Attending: Eric, Dustin, Marvin, Raphael, DaveL, Ashot, Yar, DaveK, Itaru, Aram, Mark, Stefan, Liping
Phone: Aaron
Announcements:
DaveK: DVCS suggestion to remove HyCal from Hall B after run; discussion.
Engineering:
DaveK: Repairs & tests continue; complete late next week.
Cable support moving to test lab on Monday.
Suggestion: Move HyCal frame next to baskets; discussion.
Problem: cable arrangements in baskets; DaveL, Denny, Doug & DaveK will meet & discuss.
Hardware:
PC boards in progress; 1.5 move HV to go, 3 more dynode cable sets to go; discussion.
Yar: Temperature monitoring within 1 degree now that the light's not shining on them.
LMS: Discussion of HV channels; referred to new meeting.
DAQ:
Mark: Slow controls moving to hall. Discussion of power supply.
DaveL: Update on electronics & DAQ in test lab; progressing.
Aram: Update on analysis.
Raphael: update on analysis, clusters & resolution.
Aaron: Presentation & discussion.
Spare Parts:
DaveL: Electronics list.
Discussion of various systems & targets.