4.0 GeV Kox/Beise 2.4 GeV
4/29/97 Tuesday Maintenance Install - Maintenance - Maintenance -
4/30/97 Wednesday Polarization Install - Maintenance - Polarization 0.8 GeV
5/1/97 Thursday Up Install - Install - Kox/Beise 1.4 GeV
5/2/97 Friday Up Install - Install - Kox/Beise 1.4 GeV
5/3/97 Saturday Up Install - Install - Kox/Beise 1.4 GeV
5/4/97 Sunday Up Install - Install - Kox/Beise 1.4 GeV
5/5/97 Monday Up Install - Install - Kox/Beise 1.4 GeV
5/6/97 Tuesday Up Install - Commission 3.4 GeV* Commission 2.0 GeV
5/7/97 Wednesday Up Install - Commission 3.4 GeV* Kox/Beise 2.0 GeV
5/8/97 Thursday Up Install - Commission 3.4 GeV* Kox/Beise 2.0 GeV
5/9/97 Friday Up Install - Commission 3.4 GeV* Kox/Beise 2.0 GeV
5/10/97 Saturday Up Install - Commission 3.4 GeV* Kox/Beise 2.0 GeV
5/11/97 Sunday Up Install - Commission 3.4 GeV* Kox/Beise 2.0 GeV
5/12/97 Monday Up Install - Commission 3.4 GeV* Kox/Beise 2.0 GeV
5/13/97 Tuesday Maintenance Install - Maintenance - Maintenance -
5/14/97 Wednesday Development Install - Maintenance - Polarization 3.4 GeV
5/15/97 Thursday Up Saha 0.8 GeV Commission 3.4 GeV* Kox/Beise 2.0 GeV
5/16/97 Friday Up Saha 0.8 GeV Commission 4.0 GeV* Kox/Beise 2.4 GeV
5/17/97 Saturday Up Saha 0.8 GeV Commission 4.0 GeV* Kox/Beise 2.4 GeV
5/18/97 Sunday Up Saha 0.8 GeV Commission 4.0 GeV* Kox/Beise 2.4 GeV
5/19/97 Monday Up Saha 0.8 GeV Commission 4.0 GeV* Kox/Beise 2.4 GeV
5/20/97 Tuesday Up Saha 0.8 GeV Commission 4.0 GeV* Kox/Beise 2.4 GeV
5/21/97 Wednesday Up Saha 0.8 GeV Commission 4.0 GeV* Kox/Beise 2.4 GeV
5/22/97 Thursday Up Saha 0.8 GeV Commission 4.0 GeV* Kox/Beise 2.4 GeV
5/23/97 Friday Up Saha 0.8 GeV Commission 4.0 GeV* Kox/Beise 2.4 GeV
5/24/97 Saturday Holiday Holiday Holiday Holiday Holiday Holiday Holiday
5/25/97 Sunday Holiday Holiday Holiday Holiday Holiday Holiday Holiday
5/26/97 Monday Holiday Holiday Holiday Holiday Holiday Holiday Holiday
5/27/97 Tuesday Restore Maintenance - Install - Maintenance -
5/28/97 Wednesday Restore Maintenance - Install - Maintenance -
5/29/97 Thursday Restore Maintenance - Install - Maintenance -
5/30/97 Friday Facility Facility TBD Install - Facility TBD
5/31/97 Saturday Facility Facility TBD Install - Facility TBD
6/1/97 Sunday Facility Facility TBD Install - Facility TBD
6/2/97 Monday Facility Facility TBD Facility TBD Facility TBD
6/3/97 Tuesday Facility Facility TBD Facility TBD Facility TBD
6/4/97 Wednesday Facility Facility TBD Commission 2.4 GeV Kox/Beise 3.2 GeV
6/5/97 Thursday Facility Facility TBD Commission 2.4 GeV Kox/Beise 3.2 GeV
6/6/97 Friday Up Saha 1.6 GeV Commission 2.4 GeV Kox/Beise 3.2 GeV
6/7/97 Saturday Up Saha 1.6 GeV Commission 4.0 GeV* Kox/Beise 3.2 GeV
6/8/97 Sunday Up Saha 1.6 GeV Commission 4.0 GeV* Kox/Beise 3.2 GeV
6/9/97 Monday Up Saha 1.6 GeV Commission 4.0 GeV* Kox/Beise 3.2 GeV
6/10/97 Tuesday Maintenance Maintenance - Install - Maintenance -
6/11/97 Wednesday Development Maintenance - Install - Maintenance -
6/12/97 Thursday Up Saha 2.4 GeV Install - Kox/Beise 3.2 GeV
6/13/97 Friday Up Saha 2.4 GeV Install - Kox/Beise 3.2 GeV
6/14/97 Saturday Up Saha 2.4 GeV Install - Kox/Beise 3.2 GeV
6/15/97 Sunday Up Saha 2.4 GeV Install - Kox/Beise 3.2 GeV
6/16/97 Monday Up Saha 2.4 GeV Install - Kox/Beise 3.2 GeV
6/17/97 Tuesday Up Saha 2.4 GeV Install - Kox/Beise 3.2 GeV
6/18/97 Wednesday Up Saha 2.4 GeV Commission 1.6 GeV Kox/Beise 3.2 GeV
6/19/97 Thursday Up Saha 2.4 GeV Commission 1.6 GeV Kox/Beise 3.2 GeV
6/20/97 Friday Up Saha 2.4 GeV Commission 1.6 GeV Kox/Beise 3.2 GeV
6/21/97 Saturday Up Saha 2.4 GeV Commission 1.6 GeV Kox/Beise 3.2 GeV
6/22/97 Sunday Up Saha 2.4 GeV Commission 1.6 GeV Kox/Beise 3.2 GeV
6/23/97 Monday Up Saha 2.4 GeV Commission 1.6 GeV Kox/Beise 3.2 GeV
6/24/97 Tuesday Maintenance Maintenance - Install - Maintenance -
6/25/97 Wednesday Development Maintenance - Install - Maintenance -
6/26/97 Thursday Up Saha 2.4 GeV Commission 4.0 GeV Kox/Beise 4.0 GeV
6/27/97 Friday Up Saha 2.4 GeV Commission 4.0 GeV Kox/Beise 4.0 GeV
6/28/97 Saturday Up Saha 2.4 GeV Commission 4.0 GeV Kox/Beise 4.0 GeV
6/29/97 Sunday Up Saha 2.4 GeV Commission 4.0 GeV Kox/Beise 4.0 GeV
6/30/97 Monday Polarization FPP tests - Maintenance - Polarization 0.8 GeV


* Footnote: Hall B operation during this time is contingent upon demonstrating that a witness beam is not required.