Accelerator & Experimental Schedule

March to August 1996 (as published 3/29/96; actual run schedule may have been modified)


Activity Name Start Date Finish Date
Deliver 3.2 GeV and 4 GeV, 25 microamp CW to Hall C E-89012 (R. Holt) 3/16/96 4/2/96
Maintenance, certify Hall A safety system 4/3/96 4/4/96
Deliver 4 GeV, 25 microamp CW to Hall C E-89-012 (R. Holt) 4/5/96 4/15/96
Maintenance, set up 50 microamp beam, deliver first beam to HallA, set up two beams, cryotarget work in Hall C, Moeller 4/16/96 4/23/96
Deliver 4 GeV, <=50 microamp CW to Hall C E-89-012 (R. Holt), E-91-013 (D. Geesaman) 4/24/96 4/29/96
Maintenance 4/30/96 4/30/96
Beam to Hall C E-91-013 (D. Geesaman), E-90-007 (Milner), beam available to Hall A for electron spectrometer tests 5/1/96 5/13/96
Laboratory Dedication 5/14/96 5/14/96
Memorial Day Holiday 5/25/96 5/27/96
Machine shutdown - A line aluminum vacuum chamber, Moeller polarimeter, install B line, service Hall C cryotarget 5/28/96 7/3/96
Independence Day Holiday 7/4/96 7/7/96
Hot checkout, establish reliable two beam operation, commission Moeller, set up polarized beam to Hall C (nights) 7/8/96 7/15/96
Beam Hall C E-89-008 (Filippone), 4 GeV, >=50 microamp CW, Hall A commissioning 7/16/96 7/30/96
Maintenance, machine development 7/31/96 8/1/96
Beam to hall C E-89-008 (Filippone), 4GeV, >=50 microamp CW, Hall A commissioning 8/2/96 8/9/96
Checkout Hall C (Zeidman, Baker), Hall A commissioning, maintenance 8/10/96 8/12/96
Beam to Hall C E-91-016 (Zeidman), Hall A commissioning 8/13/96 8/30/96
Labor Day Holiday 8/31/96 9/3/96