Activity Name | Start Date | Finish Date |
Deliver 3.2 GeV and 4 GeV, 25 microamp CW to Hall C E-89012 (R. Holt) | 3/16/96 | 4/2/96 |
Maintenance, certify Hall A safety system | 4/3/96 | 4/4/96 |
Deliver 4 GeV, 25 microamp CW to Hall C E-89-012 (R. Holt) | 4/5/96 | 4/15/96 |
Maintenance, set up 50 microamp beam, deliver first beam to HallA, set up two beams, cryotarget work in Hall C, Moeller | 4/16/96 | 4/23/96 |
Deliver 4 GeV, <=50 microamp CW to Hall C E-89-012 (R. Holt), E-91-013 (D. Geesaman) | 4/24/96 | 4/29/96 |
Maintenance | 4/30/96 | 4/30/96 |
Beam to Hall C E-91-013 (D. Geesaman), E-90-007 (Milner), beam available to Hall A for electron spectrometer tests | 5/1/96 | 5/13/96 |
Laboratory Dedication | 5/14/96 | 5/14/96 |
Memorial Day Holiday | 5/25/96 | 5/27/96 |
Machine shutdown - A line aluminum vacuum chamber, Moeller polarimeter, install B line, service Hall C cryotarget | 5/28/96 | 7/3/96 |
Independence Day Holiday | 7/4/96 | 7/7/96 |
Hot checkout, establish reliable two beam operation, commission Moeller, set up polarized beam to Hall C (nights) | 7/8/96 | 7/15/96 |
Beam Hall C E-89-008 (Filippone), 4 GeV, >=50 microamp CW, Hall A commissioning | 7/16/96 | 7/30/96 |
Maintenance, machine development | 7/31/96 | 8/1/96 |
Beam to hall C E-89-008 (Filippone), 4GeV, >=50 microamp CW, Hall A commissioning | 8/2/96 | 8/9/96 |
Checkout Hall C (Zeidman, Baker), Hall A commissioning, maintenance | 8/10/96 | 8/12/96 |
Beam to Hall C E-91-016 (Zeidman), Hall A commissioning | 8/13/96 | 8/30/96 |
Labor Day Holiday | 8/31/96 | 9/3/96 |