Weekly Meeting Minutes - October 24, 2003
Attending: Ashot, DaveK, Mark, Dustin, Dan, Itaru, Raphael, Phil, Abdellah, Eric, Aram, Yar
Phone: Sam, Dan Sober
Engineering:
Installed boom crane in hall & test loaded it. Lifter load-test sometime next month.
TSOP for HyCal load-test submitted.
Tilt sensors ordered.
Back doors done & being mounted.
Water & temp sensor feed-through plates ordered..
PrimEx deck lights done, rack supports & electrics done next week.
HyCal:
Stacking done. Testing on optical contact finalized next month.
Abdellah: De-gaussing procedure in progress.
Norm: Presentation on beam profile monitor.
Itaru: Tagger energy calibration results.
Dustin: Discuss calibration process.
Raphael: Analysis results.