Weekly Meeting Minutes - May 16, 2003
Attending: Dave L., Itaru, Ashot, Raphael, Yar, Mark, Dustin, Anatoly, Rafael, Doug, Sasha, Mabub, Marianna, Aleg
On Phone: Liping, Sam, Rory, Dan
Announcements:
Tech review tentatively scheduled for late August / early September
Chemical storage cabinet will be available in the Test Lab. Acetone and other chemicals should be moved there next week.
Engineering:
Doug: Crossbeam piece is in the hall and will be aligned next week.
Foam padding tested and ordered.
Cable assembly setup moved to behind hall, 2 of 54 bundles done.
Has office space for 2-3 students but only 1 computer.
Setup/Development:
Raphael: Crystal assemblies are finished except for the 130 that need to be re-worked.
Wrapping test results and discussion.
Lead glass: 370 assemblies done, minor problems dealt with.
Anatoly: One of the ten needed PC board assembly shown. The parts are in the EEL building, and the job is open for volunteers.
Yar: Linearity tests in progress.
Discussion of temperature monitoring and priorities.
Dave working on Test Lab DAQ.
Rory: Discussion on veto counter & wrapping materials.
Dan: Presentation on alternative analysis.